Memorandum of Understanding between the Ministry of Economic Affairs and
Employment of the Republic of Finland and the Ministry of Economic Affairs and
Communications of the Republic of Estonia
concerning cooperation on setting up additional liquefied natural gas (LNG) supplies in
Finland and Estonia
The Ministry of Economic Affairs and Employment of the Republic of Finland and the
Ministry of Economic Affairs and Communications of the Republic of Estonia,
hereinafter referred to collectively as ,,the Participants”:
Acknowledging:
O That the need for natural gas supplies in the whole region of Finland and the Baltic States,
hereinafter “the Region”, remains high in coming years;
O That Finland and Estonia are stili heavily dependent on the Russian natural gas supplies to
the Region;
O That with the Russian attack on Ukraine from 24th of February 2022, the risk of Russian gas
supply disruption in the Region has significantly risen suddenly and unexpectedly;
O The Region is highly vulnerable towards the disruption ofgas supplies from Russia;
O That the possibilities in Finland and Estonia for further diversification for gas supplies is
limited both in terms ofphysical capacity and trade options;
O That there is an immediate and necessary need to secure fuli gas supplies for Finland and
Estonia as soon as it is possible.
Recognising:
O The communication from the European Commission on the package RePowerEU,
according to which the European Union must end the dependency on Russian gas supplies
as soon as possible and well before 2030;
O The importance ofhaving independent gas supplies in Finland and Estonia for the economy
and society to function as efficiently and prosperous as possible;
O The need for an additional gas supply route for Finland and Estonia;
O The decision made by Estonian government to stop Russian gas imports as soon as possible
but not later than by the end of 2022.
Set an objective:
O To jointly charter a suitable FSRU (Floating Storage Regasification Unit) for the needs of
Finland and Estonia to:
o increase the diversification of gas supply in Finland and Estonia;
o increase independence on Russian gas supplies with a view to phase out of
the dependence on Russian gas supplies simultaneously with the added
diversified gas supplies as soon as it is possible.
O To build the necessary port facilities and on shore infrastructure for the FSRU both in
Finland and Estonia and to start preparatory works on both sites as soon as possible;
O To commission the FSRU by the end of the fourth quarter of 2022 in either Finland or
Estonia, depending on which site is first ready to accommodate the FSRU for the winter
period of 2022-23 and in a functionally appropriate portin Finland thereafter.
O To decide the possibility to use FSRU at Estonian side as an emergency back-up location
should it be necessary for ensuring Finnish and Estonian security of gas supply.
Have reached the following understanding:
Paragraph 1
Nature and scope of the Memorandum
(1) The Memorandum of Understanding (hereinafter M0U) sets out a legally non-binding
—
framework for cooperation on establishment and financing of additional gas supply routes in
the Finnish and Estonian gas market as soon as possible and targeting 1st ofNovember 2022
(hereinafter Joint Project).
—
(2) The Joint Project represents port facilities and on shore infrastructures in both countries and
ajointly chartered FSRU (Floating Storage Regasification Unit).
(3) The MoU outlines the roles of the Participants as well as the national Gas Transmission
System Operators.
(4) The MoU records a political intent alone. The said MoU is not intended to establish any
new legal commitments, or to replace or modify any existing legal obligations. The MoU
confers no new powers nor implies any financial commitments, ail commitments being satisfied
from existing resources.
(5) The MoU is intended to remain in effect and will he limited to the scope necessary for
implementation of the Joint Project.
Paragraph 2
Specifications of the Joint Project
(1) The Joint Project serves the purpose for developing a FSRU with an annual capacity of at
least 30 TWh.
(2) The location of the Joint Project will be in functionally approriate ports in Finland and
Estonia, located in the vicinity of the countries’ gas transmission systems and with the
permanent location for the jointly charted FSRU in Finland. However, for the winter period of
2022-23 the FSRU will be located in either Finland or Estonia, depending on which site is first
ready to accommodate the FSRU.
(3) Within the Joint Project, the Participants aim to carry through ail the necessary analysis that
are needed for the Joint Project.
(4) The Participants aim to set a financing model of the FSRU that is based on proportional
benefit of the country. However, both countries bear the costs of the port facilities and on shore
infrastructure of their own territory.
(5) The national Gas Transmission System Operators ofboth countries will be responsible for
securing the FSRU from the beginning of fourth quarter 2022.
Paragraph 3
Cooperation
(1) The Participants will co-operate to establish and maintain necessary and favourable
conditions for the impiementation of the Joint Project.
(2) National contact points are established to facilitate the impiementation of the Joint Project
and deal with any matters arising during the impiementation.
(3) The national contact point of Finland is the Ministry ofEconomic Affairs and Employment
of Finland or designated Authority by the Ministry.
(4) The national contact point of Estonia is the Ministry of Economic Affairs and
Communications or designated Authority by the Ministry.
(5) The Participants will establish a steering group consisting of at least two members
representing each Participant.
(6) The Participants wiII nominate the national Gas Transmission System Operators to prepare
practical implementation of the Joint Project.
The foregoing represents the understanding reached between the Participants on the matters
referred to in this MoU.
Signed in duplicate in Helsinki on ofApril 2022 in the English language.
For the Ministry ofEconomic Affairs and For the Ministry ofEconomic Affairs and
Employment ofthe Republic ofFinland Communications ofthe Republic of
Estonia
Mika Lintilä Taavi Aas
The Minister of Economic Affairs The Minister of
Economic Affairs and Infrastructure