25.05.2020 No 15-1/18-1618/24750-1
BENEFICIARY STATEMENT
ANNEX 2
BENEFICIARY STATEMEN T
Improvement of the accessibility of the remote areas
in South-East Estonia and Pskov region for traditional
Title of the project
entrepreneurship and sustainable development- SME
ACCESS
Name of the legal entity Maanteeamet
applying for funding as a
beneficiary in original and Estonian Road Administration
English languages
A partnership is a relationship of substance between two or more organisations involving shared
responsibilities in undertaking the above indicated project funded by the Managing Authority of the
Estonia - Russia Cross Border Cooperation Programme (hereinafter referred to as the “Programme”).
By signing this Beneficiary Statement, the above named legal entity applying for additional funding from
the Programme as a partner (hereinafter referred to as the “organisation”) by agreeing to the principles
of good partnership practice set out below hereby declares:
1. Our organisation is not in any of the situations excluding us from participation in contracts
which are listed in Article106(1) and 107 of EURATOM (available from the following Internet
address http://eur-
lex.europa.eu/LexUriServ/LexUriServ.do?uri=OJ:L:2012:298:0001:0096:en:PDF )
2. Our organisation has read the Project Application and Application for additional financing and
understood our role in the project before the Application for additional financing was submitted
to the Managing Authority.
3. Our organisation got acquainted with the Programme, has read the Grant Contract and we
understand and accept what our obligations under the contract will be if the additional grant is
awarded. We authorise the Lead Beneficiary to sign the amendments to contract with the
Managing Authority and represent us in all dealings with the Managing Authority in the context
of the implementation of the project.
4. Our organisation has sufficient human and administrative capacity to implement activities of the
project that have been assigned to our organisation. If partner’s co-financing is foreseen in the
updated Project Application, our organisation declares it will be able to maintain sufficient
financial liquidity to implement the activities of the project. In particular our organisation will be
able to maintain sufficient financial liquidity to finance activities of the project until receipt of the
balance payment.
Teelise 4 / 10916 Tallinn / ESTONIA +372 611 9300 /
[email protected] / www.mnt.ee
5. The activities that our organisation will carry out in the project are in line with the Community
and national legislation and policies and with the rules of the Programme.
6. We are aware of our obligation to amend and sign a Partnership Agreement with the Lead
Beneficiary no later than within two months after signing the Grant Contract amendments.
7. We are aware of the Lead Beneficiary’s obligation to consult our organisation and other partners
regularly and keep us fully informed of the progress of the project.
8. We have agreed with the Lead Beneficiary that it is obliged grant us rights for using eMS
environment in order to ensure smooth project implementation including reporting.
9. We are aware that the proposals for substantial changes to the project should be agreed within
the partnership before being submitted to the Managing Authority. Where no such agreement
can be reached, the Beneficiary must clearly indicate this when submitting changes for approval
to the Managing Authority.
10. Our organisation will inform the public about the funding received from the Programme to
implement the project in compliance with Communication and Visibility Manual for EU External
Actions (available from the following Internet address:
http://ec.europa.eu/europeaid/work/visibility/index_en.htm) and Manual designed by the
ministry of the Economic development of the Russian Federation in order to insure adequate
visibility of Russian contribution to the programme
11. The project will be co-financed by the Beneficiaries from their resources or from sources other
than the European Community budget.
12. Our organisation will assume responsibility in the event of any irregularity in the expenditure
which our organisation has declared, and will repay the Managing Authority any amount unduly
paid.
13. Our organisation will keep available all documents related to the project in accordance with the
Programme requirements on the availability of documents.
14. The project activities fully or partially will not be competitive in the meaning of State Aid.
15. The total amended indicative budget of our organisation within the project amounts to EUR 1 852
991 , in the event the mentioned project is granted funding from the Programme, we hereby
declare to participate in the project and to provide minimum EUR 290 363,69 as total beneficiary
co-financing to the budget of the project. In case of change of total costs of the project, it shall
be agreed within the partnership taking into account that total minimum of requested contribution
(in percentage) shall be ensured.
Please tick, if relevant:
V our organisation is not entitled to recover any paid Value Added Tax (VAT) by whatever means,
and therefore all the expenditure related to the project to be reported will include VAT.
I have read and approved the contents of the Project Application and Application for additional financing
submitted to the Managing Authority. I undertake to comply with the principles of good partnership
practice listed above.
Name and position of the Janar Taal, Head of South Road Maintenance
signatory Department
Tartu
Location
Date of signature 22.05.2020
Signature and stamp
Signed digitally