Saatja: MARTIN Christine (CINEA) <
[email protected]>
Saadetud: 11.05.2022 15:59
Adressaat: MKM info <
[email protected]>
Koopia: (RB Rail A.S) <
[email protected]>
Teema: Notification of the application of force majeure in financing
agreements for Rail Baltica construction projects for actions: 2014-EU-
TMC-0560-M; 2016-EU-TMC-0116-M and 2019-EU-T... - Ares(2022)3590681
Manused: LET_220504_Reply to EE force majeure letter_MJ.pdf
Please find attached the document Ares(2022)3590681 from JENSEN Morten
(CINEA.B.01) dated11/05/2022.
Ref. Ares(2022)3590681 - 11/05/2022
EUROPEAN CLIMATE, INFRASTRUCTURE AND
ENVIRONMENT EXECUTIVE AGENCY (CINEA)
CINEA.B - Sustainable networks and investments
B.1 - CEF Transport: Northern Europe, Austria + MoS and ERTMS
Brussels
CINEA.B.B1.2/BO/cm
BY EMAIL ONLY Ministry of Economic Affairs and
Communications
Mr. Ahti Kuningas
Deputy Secretary General for
Transport
Suur-Ameerika 1
10122 - Tallinn
ESTONIA
[email protected]
Your Ref.: 15.03.2022 No 24.5-6/22-0002/1963
Subject: Notification of the application of force majeure in financing agreements
for Rail Baltica construction projects for Actions: 2014-EU-TMC-0560-
M; 2016-EU-TMC-0116-M and 2019-EU-TMC-0280-W
Dear Mr Kuningas,
We took note of your letter of 15/03/2022, ref: No 24.5-6/22-0002/1963 in which you
notified the Agency about a potential force majeure situation for the below Rail Baltica
Actions, which is due to the war in Ukraine:
• INEA/CEF/TRAN/M2014/1045990, Action code 2014-EU-TMC-0560-M
• INEA/CEF/TRAN/M2016/1360716 Action code 2016-EU-TMC-0116-M
• INEA/CEF/TRAN/M2019/2098073 Action code. 2019-EU-TMC-0280-W
We acknowledge that the war has a likely negative effect on the Rail Baltica in Estonia,
in different ways, e.g. on supply chains, labour shortage, etc. as it has in other Member
States.
We are pleased to note that no suspension of the above Actions was requested and that
your Ministry together with RB Estonia are doing your utmost to continue to complete
the tasks and activities of the Grant Agreements, despite the challenges. We expect that
you involve RB Rail AS, the coordinator of the Project, in finding the best ways to
continue the implementation.
European Climate, Infrastructure and Environment Executive Agency (CINEA), B-1049 Brussels, BELGIUM
[email protected]
In the CEF Committee meeting of 07/04/2022 there was a constructive exchange of view
about the difficult situation due to the war in Ukraine. We are following attentively the
evolution of the situation, however at this stage its impact is not yet clear and it is
difficult to estimate the concrete consequences for the implementation of the grant
agreements. We invite the Rail Baltica beneficiaries together to assess the situation and
develop possible mitigation measures and options in the coming months.
Let me assure you that CINEA will be available to support beneficiaries in finding
solutions. As a starting point, and as mentioned in our meeting of 31/03/2022 in Brussels,
there is possibility to extend the end date of the Rail Baltica Actions to 31/12/2024, on a
case-by-case basis, where necessary and justified, in compliance with the terms of the
Grant Agreement.
Yours faithfully,
(e-signed)
Morten JENSEN
Head of Unit
Copies: RB Rail AS -
[email protected]
DG Move B1 -
[email protected]
2
Electronically signed on 11/05/2022 12:36 (UTC+02) in accordance with Article 11 of Commission Decision (EU) 2021/2121