Registrite ja Infosüsteemide Keskus · 20. aprill 2020
Sisu (failidest)
Grant Agreement number: 881605 — LRI MS Connection 2 — JUST-AG-2019/JUST-JACC-EJU-AG-2019
Amendment Reference No AMD-881605-1
EUROPEAN COMMISSION
Directorate-General for Justice and Consumers
Programme and Financial management
AMENDMENT Reference No AMD-881605-1
Grant Agreement: 881605 — LRI Member State Connection 2 – Connection of additional
Member States to the Land Registers Interconnection Platform (LRI MS Connection 2)
The parties agree to amend the Grant Agreement as follows ('Amendment'):
1. Change of Annex 1 (description of the action)
Annex 1 is changed and replaced by the Annex 1 attached to this Amendment.
2. Change of the action’s duration
The duration of the action in Article 3 of the Specific Agreement is changed to 20 months.
3. Change of the reporting periods
The reporting period is changed.
This implies the following changes to the Grant Agreement:
• The reporting periods in Article 15.2 are replaced by:
- RP1: from month 1 to month 20
All other provisions of the Grant Agreement and its Annexes remain unchanged.
This Amendment enters into force on the day of the last signature.
This Amendment takes effect on the date on which the amendment enters into force, except where a
different date has been agreed by the parties (for one or more changes).
Please inform the other members of the consortium of the Amendment.
1
Grant Agreement number: 881605 — LRI MS Connection 2 — JUST-AG-2019/JUST-JACC-EJU-AG-2019
Amendment Reference No AMD-881605-1
SIGNATURES
For the coordinator For the Commission
[--TGSMark#signature-974770267_75_210--] [--TGSMark#signature-service_75_210--]
Thomas GOTTWALD with ECAS id ngottwth signed in the Signed by Daniela BANKIER with ECAS id bankida as an
Participant Portal on 03/04/2020 at 16:53:52 (transaction id authorised representative on 08-04-2020 09:22:07
SigId-306141- (transaction id SigId-23229-
mBczxnljFygJLYfM4rSbtMuvzKPlwyb0YA9KBgK0JW9zzX gZR5RjqLUsgVMaUCSojW9YZuHlfquiZPxEwni0b5JRhHs
ThBcZ5bfMCRKzPalcP8MdAlzndCxouzxs2OnNxsh2e- p4QGNNSA5uhBVxxv8FH2h0r6I0qhIjQzcyZyl0U8q-
jpJZscgsw0Ku5x8AwUVVTm- rS0vSrmBGYCSbve62yiKLq-
h7q34tVre0NiCwEaZgN118WRjzzI0lUiowGIef3KCjB0). QRX5zx1DaVrdIcTJkIc0zZSdpuoQQSWyzX6as9O6Ooa2
Timestamp by third party at ubFBPvoB8nzHqJyIqXYgU8AKtSJma1ODeUWPcVJBIZu)
Fri Apr 03 17:54:10 CEST 2020 Wed Apr 08 09:22:11 CEST 2020
Enclosures:
Annex 1
2
EUROPEAN COMMISSION
Directorate-General for Justice and Consumers
– Programme and Financial management
ANNEX 1 (part A)
Justice Action Grant
NUMBER — 881605 — LRI MS Connection 2
Table of Contents
1.1. The project summary................................................................................................................................. 3
1.2. The list of beneficiaries..............................................................................................................................4
1.3. Workplan Tables - Detailed implementation..............................................................................................5
1.3.1. WT1 List of work packages........................................................................................................... 5
1.3.2. WT2 List of deliverables................................................................................................................ 6
1.3.3. WT3 Work package descriptions................................................................................................... 8
Work package 1........................................................................................................................... 8
Work package 2......................................................................................................................... 10
Work package 3......................................................................................................................... 13
Work package 4......................................................................................................................... 16
1.3.4. WT4 List of milestones................................................................................................................ 19
1.3.5. WT5 Critical Implementation risks and mitigation actions........................................................... 21
1.3.6 WT6 Summary of project effort in person-months........................................................................23
1.3.7. WT7 Tentative schedule of project reviews.................................................................................24
1.1. The project summary
Project Number 1 881605 Project Acronym 2 LRI MS Connection 2
One form per project
General information
LRI Member State Connection 2 – Connection of additional Member States to the Land
Project title 3
Registers Interconnection Platform
Starting date 4 01/03/2020
Duration in months 5 20
Call (part) identifier 6 JUST-JACC-EJU-AG-2019
JUST-JACC-EJU-AG-2019
Topic
Call for proposals for action grants to support national or transnational e-Justice projects
Fixed EC Keywords
Land Register Interconnection, cross-border search, property data, real estate, e-Justice
Free keywords
Portal
Abstract 7
The European Commission has developed the central Land Registers Interconnection Platform (LRI) at the e-Justice
Portal (https://e-justice.europa.eu) in order to provide access to property-related information of the EU Member
States in an easier and more effective manner. The LRI offers a single multi-language user-interface for connecting
the national land registers of different Member States to the central LRI. In May 2019 as the first piloting countries
Austria and Estonia successfully interconnected their national land registers to the LRI platform under the project
“LRI MS Connection” (Grant Agreement No. 785840).
The project relies on the results achieved by the project LRI MS Connection. The project expands the circle of
Member States which will take the next steps towards the interconnection of their national land registers to the LRI
platform. Within the project Latvia will connect their land register to the LRI. Furthermore three more countries
– Hungary, Portugal and Spain – will undertake thorough analysis for gaining a full understanding of the country-
specific conditions to be met before launching the development of the national LRI connection.
Moreover, the project will provide a greater understanding of the issues and possibilities arising from the increasing
number of interconnected national land registers, and a systematic understanding of the possibilities to establish a
standardised connection between the varieties of different land register information systems across the European
Union, which will help to consolidate the LRI MS Connection project results.
The project provides all deliverables in electronic form and in English.
The project meetings and workshops will be non-tangible deliverables.
The number of deliverables per work package are as follows: WP1: 3; WP2: 3; WP3: 4; WP4: 4.
Page 3 of 24
1.2. List of Beneficiaries
Project Number 1 881605 Project Acronym 2 LRI MS Connection 2
List of Beneficiaries
Project Project exit
No Name Short name Country
entry date8 date
BUNDESMINISTERIUM FUER
1 AT BMJ Austria
JUSTIZ
REGISTRITE JA INFOSUSTEEMIDE
2 EE RIK Estonia
KESKUS
COLEGIO DE REGISTRADORES DE
3 LA PROPIEDAD Y MERCANTILES ES REG Spain
DE ESPANA
4 MINISZTERELNÖKSÉG HU PMO Hungary
5 TIESU ADMINISTRACIJA LV CA Latvia
INSTITUTO DOS REGISTOS E DO
6 IRN IP Portugal
NOTARIADO IP
Page 4 of 24
1.3. Workplan Tables - Detailed implementation
1.3.1. WT1 List of work packages
WP Person- Start End
WP Title Lead beneficiary10
Number9 months11 month12 month13
WP1 Project management & coordination 1 - AT BMJ 13.36 1 20
Business Analysis, Solution Design
WP2 and Consolidation for LRI Requests/ 3 - ES REG 39.20 1 18
Responses
Consolidation, Development,
Test and Deployment of national
WP3 5 - LV CA 4.28 8 20
components for LRI Requests/
Responses
Publicity and Dissemination of
WP4 2 - EE RIK 5.29 1 20
Deliverables
Total 62.13
Page 5 of 24
1.3.2. WT2 list of deliverables
Due
Deliverable WP Dissemination
Deliverable Title Lead beneficiary Type15 Date (in
Number14 number9 level16
months)17
Confidential,
only for members
Project, Risk and QA of the consortium
D1.1 WP1 1 - AT BMJ Report 2
Plan (including the
Commission
Services)
Confidential,
only for members
of the consortium
D1.2 Kick Off Meeting WP1 1 - AT BMJ Report 2
(including the
Commission
Services)
Confidential,
only for members
of the consortium
D1.3 Closing Meeting WP1 1 - AT BMJ Report 20
(including the
Commission
Services)
Confidential,
only for members
Workshop Knowledge
of the consortium
D2.1 Transfer &“Kick-Off WP2 2 - EE RIK Report 8
(including the
Consolidation”
Commission
Services)
Confidential,
only for members
Updated Analysis and of the consortium
D2.2 WP2 5 - LV CA Report 16
Design document (including the
Commission
Services)
Confidential,
only for members
Workshop of the consortium
D2.3 WP2 1 - AT BMJ Report 14
Consolidation of LRI (including the
Commission
Services)
Confidential,
only for members
Workshop Test of the consortium
D3.1 WP3 1 - AT BMJ Report 12
preparation (including the
Commission
Services)
Confidential,
only for members
of the consortium
D3.2 Updated Test Plan WP3 5 - LV CA Report 13
(including the
Commission
Services)
Page 6 of 24
Due
Deliverable WP Dissemination
Deliverable Title Lead beneficiary Type15 Date (in
Number14 number9 level16
months)17
Confidential,
only for members
of the consortium
D3.3 Test Report WP3 5 - LV CA Report 20
(including the
Commission
Services)
Confidential,
only for members
Workshop Rollout
of the consortium
D3.4 preparation & Rollout WP3 5 - LV CA Report 18
(including the
plan
Commission
Services)
Websites,
D4.1 Website WP4 2 - EE RIK patents Public 4
filling, etc.
Updated Presentations
D4.2 and Promotional WP4 2 - EE RIK Report Public 20
Guides
Confidential,
only for members
Event preparation of the consortium
D4.3 WP4 2 - EE RIK Report 16
workshop (including the
Commission
Services)
Confidential,
only for members
of the consortium
D4.4 Dissemination Events WP4 1 - AT BMJ Report 20
(including the
Commission
Services)
Page 7 of 24
1.3.3. WT3 Work package descriptions
Work package number 9 WP1 Lead beneficiary 10 1 - AT BMJ
Work package title Project management & coordination
Start month 1 End month 20
Objectives
Ensuring the successful implementation of the project by securing the adherence with the provisions set out in the Grant
Agreement and with deadlines, and by securing that budget limits are not exceeded.
Description of work and role of partners
WP1 - Project management & coordination [Months: 1-20]
AT BMJ, EE RIK, ES REG, HU PMO, LV CA, IRN IP
Overall management and coordination of the project:
All activities related to the general management and coordination of the project which are of horizontal nature
and therefore difficult to assign to specific work packages; distribution of funding payments including financial
reporting and activity reporting; the detailed planning of project activities; the management of the communication with
project partners; the quality monitoring and risk management; the communication with external stakeholders and the
organisation of coordination meetings.
Participation per Partner
Partner number and short name WP1 effort
1 - AT BMJ 1.94
2 - EE RIK 1.90
3 - ES REG 1.56
4 - HU PMO 2.00
5 - LV CA 4.44
6 - IRN IP 1.52
Total 13.36
List of deliverables
Due
Deliverable
Deliverable Title Lead beneficiary Type15 Dissemination level16 Date (in
Number14
months)17
Confidential, only
for members of the
Project, Risk and QA
D1.1 1 - AT BMJ Report consortium (including 2
Plan
the Commission
Services)
Confidential, only
for members of the
D1.2 Kick Off Meeting 1 - AT BMJ Report consortium (including 2
the Commission
Services)
Page 8 of 24
List of deliverables
Due
Deliverable
Deliverable Title Lead beneficiary Type 15
Dissemination level 16 Date (in
Number14
months)17
Confidential, only
for members of the
D1.3 Closing Meeting 1 - AT BMJ Report consortium (including 20
the Commission
Services)
Description of deliverables
D1.1 : Project, Risk and QA Plan [2]
Electronic document (EN); defines the project setup and timeline, responsibilities, communication strategy and usage
of tools such as a Collaboration Tool and telephone conference facilities, the project risks and quality assurance
measures (electronic document in English).
D1.2 : Kick Off Meeting [2]
Meeting: Initial meeting held at the beginning of the project, meeting summary (in English) is the deliverable.
Outputs: agenda, signed list of participants, minutes
D1.3 : Closing Meeting [20]
Closing Meeting held at the project end including a lessons learned session to improve the activities in possible future
projects, minutes of the meeting as an electronic document in English; agenda, signed list of participants.
Schedule of relevant Milestones
Due
Milestone
Milestone title Lead beneficiary Date (in Means of verification
number18
months)
Kick-off meeting including
MS1 Kick-Off Meeting 1 - AT BMJ 1 information on project
formalities
Closing Meeting has been
MS2 Project End 1 - AT BMJ 20 held including a lessons
learned session
Page 9 of 24
Work package number 9 WP2 Lead beneficiary 10 3 - ES REG
Work package title Business Analysis, Solution Design and Consolidation for LRI Requests/Responses
Start month 1 End month 18
Objectives
The objective of this activity is to analyse if the technical and organisational specifications of the national land register
systems fulfil the requirements laid out in the EC functional specifications to connect the land registers to the LRI
central platform.
Performing the detailed business analysis for the data fields of the LRI requests and responses in order to map these
fields to the correct parameter fields of the national land register search requests, and the national land register search
results to LRI responses. The deliverable created during the LRI MS Connection Project by “WP2: Business Analysis
and Solution Design for LRI Requests/Responses” serves as a model for the deliverables to be created in this WP and
shall be updated and altered according to the requirements to connect the national land registers of the beneficiaries
having not participated in the LRI MS Connection Project.
Design of the architecture (component structure) of the national modules which communicate with the LRI platform
at the European e-Justice Portal.
Consolidation of LRI MS Connection project results to ensure the sustainability of these results (e.g. reviewed “Terms &
Conditions” for the central LRI search). On the basis of the analysis done by the new beneficiaries new requirements for
the central LRI platform might arise. Additional features will be analysed to adapt to new requirements and to improve
the cross-border usability (e.g. harmonised and translated error-messages, test automation). Additionally, the project
partners will provide their experience to the EC for enhancing the central LRI with the implementation of planned
features.
Description of work and role of partners
WP2 - Business Analysis, Solution Design and Consolidation for LRI Requests/Responses [Months: 1-18]
ES REG, AT BMJ, EE RIK, HU PMO, LV CA, IRN IP
2.1 Gap Analysis
Analysis of technical and organizational (and possibly legal) specifications and constraints in the countries to be
connected to the central LRI platform. It involves subject matter experts for the national land registers.
2.2 Business Analysis and mapping of the LRI Requests to national LRs
Do the detailed business analysis for the data fields of the LRI requests and responses in order to map these fields to the
correct parameter fields of the national land register search requests and the national land register search results to LRI
responses for the partner countries including the evaluation of the possible re-use of existing interfaces and national
LRI connection modules created during the LRI MS Connection Project by AT BMJ and EE RIK. It involves subject
matter experts for the national land registers. AT BMJ and EE RIK will support the partners with their knowledge gained
during the LRI MS Connection project.
2.3 Analysis of new central LRI requirements
New requirements to be implemented in the central LRI component – as a result of the consolidation activities – as
prerequisites for the connection of additional MS
2.4 Updated design of architecture and specifications of national LRI components
Design of the architecture, the component structure, interfaces and specifications of the national Web Services modules
for LRI requests and responses, including new functions used by all project partners such as common error messages
and the evaluation of the implementation of automated test functions. It involves subject matter experts for the national
land register. AT BMJ and EE RIK will support the partners with their knowledge gained during the LRI MS Connection
project.
2.5 Knowledge transfer & on-site support
AT BMJ and EE RIK support the other partners with their knowledge gained during the analysis and design phase of the
LRI MS Connection project. This includes the institutionalized knowledge transfer by means of a dedicated workshop
and the potential on-site support of partners if requested.
Page 10 of 24
Participation per Partner
Partner number and short name WP2 effort
1 - AT BMJ 0.56
2 - EE RIK 2.60
3 - ES REG 4.25
4 - HU PMO 19.15
5 - LV CA 4.31
6 - IRN IP 8.33
Total 39.20
List of deliverables
Due
Deliverable
Deliverable Title Lead beneficiary Type15 Dissemination level16 Date (in
Number14
months)17
Confidential, only
Workshop Knowledge for members of the
D2.1 Transfer &“Kick-Off 2 - EE RIK Report consortium (including 8
Consolidation” the Commission
Services)
Confidential, only
for members of the
Updated Analysis and
D2.2 5 - LV CA Report consortium (including 16
Design document
the Commission
Services)
Confidential, only
for members of the
Workshop Consolidation
D2.3 1 - AT BMJ Report consortium (including 14
of LRI
the Commission
Services)
Description of deliverables
D2.1 : Workshop Knowledge Transfer &“Kick-Off Consolidation” [8]
Workshop “Knowledge Transfer”, Meeting summary of the Workshop “Knowledge Transfer” as an electronic
document (EN), Agenda, signed list of participants; Workshop “Kick-Off Consolidation” including an outline of
the consolidation activities in WP2. The meetings summary as an electronic document (EN), Agenda, signed list of
participants.
D2.2 : Updated Analysis and Design document [16]
Updated version of the Analysis/Design document created as Deliverable 2.1 during the LRI MS Connection project
adding the country-specific analysis and design results of the new partners and adding new features such as common
error messages across the connected land registers that might be required to be implemented across all national LRI
components. The deliverable will be an electronic document (EN).
D2.3 : Workshop Consolidation of LRI [14]
Meeting summary of the Workshop “Consolidation of LRI” plus an action list as an electronic document (EN).
Agenda, signed list of participants.
Page 11 of 24
Schedule of relevant Milestones
Due
Milestone
Milestone title Lead beneficiary Date (in Means of verification
number18
months)
Knowledge transfer from the
already connected project
Workshop Knowledge
MS3 1 - AT BMJ 7 partners AT BMVRDJ and EE
Transfer held
RIK to the other beneficiaries
has been held
Planning and structuring of
Workshop Kick-Off
MS4 1 - AT BMJ 7 the consolidation activities of
Consolidation held
AT BMVRDJ and EE RIK
Workshop with the
participation of the project
partners, the EC and possibly
the EC IT subcontractors
Workshop Consolidation of involved about the exchange
MS5 1 - AT BMJ 13
LRI held of experience with the
connection of the MS LR
components to the central LRI
platform and about planned
EC implementations.
Page 12 of 24
Work package number 9 WP3 Lead beneficiary 10 5 - LV CA
Consolidation, Development, Test and Deployment of national components for LRI
Work package title
Requests/Responses
Start month 8 End month 20
Objectives
Development of the national LRI components required to connect the national land register of LV to the LRI platform
at the European e-Justice Portal in order to communicate via LRI requests/responses implemented as Web Service
modules. The deliverables created during the LRI MS Connection Project in “WP3 - Development, Test and Deployment
of national components for LRI Requests/Responses” serve as models for the deliverables to be created in this WP and
shall be updated and altered according to the requirements to connect the national land register of LV
Consolidation of the LRI MS Connection project results by developing enhancements of existing national LRI
components according to the results of WP2
Testing of the national LRI components together with the multi-language search user-interface developed by the
European Commission at the European e-Justice Portal
Deployment of the national production environment for the national side of the Land Registers Interconnection with
the European e-Justice Portal
Description of work and role of partners
WP3 - Consolidation, Development, Test and Deployment of national components for LRI Requests/Responses
[Months: 8-20]
LV CA, AT BMJ, EE RIK, IRN IP
3.1 Development of the national LRI components
LV develops the national LRI components required to connect the national land register to the LRI platform at the
European e-Justice Portal in order to communicate via LRI requests/responses implemented as Web Service modules;
AT BMJ and EE RIK support with knowledge transfer
3.2 Consolidation and enhancement of national LRI components
Consolidation and enhancement of existing national LRI components according to the requirements defined in WP2
3.3 Testing of the national LRI components
Testing of the national LRI components together with the multi-language search user-interface developed by the
European Commission at the European e-Justice Portal in order to proof the functionality of the Land Registers
Interconnection, potentially in an automated manner; AT BMJ and EE RIK support with knowledge transfer
3.4 Deployment of the production environment for the national side of the LRI connection to the e-Justice portal
LV deploys the national production environment for the national side of the Land Register Interconnection with the
European e-Justice Portal; AT BMJ and EE RIK support LV with knowledge transfer. At the same time AT BMJ and
EE RIK deploy potential upgrades and necessary tuning of their national solutions, which have been developed in Task
3.2, in order to accommodate the potential modifications of the central LRI testing and production environments.
Participation per Partner
Partner number and short name WP3 effort
1 - AT BMJ 0.28
2 - EE RIK 3.00
5 - LV CA 0.70
6 - IRN IP 0.30
Total 4.28
Page 13 of 24
List of deliverables
Due
Deliverable
Deliverable Title Lead beneficiary Type15
Dissemination level 16 Date (in
Number14
months)17
Confidential, only
for members of the
Workshop Test
D3.1 1 - AT BMJ Report consortium (including 12
preparation
the Commission
Services)
Confidential, only
for members of the
D3.2 Updated Test Plan 5 - LV CA Report consortium (including 13
the Commission
Services)
Confidential, only
for members of the
D3.3 Test Report 5 - LV CA Report consortium (including 20
the Commission
Services)
Confidential, only
Workshop Rollout for members of the
D3.4 preparation & Rollout 5 - LV CA Report consortium (including 18
plan the Commission
Services)
Description of deliverables
D3.1 : Workshop Test preparation [12]
The deliverable will be the meeting summary of the Workshop “Test Preparation” and the first draft of the test plan as
an electronic document in English, Agenda, signed list of participants
D3.2 : Updated Test Plan [13]
Electronic document in English describing the test strategy and methodology and the intended test scenarios which
shall be tested; this document shall be based upon the test plan created as D3.3 during the LRI MS Connection project
whilst acknowledging the increased number of LRI participants
D3.3 : Test Report [20]
Electronic document in English describing the outcomes of actual tests done during the testing phase.
D3.4 : Workshop Rollout preparation & Rollout plan [18]
Summary of the “Rollout Preparation Workshop”, agenda, signed list of participants and the first draft of the updated
Rollout-Plan which will be based upon the Rollout-Plan document created as D3.6 during the LRI MS Connection
Project whilst acknowledging the increased number of LRI participants. The Rollout Plan will be an electronic
document in English that describes how to deploy the national side of the LRI connection in the national production
environment. The document is based upon the results of the D3.5 workshop and the Rollout-Plan plan document
created as D3.6 during the LRI MS Connection Project
Page 14 of 24
Schedule of relevant Milestones
Due
Milestone
Milestone title Lead beneficiary Date (in Means of verification
number18
months)
LV CA starts testing with
Start of actual testing in the
MS6 5 - LV CA 14 queries from the central LRI
test-environment
to the LV land register
Confirmation by the partners
that the tests were finished
MS7 Completion of testing 5 - LV CA 20 successfully and that
all necessary tests were
documented.
Deployment of the national LV CA deploys the national
side of the LRI connection side of the LRI connection
MS8 5 - LV CA 20
in the national production in the national production
environment environment
Page 15 of 24
Work package number 9 WP4 Lead beneficiary 10 2 - EE RIK
Work package title Publicity and Dissemination of Deliverables
Start month 1 End month 20
Objectives
Establishment of wide awareness of the project outcomes and deliverables.
Informing the future clients of the developed Web Services on the new opportunities provided to private persons and
businesses as well as to legal professionals
Raising the public awareness
Informing Member State authorities about the project and its deliverables; provision of the methodology and guidance
for establishing the national connection to the interconnection facility at the e-Justice Portal.
Description of work and role of partners
WP4 - Publicity and Dissemination of Deliverables [Months: 1-20]
EE RIK, AT BMJ, ES REG, HU PMO, LV CA, IRN IP
Management of project publicity and promotion of deliverables:
Press-releases, website and announcements regarding the project activities are to be published; promotion of deliverables
placing special focus on sharing the experience gained and the deliverables created during the project for prospective
users of the Web Services and the other Member States with existing electronic land registers. Dissemination of the
project results at an LRI event (D4.4) and at 2 domain-specific community meetings.
Participation per Partner
Partner number and short name WP4 effort
1 - AT BMJ 0.44
2 - EE RIK 1.50
3 - ES REG 0.66
4 - HU PMO 1.23
5 - LV CA 0.70
6 - IRN IP 0.76
Total 5.29
List of deliverables
Due
Deliverable
Deliverable Title Lead beneficiary Type 15
Dissemination level 16 Date (in
Number14
months)17
Websites,
D4.1 Website 2 - EE RIK patents Public 4
filling, etc.
Updated Presentations
D4.2 2 - EE RIK Report Public 20
and Promotional Guides
Event preparation Confidential, only
D4.3 2 - EE RIK Report 16
workshop for members of the
Page 16 of 24
List of deliverables
Due
Deliverable
Deliverable Title Lead beneficiary Type 15
Dissemination level 16 Date (in
Number14
months)17
consortium (including
the Commission
Services)
Confidential, only
for members of the
D4.4 Dissemination Events 1 - AT BMJ Report consortium (including 20
the Commission
Services)
Description of deliverables
D4.1 : Website [4]
The website will present the project deliverables and news about ongoing project activities.
D4.2 : Updated Presentations and Promotional Guides [20]
Presentations (in English, electronic document) will be prepared to promote the project deliverables, to explain the
lessons learned and to deliver guidance for other countries interested in establishing the LRI connection; based on the
presentations created as D5.2 in the LRI MS Connection project. Furthermore Guides (EN; electronic and printed) for
main target groups to introduce the new web services and address users in the beneficiary countries
D4.3 : Event preparation workshop [16]
Summary of the workshop, the planned agenda and the planned preparation tasks as an electronic document (EN),
signed list of participants
D4.4 : Dissemination Events [20]
Dissemination event - Meeting summary of the dissemination event (estimated 30 to 50 participants) for informing
other Member States and legal professionals about the deliverables and results of the project; electronic document
(EN), agenda, signed list of participants, presentations Domain-specific community meetings (2) - summary, agenda,
presentations,signed list of participants
Schedule of relevant Milestones
Due
Milestone
Milestone title Lead beneficiary Date (in Means of verification
number18
months)
A special project web-site
will be published/reused on
the basis of the website of
the preceding project LRI
MS9 Website 2 - EE RIK 3 MS Connection at https://lri-
ms.eu/. The project results
will be published at the site
and the ongoing project
activities described regularly.
The partners will start
the preparation of the
Event preparation workshop dissemination event in this
MS10 2 - EE RIK 15
held workshop. The workshop
will tackle issues like agenda
planning, identifying and
Page 17 of 24
Schedule of relevant Milestones
Due
Milestone
Milestone title Lead beneficiary Date (in Means of verification
number18
months)
contacting the target group,
creating contents, etc.
An international meeting
will be organised with an
estimated audience of 30-50
MS11 Dissemination Event held 1 - AT BMJ 20
participants from national
authorities, judicial staff and
legal professionals.
Page 18 of 24
1.3.4. WT4 List of milestones
Due
Milestone WP
Milestone title Lead beneficiary Date (in Means of verification
number18 number9
months)17
Kick-off meeting including
MS1 Kick-Off Meeting WP1 1 - AT BMJ 1 information on project
formalities
Closing Meeting has been
MS2 Project End WP1 1 - AT BMJ 20 held including a lessons
learned session
Knowledge transfer from the
already connected project
Workshop Knowledge
MS3 WP2 1 - AT BMJ 7 partners AT BMVRDJ and EE
Transfer held
RIK to the other beneficiaries
has been held
Planning and structuring of
Workshop Kick-Off
MS4 WP2 1 - AT BMJ 7 the consolidation activities of
Consolidation held
AT BMVRDJ and EE RIK
Workshop with the
participation of the project
partners, the EC and possibly
the EC IT subcontractors
Workshop
involved about the exchange
MS5 Consolidation of LRI WP2 1 - AT BMJ 13
of experience with the
held
connection of the MS LR
components to the central LRI
platform and about planned
EC implementations.
LV CA starts testing with
Start of actual testing in
MS6 WP3 5 - LV CA 14 queries from the central LRI
the test-environment
to the LV land register
Confirmation by the partners
that the tests were finished
MS7 Completion of testing WP3 5 - LV CA 20 successfully and that
all necessary tests were
documented.
Deployment of the
LV CA deploys the national
national side of the
side of the LRI connection
MS8 LRI connection in the WP3 5 - LV CA 20
in the national production
national production
environment
environment
A special project web-site
will be published/reused on
the basis of the website of
the preceding project LRI
MS9 Website WP4 2 - EE RIK 3 MS Connection at https://lri-
ms.eu/. The project results
will be published at the site
and the ongoing project
activities described regularly.
Page 19 of 24
Due
Milestone WP
Milestone title Lead beneficiary Date (in Means of verification
number18 number9
months)17
The partners will start
the preparation of the
dissemination event in this
Event preparation workshop. The workshop
MS10 WP4 2 - EE RIK 15
workshop held will tackle issues like agenda
planning, identifying and
contacting the target group,
creating contents, etc.
An international meeting
will be organised with an
Dissemination Event estimated audience of 30-50
MS11 WP4 1 - AT BMJ 20
held participants from national
authorities, judicial staff and
legal professionals.
Page 20 of 24
1.3.5. WT5 Critical Implementation risks and mitigation actions
Risk
Description of risk WP Number Proposed risk-mitigation measures
number
Main risks of the project
are caused by external
dependencies: The project
is dependent on external Regular and institutionalized forms of
1 components and interfaces WP1, WP2, WP3 communication with the EC and/or its IT
which have to be delivered subcontractor
on time by external partners,
e.g. subcontractors of the
European Commission.
The majority of MS
documents queried via
the LRI Platform on the
e-Justice Portal are not
free of charge. The MS are
dependent on the EC to
implement payment services
on the LRI platform to allow Regular and institutionalized forms of
the users to access those communication with the EC and/or its
documents. As payment subcontractor; if required, partners will support
services are new for the e- the EC with their know-how gained in the
Justice Portal there are many operation of their national land registers and
legal, contractual, financial they will participate in the tests of the payment
2 WP1, WP2, WP3, WP4
(invoicing) and tax (VAT) system. These issues and risks will be closely
issues and organisational monitored and require close communication
issues of the money-flow still with the European Commission and other related
to be clarified and solved, projects who also need a payment service like
as well as issues with the BRIS (Business Registers Interconnection) and
organisation flow and the IRI (Insolvency Registers Interconnection).
money transfer flow. Further
delays in the implementation
of payment solutions might
endanger the LRI System in
the long run as limited access
to search result might lead to
the problem of credibility.
Retrieving the documents
of the query by owner
requires in certain cases
the authentication of
users due to MS law. The
central LRI platform is Regular and institutionalized forms of
expected to be connected communication with the EC and/or its IT
with the MS authentication subcontractor; if required, partners can support
3 mechanisms currently WP1, WP2, WP3, WP4 the EC with know-how and participate in the tests
in place. The analysis, of the authentication solution These issues and
design, development and risks will be closely monitored. They require close
testing of the necessary communication with the European Commission.
adaptions of the national
authentication portal for
court professional was done
for AT and EE in the LRI
MS Connection Project.
Page 21 of 24
Risk
Description of risk WP Number Proposed risk-mitigation measures
number
The MS are dependent on
the EC to implement the
required feature on the LRI
platform. Further delays
in the implementation of
authentication solutions
might endanger the LRI
System in the long run as
limited access to search
result might lead to the
problem of credibility.
Interfaces of the LRI
platform with the national Regular and institutionalized forms of
4 side might change when WP2, WP3 communication with the EC and/or its IT
including the actual payment subcontractor.
service provider.
Public notices do not gain the Distribute via existing networks/fora such as WP
5 WP4
expected attention. E-Law (E-Justice)
The delayed delivery of
the project outcomes will
6 leave less time for promotion WP4 Promote also high level outlines of deliverables
activities and preparation of
the promotion web-site.
Diverse technical solutions
of land registers and/or
Analyse current situation and requirements at an
7 diverging national legislation WP2, WP3
early stage Involve national LR experts
lead to non-transferability of
existing experience.
Page 22 of 24
1.3.6. WT6 Summary of project effort in person-months
WP1 WP2 WP3 WP4 Total Person/Months per Participant
1 - AT BMJ 1.94 0.56 0.28 0.44 3.22
2 - EE RIK 1.90 2.60 3 1.50 9
3 - ES REG 1.56 4.25 0 0.66 6.47
4 - HU PMO 2 19.15 0 1.23 22.38
5 - LV CA 4.44 4.31 0.70 0.70 10.15
6 - IRN IP 1.52 8.33 0.30 0.76 10.91
Total Person/Months 13.36 39.20 4.28 5.29 62.13
Page 23 of 24
1.3.7. WT7 Tentative schedule of project reviews
Review Tentative Planned venue
Comments, if any
number 19 timing of review
In the framework of the assessment of the final
RV1 15 narrative and financial reports, a review may be
organised
Page 24 of 24
1. Project number
The project number has been assigned by the Commission as the unique identifier for your project. It cannot be
changed. The project number should appear on each page of the grant agreement preparation documents (part A
and part B) to prevent errors during its handling.
2. Project acronym
Use the project acronym as given in the submitted proposal. It can generally not be changed. The same acronym should
appear on each page of the grant agreement preparation documents (part A and part B) to prevent errors during its
handling.
3. Project title
Use the title (preferably no longer than 200 characters) as indicated in the submitted proposal. Minor corrections are
possible if agreed during the preparation of the grant agreement.
4. Starting date
Unless a specific (fixed) starting date is duly justified and agreed upon during the preparation of the Grant Agreement,
the project will start on the first day of the month following the entry into force of the Grant Agreement (NB : entry into
force = signature by the Commission). Please note that if a fixed starting date is used, you will be required to provide a
written justification.
5. Duration
Insert the duration of the project in full months.
6. Call (part) identifier
The Call (part) identifier is the reference number given in the call or part of the call you were addressing, as indicated
in the publication of the call in the Official Journal of the European Union. You have to use the identifier given by the
Commission in the letter inviting to prepare the grant agreement.
7. Abstract
8. Project Entry Month
The month at which the participant joined the consortium, month 1 marking the start date of the project, and all other start
dates being relative to this start date.
9. Work Package number
Work package number: WP1, WP2, WP3, ..., WPn
10. Lead beneficiary
This must be one of the beneficiaries in the grant (not a third party) - Number of the beneficiary leading the work in this
work package
11. Person-months per work package
The total number of person-months allocated to each work package.
12. Start month
Relative start date for the work in the specific work packages, month 1 marking the start date of the project, and all other
start dates being relative to this start date.
13. End month
Relative end date, month 1 marking the start date of the project, and all end dates being relative to this start date.
14. Deliverable number
Deliverable numbers: D1 - Dn
15. Type
Please indicate the type of the deliverable using one of the following codes:
R Document, report
DEM Demonstrator, pilot, prototype
DEC Websites, patent fillings, videos, etc.
OTHER
ETHICS Ethics requirement
ORDP Open Research Data Pilot
DATA data sets, microdata, etc.
16. Dissemination level
Please indicate the dissemination level using one of the following codes:
PU Public
CO Confidential, only for members of the consortium (including the Commission Services)
EU-RES Classified Information: RESTREINT UE (Commission Decision 2005/444/EC)
EU-CON Classified Information: CONFIDENTIEL UE (Commission Decision 2005/444/EC)
EU-SEC Classified Information: SECRET UE (Commission Decision 2005/444/EC)
17. Delivery date for Deliverable
Month in which the deliverables will be available, month 1 marking the start date of the project, and all delivery dates
being relative to this start date.
18. Milestone number
Milestone number:MS1, MS2, ..., MSn
19. Review number
Review number: RV1, RV2, ..., RVn
20. Installation Number
Number progressively the installations of a same infrastructure. An installation is a part of an infrastructure that could be
used independently from the rest.
21. Installation country
Code of the country where the installation is located or IO if the access provider (the beneficiary or linked third party) is
an international organization, an ERIC or a similar legal entity.
22. Type of access
VA if virtual access,
TA-uc if trans-national access with access costs declared on the basis of unit cost,
TA-ac if trans-national access with access costs declared as actual costs, and
TA-cb if trans-national access with access costs declared as a combination of actual costs and costs on the basis of
unit cost.
23. Access costs
Cost of the access provided under the project. For virtual access fill only the second column. For trans-national access
fill one of the two columns or both according to the way access costs are declared. Trans-national access costs on the
basis of unit cost will result from the unit cost by the quantity of access to be provided.
Part B
Contents
1. Project background, needs assessment & relevance ................................................. 2
2. Objectives, methodology & impact .................................................................................... 4
2.1 Objectives, impact & methodology .............................................................................................. 4
2.2. Cost effectiveness ...................................................................................................................... 7
2.3. European added value ............................................................................................................... 7
2.4 Timetable..................................................................................................................................... 9
3. Participants and project management ........................................................................... 11
3.1 Consortium cooperation & division of roles for multi-beneficiary grants .................................... 11
3.2 Subcontracting .......................................................................................................................... 13
3.3 Project management ................................................................................................................. 15
3.4 Project teams and staff .............................................................................................................. 15
3.5 Monitoring and evaluation ......................................................................................................... 17
3.6 Dissemination, communication and visibility of EU funding ....................................................... 18
3.7 Ethics......................................................................................................................................... 19
3.8 Sustainability and continuation .................................................................................................. 20
4. History of changes between your proposal and Annex I to the Grant
Agreement "Description of the Action" .............................................................................. 22
1
1. Project background, needs assessment & relevance
Background
Describe background and context behind the project, including your understanding of the relevant EU policies.
Needs Assessment
Provide a needs assessment. A need is a gap between what is and what should/ would be helpful or useful.
The needs assessment should be your starting point. Specify which needs will be addressed and how they have been identified. It should be specific
and focus on the actual needs of the target group. It should include relevant, reliable data and, a robust analysis clearly demonstrating the need for
the action (therefore avoid references to generic statements and information about the problems and needs of the target group).
You can refer to existing research, studies and previous projects that already demonstrate the need for action.
E.g. There is a lack of reporting for victims of gender-based violence. Therefore, there is a need to train professionals in understanding the reasons
behind this so they can empower victims.
Relevance
Explain how your project relates and contributes to the priorities of the call to which you are applying.
Describe the target groups of this project referring to the needs assessment. Which target group(s) need to be supported/ assisted by/in the project.
Why have you chosen to focus on their needs? What EU countries are directly targeted by the project and why have you chosen them?
Clarify to what extent the project builds on synergies with other EU projects. If applicable, explain to what extent your project builds on previous project
results in this field (state of play, relation to existing/recent developments, approaches, achievements, other EU programmes).
Background
The Land Registers Interconnection (LRI) is the voluntary interconnection of the Member State
registers containing property data and property-related rights. The European Commission has
completed a feasibility study on the Land Registers Interconnection (LRI) already in 2014 for the
reasons outlined below. In 2016, the Commission initiated the specific LRI project by consulting all of
the Member States in the LRI Expert Group. While the LRI project of the European Commission had
defined the technical interfaces in form of Web Services for the interconnection of the LRI platform at
the European e-Justice Portal with the land registers of the Member States, it was still necessary to
conduct additional analyses and to design the responding solutions at the side of national land
registers of the Member States for the establishment of mutually interconnected service provision.
During the LRI MS Connection project (Grant Agreement No. 785840) the interconnection of the land
registers of Austria and Estonia to the LRI platform was developed. Yet in order to fully harness
possibilities of the LRI, a greater number of connected Member States is desired.
Needs Analysis
The quality of justice requires efficient and rapid access to legal information that citizens and legal
professionals need to know. This includes obtaining reliable information on property rights of citizens
and companies and verifying whether the registration of these rights is valid, for example, before
purchasing or selling a property, when applying for a mortgage at a bank and during insolvency and
succession (inheritance) procedures. Therefore, citizens, companies, public authorities and legal
professionals (including notaries, lawyers, judges and court officials, as well as credit institutions)
need to have access to the property data in the land registers across Europe.
Currently several Member States in Europe are providing web-based search mechanisms for
querying data and documents from the national land registers. However, these services may be
accessible only nationally or in the national language only – thus not satisfying the needs of the
citizens, companies and legal professionals in other Member States. The fragmentation of land
2
registers impedes efficient searches for the properties and the related information on owners,
restrictions and other parameters.
There are potentially all 500 million European citizens, acting as private persons, company
representatives or legal professionals (e.g. judges, court officials, notaries and lawyers) who could
have an interest in querying the land registers of the Member States. The increased mobility of
citizens and the increased number of cross-border acquisitions of property boost the relevance of
improved searches across the Member State land registers.
Regulation No 650/2012 of 4 July 2012 on jurisdiction, applicable law, recognition and enforcement of
decisions and acceptance and enforcement of authentic instruments in matters of succession and on
the creation of a European Certificate of Succession allows for the easy cross-border execution of
succession proceedings whilst often times resulting in the slow and cost-inefficient process of
querying the respective land registers to identify the properties. Judges, court officials or notaries
working on a cross-border succession case should be able to easily perform a search by person
name to identify the property of a deceased person registered in another Member State by
conducting a property search in a specific country or by carrying out a Pan-European search.
Relevance
The interconnection of the national land registers in Europe via the e-Justice Portal has been a focus
area of the European Commission since the year 2013. The project activities include the expansion
and adaptation of the existing LRI solution. The project aims to support the implementation of e-
Justice projects within the European e-Justice Portal whilst clearly having a European dimension. The
connection of additional Member States will secure the viability and sustainability of the existing LRI
platform.
This transnational project supports the implementation of the 2019-2023 Action Plan for European e-
Justice (5140/19) adopted by the Council of the European Union on 6 December 2019 whilst
acknowledging the principle of decentralisation laid out in the 2019-2023 Strategy on European e-
Justice (5139/1/19 REV 1) adopted by the Council of the European Union on 6 December 2019. This
decentralised approach to interconnect the various systems already established in the Member
States respects the principles of proportionality and subsidiarity.
The established technical solutions for connecting the national land registers to the e-Justice Portal
will also become important sample cases for the further circle of Member States considering the
respective establishment of the connection to the Land Register Interconnection platform on the e-
Justice Portal in the upcoming years.
3
2. Objectives, methodology & impact
2.1 Objectives, impact & methodology
Project approach
Describe the project approach. You will need to be specific and must use the headings below to structure your response.
Objectives
Define what the specific project objectives are and explain how they respond to the needs/issues/challenges/gaps of the respective cohort (actions to
be taken) highlighted in the needs assessment.
The objectives should be specific, measureable, realistic and achievable within the duration of the project. For example, a sample of 1000 professionals
was surveyed as part of the needs assessment and we will target 200 of these professionals as recipients of this project. They have a potential to
reach out to 5000 persons in the final target group. We aim to train at least 50% of them in understanding the reasons behind underreporting of
violence. This shall result in decreasing the underreporting rate and thus empowerment of victims.
For each objective, define appropriate indicators as you have listed in Annex 3, for measuring progress (including baseline value and target value).
Impact
Define the expected results (short, medium and long-term) of the project. What tangible and intangible impact will the project have on the target
groups? In what way the gap identified will be reduced? How the activities will contribute to improve the situation (difference between starting point/state
of play and the situation after the completion of the project?)
Results are immediate changes that materialise for the target groups after the completion of the project (e.g. improved knowledge, increased
awareness). Results are different to deliverables. Deliverables are activities undertaken and outputs produced with the resources allocated to the
project, e.g. training courses, conferences, manuals, video etc.
Does the project bring innovative solutions?
Methodology
Describe your methodology to achieve the proposed project objectives. Why it is the most suitable approach for implementing the project throughout
its lifecycle.
Methodology is not a list of activities but are instruments, approaches that will be used, applied and created. For example, we will host a series of
workshops for the 200 professionals to help them to understand the reasons behind underreporting of gender-based violence.
Objectives
In order to establish operational interconnections to the e-Justice portal, the proposed project will
undergo the activities of analysing both the existing features of and the data provided by the
respective land registers of ES, HU, LV and PT as well as the business analysis and mapping of the
LRI requests to the national land registers. The beneficiaries will design the national Web Services
required to establish the connection between the respective national land registers and the LRI
platform at the e-Justice Portal. The analysis for the connection to the LRI platform will be completed
by ES, HU, LV and PT, supported and consolidated by the forerunners of AT and EE.
In addition to the analysis, LV will develop and implement the national technical solution for the
connection of their national land register and the central Land Registers Interconnection platform of
the European Commission. This additional interconnection of one MS (LV) to the Land Register
Interconnection Platform will be described in the Rollout Plan (D3.4).
As an end result, the project will deliver the means for providing legally valid electronic data
originating from three national land registers (AT and EE from LRI MS Connection and LV) to citizens,
companies and legal professionals across the borders of the Member States using a single entry
point with a multi-language search interface at the European e-Justice Portal.
The dissemination activities aim at presenting the project results to land registry agencies and
respective experts of the field, public officials dealing with legal proceedings and legal professionals
in order to demonstrate the advantages of the Land Registers Interconnection and to motivate other
Member States to get connected to LRI. Therefore, an international meeting will be organised with an
4
estimated audience of 30 to 50 participants. Additionally, the project will be presented at least at two
domain-specific working parties and conferences held during the project timespan. Supporting
materials (website, promotional flyers and presentations) will be provided.
Impact
The intangible short-term result of the project is enabling 4 member states (ES, HU, LV and PT) to
implement their connection to the Land Registers Interconnection (knowledge transfer, analytical and
conceptual work). While ES, HU and PT will not implement their connection in the course of the
project, the connection of one Land Register (LV) to the Land Registers Interconnection Platform of
the European Commission is a medium-term tangible project result. With the help of this project,
potentially all 500 million European citizens, all companies and in addition professional user groups
(e.g. judges, court officials, notaries, lawyers) can query the land registers of Estonia, Austria and
Latvia to acquire land property-related information via the Internet.
Further short- and medium-term intangible results are the raised awareness of expert users and
domain-specific stakeholders such as national authorities, judicial staff and legal professionals about
the project. Apart from stakeholder outreach via materials and the website, an estimated total of at
least 40 stakeholders is expected to be addressed personally during the WP4 Conference and at
other community-specific meetings. Consolidation activities in WP2 and WP3 will benefit all potential
LRI users by providing an improved user experience (such as improved interfaces, harmonised error
messages, etc.).
In the long run, these project results will support the process of reaching the goal of the European
Commission (see Chapter 1. Relevance) for the easier querying of any European land register
information by means of a centralized query service. The deliverables and experiences of this project
can be used directly as examples to other Member States – those will be able to integrate and call the
corresponding national search functionalities of their own national land registers based on the know-
how and experience of the already connected countries. Follow-on Member States joining LRI in the
future can re-use all the project deliverables created in English language and use them as templates
for their own work (as partly done in this project with the re-use of deliverables created during the LRI
MS Connection Project). Citizens, businesses (e.g. banks), judicial authorities and practitioners will
be able query any other LRI-connected land register as well.
The long-term impact of the project will be the easier cross-border access to property information for
all target groups mentioned above by lowering the costs of receiving the necessary information from
land registers of other MS (one query instead of multiple queries, direct access to the service for
users over the Internet without resorting to intermediary actors) and enabling the users of property
data to act more efficiently in their daily business. Furthermore, it will speed up judicial proceedings
that rely on the retrieval of land register information from other European Member States.
For legal professionals and state officials the financial costs for gaining the necessary property
information will be lower than today and the respective government services can be provided with
shorter delivery times.
By doing so the project strengthens all four freedoms of the European Union.
5
Methodology
In order to achieve high quality deliverables several measures are foreseen: The documents
delivered regarding the project activities will be evaluated internally in the form of peer reviews done
by the project partners. The project team members of all partners shall review deliverable parts
created by other members in the project team – in order to achieve good quality of the deliverable
documents. For the software to be developed and adapted a test plan will be created and test
scenarios for systematic testing of the core functionalities will be described. To document the results
of the tests a test report document will be created which shall record the results of the execution of
test cases – each for the testing of specific test scenarios. Experiences of partners will be shared at
internal workshops covering several aspects of the work. A Rollout Plan will be composed in order to
prepare for and to monitor the deployment and rollout of the delivered technical solutions.
Regarding the risk management potential risks within all work packages will be regularly identified
and documented in order to assess and prioritise the identified risks according to their probability and
impact and to decide on mitigating actions for the highest priority risks.
The project dissemination will be done at several occasions including community meetings such as
meetings of the Working Party on E-Law (E-Justice), ELRA (European Land Registry Association)
assemblies and the dissemination event to be held at the end of the project.
6
2.2. Cost effectiveness
Demonstrate that your project represents good value for money and that you aimed for cost efficiency in the estimated budget. You may include any
comments of the horizontal nature in relation to the items presented in the estimated budget.
The activities carried out during the project will be based upon the findings of the LRI MS Connection
project. The coordinating role of AT BMJ, the provision of knowledge transfer activities by AT BMJ
and EE RIK in both the analysis and the implementation phase of the project and the workshop on
Knowledge-Transfer will ensure that the partners can familiarize themselves with the results of the
LRI MS Connection project. The deliverables to be created during the project will re-use and update
those deliverables already created in the past project. This approach will minimize the resources
necessary and minimise the risk of overlapping activities and double funding. The media created for
dissemination in the LRI MS Connection project (flyers, roll-ups, website) will be re-used in the
project.
Some costs – especially project management costs – have been calculated with a risk surcharge in
accordance with the risks identified in section 5.2. Experience from the previous project
“LRI MS Connection” has shown that due to lacking experience in the field of land register
interconnection the project partners had to adopt to results found during the progress of the project. In
addition, the LRI platform of the European Commission had not been used in a productive
environment before. Therefore, several requirements were set up during the first project.
The same effect is expected for this follow-up project since some crucial functionalities like “payment”
and “authentication and authorisation” are not yet implemented by the central LRI platform. During the
implementation of these functionalities further changes in the system must be taken into account and
therefore project management efforts have been calculated higher to reflect these uncertainties.
The uneven distribution of budget between the partners reflects their participation in the different
phases of the project. Whereas some partners will participate in all project phases others will
complete e.g. only the analysis phase and follow up with the implementation at a later stage outside
the project timeframe (and on their own expenses or other EU-funding).
2.3. European added value
European dimension
Illustrate the European dimension of the planned activities: trans-national dimension of the project; impact/interest for a number of countries;
possibility to use the results in other countries, potential to develop mutual trust/cross-border cooperation among EU countries, contribution to the
consistent and coherent implementation of EU law, and to public awareness about the rights deriving from it etc.
Which countries will benefit from the project (directly and indirectly)? Where will the activities take place?
The increased mobility of European citizens leads to an ever increasing number of cross-border
financial transactions, a rise of acquisitions of real estate by European citizens in other Member
States and an increased number of cross-border civil and criminal proceedings. These activities
require the query of land register information in other Member States or the pan-European query of
land register information in relation to a certain citizen.
7
The European Parliament and the Council of the European Union adopted a range of instruments to
create and guard the area of freedom, security and justice, which affects cross-border proceedings
such as inheritance proceedings and the enforcement of criminal law.
Regulation No 650/2012 of 4 July 2012 on jurisdiction, applicable law, recognition and enforcement of
decisions and acceptance and enforcement of authentic instruments in matters of succession and on
the creation of a European Certificate of Succession allows for the easy cross-border execution of
succession proceedings. Often times land register information has to be retrieved in a slow and cost-
inefficient procedure. Judges and court officials or notaries working on a cross-border succession
(inheritance) case should be able to perform a search by person name to identify property of a
deceased person in the land register of another Member State – or even do a pan-European search.
Regulation (EU) 2018/1805 of the European Parliament and of the Council of 14 November 2018 on
the mutual recognition of freezing orders and confiscation orders allows for the easier depriving of
criminals of their illegally acquired assets. To retrieve the information on property acquired by
criminals and their ciphers, the LRI project allows the public prosecutors to easily and quickly query
the land registers of the European Member States without burdening them with the consultation of
their counterparts in 27 Member States.
Additionally, the free movement of capital in the EU as one of the key elements of the Single Market
includes the ability to carry out the purchases of real estate in another country which is facilitated by
acquiring the latest and reliable land register data.
The Land Registers Interconnection (LRI) project initiated by the European Commission is a
European initiative to reduce the issues of discrepancy, complexity and multitude of land registration
systems amongst Member States. European citizens and legal professionals shall be able to query
and retrieve property and property-related information via a single multilingual interface.
The defined interfaces of the LRI central platform which currently only Austria and Estonia are
connected to are equipped to connect all Member States ready to do so. The main advantage for
future follow-on Member States is that they will have AT, EE and LV as LRI-connected test-partners
from the beginning of their own work.
The deliverables and experiences of this project can be used directly as examples for other Member
States – of course they will need to integrate and call the corresponding national search
functionalities of their own national land registers. Follow-on Member States joining LRI will be able to
re-use all the project deliverables in English language and use them as templates for their own work.
8
2.4 Timetable
Fill in cells in beige to show the duration of activities. Repeat lines/columns as necessary.
Note: Use the project month numbers instead of calendar months. Month 1 marks always the start of the project. In the timeline you should indicate the timing of each activity per WP.
MONTHS
ACTIVITY
M M M M M M M M M M M M M M M M M M M M M M M M
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Activity 1.1 – Overall
management and
coordination of the project
Activity 2.1 - Gap Analysis
Activity 2.2 - Business
Analysis and mapping of the
LRI Requests to national
LRs
Activity 2.3 - Analysis of
new central LRI
requirements
Activity 2.4 - Updated
Design of architecture and
specification of national LRI
components
Activity 2.5 - Knowledge
transfer and on-site support
Activity 3.1 - Development of
the national LRI
components
Activity 3.2 - Consolidation
and Enhancement of
national LRI components
Activity 3.3 - Testing of the
national LRI components
Activity 3.4 - Deployment of
the production environment
9
for the national side of the
LRI connection to the e-
Justice portal
Activity 4.1 - Management of
project publicity and
promotion of deliverables
10
3. Participants and project management
The list of beneficiaries is included in annex 1 Part A section 1.2.
3.1 Consortium cooperation & division of roles for multi-beneficiary grants
Not applicable for mono-beneficiary grants (single applicants).
Describe the consortium (beneficiaries) and explain how they will work together to implement the project. How will they bring together the necessary
expertise? How do the members complement each other?
In what way does each of the participants contribute to the project? Show that each has a valid role and adequate resources to fulfil that role.
Mention how other third parties (subcontractors, partner organisations, third parties giving in-kind contributions, key stakeholders, etc) will be involved.
Note: When building your consortium you should think of organisations that can help you reaching an objective/solving a problem also in relation to
the EU countries they are located in.
AT BMJ and EE RIK have successfully participated in the LRI MS Connection project that ended in
May 2019. Both partners successfully implemented the national land register connection to do the
pioneering work together with the European Commission to make the Land Registers Interconnection
a success. Additionally, AT and EE have already a proven track record for successful cooperation in
EU projects such as e-CODEX, Me-CODEX, Interconnection of Insolvency Registers and Multi-
aspect Initiative to Improve cross-border videoconferencing (see Chapter 6).
Being successfully connected to the LRI Platform with their national LRs (productive environment),
AT BMJ and EE RIK take up the roles of supporting and/or coordinating partners in this project to
support the other implementing partners with their experience gained during the LRI MS Connection
Project.
With regards to Austria and Estonia, the key stakeholders for the keeping of the respective land
registers are involved in the project with AT BMJ (and its subcontractor hosting the Austrian land
register) and EE RIK hosting the Estonian land register.
Following a decision of the Austrian government to concentrate and outsource most of the IT related
work-force (including business analysts, application team leaders, project managers, developers,
operation and administrative staff) of the Federal Government in a separate computing centre, a
separate IT service provider was founded. It provides its services to several ministries and
government bodies and is 100% owned and controlled by the Republic of Austria. Austrian federal
law allows for the awarding of IT service contracts both via federal law and via in-house procurement.
This is the default proceeding for any IT-service and -development activities and the reason for the
declared amount of sub-contracting costs. The subcontractor conducts already the development,
maintenance and operation for the Austrian Land Register application. The legal responsibility
including liability for the Austrian Land Register remains with AT BMJ. The AT subcontractor has
already successfully conducted activities in the first “LRI MS Connection” project regarding project
office tasks and the technical implementation. The distribution of tasks within “LRI MS Connection 2”
will continue the successful collaboration of the Austrian institutions involved in the project.
11
The “Colegio de Registradores de la Propiedad y Mercantiles de Espana” is a corporation under
public law created by Decree of May 18, 1934 and is the competent chamber for the Spanish land
registrars.
The Hungarian Prime Minister’s Office (Miniszterelnökség) with its “Department of Land
Administration and Geoinformation” is the competent body for the administration of the Hungarian
Land Register. The “Department of Land Administration and Geoinformation” has been transferred
from the Ministry of Agriculture to the Prime Minister’s Office just recently as per 1.4.2019.
LV CA is responsible for maintenance and administration of the State Unified Land Register. LV CA is
a modern growth-oriented state administration institution whose principal objective is securing
administrative support for the effective operation and development of courts. In the dimension of the
strategic development LV CA is focused on increasing the effectiveness and reducing the backlog,
providing access to justice and strengthening the capacity of the judicial sector.
The Portuguese land register is kept by the Land Registry Offices, under the direction of the Land
Registrars, which are part of the Instituto dos Registos e do Notariado (Institute of Records and
Notaries).
Project set-up & division of roles for mono-beneficiary grants:
Not applicable for multi-beneficiary grants (multi-beneficiary consortium).
Describe how the beneficiary and third parties (subcontractors, third parties giving in-kind contributions, key stakeholders, etc) will be involved in the
project. How will they bring together the necessary expertise?
Not applicable
12
3.2 Subcontracting
Give details on subcontracted action tasks (if any) and explain the reasons why (as opposed to direct implementation by the participants).
Note: Subcontracting concerns the outsourcing of a part of the action to a party outside the consortium. It is not simply about purchasing goods or services. We normally expect that the
consortium participants to have sufficient operational capacity to implement the project activities themselves. Sub-contracting should therefore be exceptional.
Include only subcontracts that comply with the rules (i.e. best value for money and no conflict of interest; subcontracting is not possible for key coordinator tasks and may not cover the core of
the action; see art 10 of the Model Grant Agreement).
Participant Description of the Estimated Justification Best-value-for-money
name subcontracted action costs (EUR)
task (why is subcontracting necessary?) (how do you intend to ensure it?)
AT BMJ All technical tasks: EUR The Austrian government decided to concentrate and outsource most of the IT related work- According to § 5 (2)
analysis, 205.200,00 force (including business analysts, application team leaders, project managers, developers, Bundesrechenzentrumgesetz the
implementation, operation and administrative staff) of the federal government in a separate computing center subcontractor is bound to the
testing, rollout. which is shared by several ministries (e.g. Ministry of Finance, Ministry of Justice and other principles of austerity, efficiency
government bodies).Therefore, AT BMJ does not have sufficient staff at its disposal to do and appropriateness in
Provide input for technical implementation as well as IT project office tasks by itself. However, AT BMJ will accordance with the principle of
experience exchange account for strategic decisions, business requirements and the overall project controlling. cost coverage which is
with partners. monitored by the Austrian
The subcontractor is constructed as a company with limited liability and has the full Federal Ministry of Finance.
Provide input for responsibility for its own revenue and costs. It is 100% owned and controlled by the Republic of
information exchange Austria represented by the Austrian Federal Ministry of Finance. Subcontracting is therefore
with European fully compliant with Directive 2014/24/EU.
Commission
The legal base for the subcontracting is defined in Austrian Federal Law in conformity with the
Project Office EU provisions: “Bundesrechenzentrumgesetz”, see also under
http://www.ris.bka.gv.at/GeltendeFassung.wxe?Abfrage=Bundesnormen&Gesetzesnummer=10
001466 .
This is the default process for any Federal Government IT service and development activities
and the reason for the indicated amount of subcontracting costs.
The subcontractor is already the implementing body for development, maintenance and
operation for the Austrian Land Register application. The legal responsibility including liability
for the Austrian land register remains with AT BMJ.
LV CA Technical EUR For WP3 implementation in the part of national land register systems for the connection The Latvian Public Procurement
development, testing 70.000.- preparation for LRI, connection part, development and for testing phase, LV CA will use the Law ensures the openness of
and deployment as service provider who provides services maintenance of the Unified State Land Register. This the procurement procedure, free
described in tasks service provider had been chosen according to the public procurement procedure. competition of suppliers, as well
3.1, 3.2, 3.3, 3.4, 3.5 as equal and fair attitude thereto
of the proposal. and effective use of State and
local government funds,
reducing the risk of the
commissioning party to the
minimum. The Public
Procurement Law shall be
applied to the procurement
procedures referred if the
contract price of public supply
contracts or of service contracts
13
is 10.000 Euro (without VAT) or
more.
Other issues: Subcontracting is about 35% of the total eligible costs. The high ratio of subcontracting is mainly due to the technical nature of several tasks – the
If subcontracting for the entire project beneficiaries do not have sufficient technical staff in their own organisation – and to the high degree of strategic outsourcing by AT BMJ. This high
goes beyond 30% of the total eligible degree of outsourcing technical and project office activities to the AT subcontractor is the result of strategic decisions by the
costs, give specific reasons. Austrian Federal Government as outlined above.
14
3.3 Project management
Explain the overall project management concept, in particular how decisions will be taken and how permanent and effective communication will be
ensured.
Work package 1 (WP1) is the horizontal work package for the overall coordination of all work
packages and communication with external stakeholders like the European Commission. WP1 lead
by AT BMJ is dealing with project management, project monitoring and risk mitigation. Therefore, AT
BMJ and the partners involved intend to monitor the project progress and to apply corresponding
measures for potential deviations from the intended project objectives.
To do so, the project partners will report their progress regularly to the project manager. The progress
and issues will be discussed and activities to solve or mitigate will be decided and initiated. Tangible
deliverables are defined for each work package, which allows a check on timely delivery and quality
of the results.
The permanent and effective communication is assured by the use of telephone conferences (at least
every month and on demand), consortium meetings and technical and organizational workshops.
Additional meetings will be held on demand. The parties will use a central collaboration platform for
communication and the distribution of documents which shall store all content created in the course of
the project. The coordinator will create mailing lists for all project partners and a project office mail
address which shall serve as the single point of contact with regards to the coordinator.
The project partners will form the decision-making body of the project consortium. All major decisions
shall be discussed and agreed upon unanimously between the parties.
3.4 Project teams and staff
Describe the project teams and how they will work together to implement the project.
List the staff included in the project budget (budget category A) by function/profile (e.g. project manager, senior expert/advisor/researcher, junior
expert/advisor/researcher, trainers/teachers, technical personnel, administrative personnel etc) and describe shortly their tasks.
The project will be implemented by six partners from six different Member States, as follows:
The project partner 1 (coordinator):
Austria – Federal Ministry of Justice (full legal name in German: BUNDESMINISTERIUM FUER
JUSTIZ)
The implementing department "Legal Informatics and ICT (information and communication
technology)" is responsible for the Austrian Land Register, Business Register, Insolvency Register
and the Court Case Management System in Austria.
Core project team members:
Dr. Thomas Gottwald, Senior Legal Expert for Civil Law, Project Manager, LEAR
Dr. Martin Schneider, Senior Legal Expert, Legal Informatics and ICT department
Manfred Buric, Senior Legal Expert for AT Land Register, Project Manager, Contact Person
Mathias Maurer, Senior Legal Expert, Coordination of work packages, Contact Person
Robert Behr, Senior Technical Expert, Financial Manager, Contact Person
15
Manfred Fraißl, Senior Technical Expert, Team-leader of the development team of the AT Land
Register
Georg Garstenauer, Legal Expert, Junior Project Manager, Contact Person
The project partner 2:
Estonia – Centre of Registers and Information Systems (full legal name in Estonian:
REGISTRITE JA INFOSÜSTEEMIDE KESKUS)
The implementing department "Court Registers Department" develops and operates the Estonian e-
Land Register. The Centre of Registers and Information System administrates also other state
registries and information systems of very high importance, such as the Business Register and the
Company Registration Portal, the e-Notary system, the information systems of courts, the Probation
Supervision Register, the Prisoners Register, the Criminal Records Database, the e-File, the
electronic State Gazette, etc.
Core project team members:
Ingmar Vali, Technical Expert, Head of the Court Registers Department, Contact Person
Katri Tammsaar, Technical Expert, Contact Person
The project partner 3:
Spain – Public Law Corporation of Land and Mercantile Registrars of Spain (full legal name in
Spanish: COLEGIO DE REGISTRADORES DE LA PROPIEDAD Y MERCANTILES DE ESPANA)
Core project team members:
Enrique Maside Páramo, Main Contact
Francisco J. Gimeno, Legal Expert, Contact Person
Pedro Pernas Ramírez, Legal Expert, Contact Person
The project partner 4:
Hungary – Prime Minister’s Office (full legal name in Hungarian: MINISZTERELNÖKSÉG)
Core project team members:
dr. Balazs Toth, Senior legal expert for HUN Land Register, Head of Department, Department of Land
Administration and Geoinformation, Contact Person
The project partner 5:
Latvia – Court Administration of Latvia (full legal name in Latvian: TIESU ADMINISTRACIJA)
Court Administration of Latvia is responsible for the maintenance and the administration of the State
Unified Land Register, Court Informative system, the Register of Enforcements cases including the e-
auction portal.
Core project team members:
Liga Lapina, Head of Judicial Information Division, Department for Courts and Land Registries,
Contact Person
Kristina Mucina, Deputy Head of Judicial Information Division, Department for Courts and Land
Registries, Contact Person
Janis Dreimanis, Deputy Head of Project management and international cooperation Division,
Contact Person
The project partner 6:
Portugal – Institute of Registries and Notaries (full legal name in Portuguese: INSTITUTO DOS
REGISTOS E DO NOTARIADO, I.P.)
Core project team members:
16
Paulo Manuel Garcês Vieira, Project manager, Contact Person
The partners will apply the cooperation structure used during the LRI MS Connection project including
both periodic face-to-face meetings and telephone conferences. The communication is facilitated by a
common collaboration platform using IBM Connections and mailing lists.
3.5 Monitoring and evaluation
Describe how you intend to monitor and evaluate the progress of the project. This includes explaining which quantitative and qualitative indicators you
propose to use for the evaluation and coverage of the project activities and results.
Explain which quantitative and qualitative indicators you propose to use for the evaluation of the outreach and coverage of the project activities and
project results.
Note: We encourage participants to monitor and evaluate changes in attitudes and behaviour of the target group throughout and after the life of the
project. This includes examining the behavioural causes of the issue and its underlying determinants, identifying the encouraged behaviour(s) for each
target group, specifying which behavioural solutions will be tested, explaining how the expected results will be evaluated and whether the proposed
solutions will be pre-tested before full-scale implementation (see more detailed guidance).
Monitoring of the Project Implementation
Work package 1 (WP1) is dealing with project management, project monitoring and risk mitigation.
Therefore, WP1 will monitor the project progress and apply corresponding measures for potential
deviations from the intended project objectives.
To do so, the project work package leaders will report their progress regularly to the project manager.
The progress and issues will be discussed and activities to solve or mitigate will be decided and
initiated. Tangible deliverables are defined for each work package, which allows a check on timely
delivery and quality of the results.
Evaluation:
In order to achieve good quality of our deliverables we plan the following measures:
• The deliverable documents of our project activities will be evaluated by internal quality
reviews in form of peer reviews done by the project partners. Project team members of all
partners shall review deliverable parts created by other persons in the project team in order
to achieve good quality of the deliverable documents.
• For the software to be developed (adapted) the partners will create a test plan and describe
test scenarios for systematic testing of the core functionality. To document the results of the
tests they will create a test report which shall document the results of the real execution of
test cases – each for testing of a specific test scenario.
• To monitor deployment (rollout) in the participating MS not yet connected the partners will
also create a rollout plan
• Regarding risk management, the plan is to
o identify potential risks within all work packages regularly
o document the risks in a risk register
o assess and prioritise the identified risks according to probability and impact
o decide on mitigating actions for the highest priority risks, taking into account also
proximity (how far away in time will the risk occur – if it materializes)
17
The partners can use the deliverables and lessons learned documents created in the context of the
LRI MS Connection project. Having already implemented a connection to the Central LRI component,
AT BMJ and EE RIK will take on technical and organizational support roles and they are able to
prematurely identify the risks occurring during the implementation of the connection of the beneficiary
countries.
Feedback from project participants will be gained during regular project meetings and workshops in
informal form. During the project closing meeting a formal feedback and lessons learned session will
be held.
3.6 Dissemination, communication and visibility of EU funding
Describe the dissemination and communication activities which are planned in the framework of the project in order to promote the project
activities/results and maximise the impact (to whom, which format, how many copies, etc.). Clarify how you will reach the target groups, the relevant
stakeholders, policymakers and the general public and explain the choice of the dissemination channels.
Describe how the visibility of EU funding will be ensured.
The dissemination and awareness building of the project results and deliverables holds a crucial
place among the other project activities, since the deliverables of the project are of practical nature
and are intended to provide an example for other Member States in the process of interconnecting
with the network of European land registers.
The initial and overall focus of the WP4 dissemination activities is to target domain-specific experts
(practitioners and public officials dealing with land registers) and policy makers in order to increase
awareness among practitioners and experts and to convince the responsible decision-makers from
the judicial and/or political domain to connect their respective Land Register Systems to the LRI
platform.
Moreover, an additional focus is placed on inviting experts on the prevention of terrorism and money
laundering (from member state judicial and/or law enforcement agencies, and European and
international organisations and networks such as Eurojust, Europol, European Judicial Network) as
well as businesses engaged in cross-border mortgage financing (banking and insurance sector). WP4
will ensure that any dissemination materials produced will also address the aforementioned groups
and/or will be available in separate versions addressing these groups. With the going-live of the
Central LRI Platform and solutions for the payment process (both factors are external), the
dissemination focus will slightly shift to communication activities incentivising potential users to use
the service to increase query numbers.
The dissemination activities include the delivery and spreading of press releases and public notices
(in proximity with project Milestones and domain specific events; at least at 4 occasions [Project Kick-
off, Successful Tests with LV, closing conference and project end]) via the professional networking
channels, public websites and one kind of social network best suited to reach the above-mentioned
audiences (e.g. Twitter, LinkedIn). Also, presentations promoting the project outcomes will be held at
several domain-specific working parties and international e-government conferences.
The already existing demonstration environment that includes AT and EE search results provides
interested land registries and software developers with an opportunity to familiarise themselves with
the functionalities and features of the developed solutions for AT and EE in order to consider its
applicability for their national environments. Access to the demo environment shall be granted upon
request. Apart from that, it shall be shown at domain-specific events and exhibited/shared for hands-
18
on testing if possible. Until the going-live of the Central LRI Platform, the demonstration environment
serves as an invaluable means to make the project results palpable.
During the year 2021 an international closing conference will be held for promoting the project
deliverables especially for the neighbouring and the next circle or follow-up countries for discussing
the linked development issues and opportunities becoming available by that time.
Furthermore, the exploitation of the project results is envisioned to continue after the end of the
project. For this reason, the project website shall remain accessible for at least another 3 years
containing a full stock of all project results that can be made public.
3.7 Ethics
Ethics
Describe any ethical issues that may arise during the implementation of the project and the measures you intend to take to mitigate them, including
with regard to the interactions between projects staff, target groups and persons benefitting from the project.
Gender mainstreaming
Describe how you will ensure gender mainstreaming in the project activities. Gender mainstreaming means integrating a gender perspective in the
design, implementation, monitoring and evaluation of a project as appropriate. Project activities should be pro-active and contribute to the equal
empowerment of both genders, and ensure that they achieve their full potential, enjoy the same rights and opportunities. Gender mainstreaming goes
beyond counting the number of women and men in a room. In the delivery of project activities gender mainstreaming shall be ensured by monitoring
access, participation, and benefits among women and men, and by incorporating remedial action that redresses any gender inequalities in project
implementation.
Rights of the child mainstreaming
If your project has a direct or indirect impact on children and their rights, indicate it clearly here. Make sure that your project is based on a child rights
approach, i.e. that all the rights of the EU Charter of Fundamental Rights and the United Nations Convention on the Rights of the Child (UNCRC) and
the Optional protocols, are promoted, respected, protected and fulfilled. The project should address children as rights holders and should ensure their
participation in the design and implementation of the project. For more detailed explanation, see the text of the call.
If your project directly involves children during any of its phases or activities, you are required to provide your child protection policy as Annex 4 (every
organisation member of the project consortium whose work involves children needs to have one). In case your project does not involve children now,
but should that change during the implementation of the project, submit the child protection policy at the same time when requesting the approval for
the change in the project.
The child protection policy document will be carefully assessed and evaluated against the quality award criteria during the selection phase. If Annex 4
is not submitted, if it is very vague, or if it doesn’t constitute a proper child protection policy, the points your proposal will be awarded under the quality
criteria will be significantly reduced (by half). For more detailed explanation, examples and guidelines on the child protection policies, see the text of
the call.
Ethics
The ethical issue which might arise with the Land Registers Interconnection are to ensure data
protection and privacy. The implementation of the Action will follow the pertinent European and the
respective national data protection rules. Land register data is already processed and published
nationally by complying with national law and the GDPR. The same rules will be applicable to the
data provided by the national land registers via the LRI platform. This principle was already applied
and agreed with the European Commission in the preceding project “LRI MS Connection”.
Therefore, specific queries within the Member States which could be misused are forbidden for
normal users and only properly authenticated legal professionals who can proof a strong legal interest
19
have access to these restricted queries (e.g. search by person name of the owner to identity all
properties of a specific person). These types of queries are only allowed for privileged legal
professionals (e.g. court staff, notaries) in the context of specific legal procedures, e.g. for identifying
all immovable property of a deceased person during a succession (inheritance) case. Therefore,
when implementing the Land Registers Interconnection these restrictions must be maintained as well.
Future EC plans foresee the adaptation of the national authentication mechanisms in order that
specific groups of legal professionals (e.g. court staff) can be authenticated by their national (home)
authentication portal which will be connected by proper technical means with the LRI platform at the
European e-Justice Portal. This will ensure that only properly authenticated legal professionals can
get access to restricted LRI queries.
Gender Mainstreaming
The project staff will involve experts and specialists from different sexes and genders.
In specific user groups /e.g. judges and court officials) the percentage of women is high: e.g. in
Austria more of 50% of the judges are female.
In accordance with Articles 2 and 3 of the Treaty on the European Union (2016/C 202/01) and other
EU legislation, especially Regulation 1382/2013 establishing a Justice Programme, to establish
equality between men and women as a specific task of the Community, the LRI2 Consortium commits
to incorporating the principles of gender main-streaming throughout the various elements of the entire
project.
Rights of the child mainstreaming
The query services of the land registers made available with the support of the project will be
provided by the state authorities of the partner countries which are applying proper privacy protection
mechanisms applicable both for adults and children.
The coordinator and the beneficiaries will not have direct contacts with children under the project.
3.8 Sustainability and continuation
Describe the follow-up of the project after the EU funding ends. How will the sustainability of the project impact be ensured?
Which kind of resources/form of collaboration with other entities will be used to take up the project outputs and results? Are there any possible
synergies/complementarities with other activities/projects that could reinforce the long-term sustainability of the project?
The project is relying upon the results developed during the LRI MS Connection project to both
ensure the sustainability of the LRI MS Connection results, and avoid the duplication of activities.
The other Member States will be invited to interlink their land registers for trans-national service
provision – to grow the number of interconnected land registers. The successful end of the project will
encourage further countries to develop their national connection points to the e-Justice Portal. The
project partners will provide these countries, and also other Member States with lessons learned and
experiences gained through the project, in order to grow the network of countries able to share
property related information digitally.
In case of Estonia the interconnection of the land register to the e-Justice portal will be sustained
within the overall sustainability actions of the land register as an integral service of the land register to
20
the clients and colleagues residing outside its own territory. Also in Austria the modules for the
national side of the LRI connection will be maintained by the teams responsible for the AT Land
Register and for AT cross-judicial services.
The successful use cases from the partners will be collected over time and presented to the other
European Member States.
21
4. History of changes between your proposal and Annex I to the Grant
Agreement "Description of the Action"
Please state whether you have made any changes in the data entered in on-line forms in the
participant portal (which will become Part A of the Description of the Action) when compared to
Part B of the original proposal (Description of workpackages and activities).
Changes suggested in NO Section “Financial Information”: HU PMO “Direct
the Evaluation personnel costs declared as actual costs” were
Summary Report reduced after further examination of the tasks to be
undertaken by HU PMO resulted in lower estimated
costs (The “Requested grant” figure was changed
accordingly).
Section “Work Packages”: Efforts indicated (person
months) were changed to match the correct
EC formula (for ES REG: WP1-2, 4; PT IRN: WP1-
4). The efforts indicated for HU PMO (WP1-2) were
changed reflecting the reduced personnel costs and
applying the correct EC formula. HU PMO was
added as a beneficiary participating in WP4 (the
respective effort had initially been misallocated to
WP2).
Other changes YES Section “Deliverables”: Reduction and consolidation
of Deliverables as requested by the project officer
Section “Beneficiaries”: Beneficiary 1 short name
changed to “AT BMJ”
Changes for YES Extension of the project duration to 20 months.
Amendment Adaption of work packages, milestones and
Deliverables accordingly. Justification provided.
Please state whether you have made any changes in Part B of the Description of the Action when
compared to Part B of the original proposal (General Description of the project and applicant
organisation).
Changes suggested in YES 2.1 Objectives, impact & methodology: Adaption of
the Evaluation revised Deliverable plan; re-structured and expanded
Summary Report description of project results including measurable
data; description of long-term impact revised;
2.2 Cost Effectiveness: Justification of high WP1
costs due to anticipated changes in the project scope
during the project timespan;
2.2 Cost Effectiveness: Explanation of the budget
distribution between the partners;
3.1 Consortium cooperation: Underlining the
successful cooperation between AT BMJ and its
subcontractor for mitigating project management
risks.
3.2 Subcontracting: Extended description of
subcontracting for beneficiary AT BMJ
3.6 Ethics: Compliance with data protection;
3.6 Gender Mainstreaming: Extend description;
3.6 Dissemination: Social Network added; extended
description of dissemination strategy and activities
22
added; user group on prevention of money
laundering/terrorist financing as well as mortgage
financing added; target groups identified;
Other changes YES 1 Needs Analysis: List of use cases expanded
2.1 Impact: Deletion of phrases replicating user
benefits already mentioned in previous sections;
3 AT subcontractor: Company name removed
3.2 AT subcontractor: Company name removed;
3.8 Description of project impact moved to 2.1;
“AT BMVRDJ” renamed as “AT BMJ”
Changes for YES 2.4 Timetable adapted to project duration of 20
Amendment months
Note: Please note that changes to your original proposal should be limited to modifications
suggested in the Evaluation Summary Report (ESR). We strongly advise against any other changes
at this point as they may lead to the Commission considering the modified proposal as not compliant
with the one recommended for funding and terminating the grant agreement preparation. Should
you wish to introduce some modifications nevertheless (e.g. as a result of "force majeure" changes
that occurred since the date of your original proposal), these must be indicated in the table. Failure
to clearly signal any changes made to your proposal may lead to termination of the grant agreement
preparation or – at any point following the signature of a grant agreement – to the termination of the
grant agreement by the Commission. In accordance with Art. 34.3.1 (i)(ii).
23
Digitally sealed by the European Commission
Date: 2020.04.03 11:25:09 CEST
This document is digitally sealed. The digital sealing mechanism uniquely binds the
document to the modules of the Funding & Tenders Portal of the European
Commission, to the transaction for which it was generated and ensures its integrity and
authenticity.
Any attempt to modify the content will lead to a breach of the electronic seal, which can
be verified at any time by clicking on the digital seal validation symbol.