Tere!
Tulede vahetus on võimalik selliselt korraldada, et täiesti pimedaks korsten ei jää üldse. Ühel tasapinnal
põleksid kõik valgustid ja teisel tasapinnal jääks 2-3 valgustit põlema. Allpool Utilitase ja Teci selgitused.
Artur Keerov
+372 50 34 083
[email protected]
From: Vladislav Mašatin [mailto:
[email protected]]
Sent: Thursday, February 1, 2018 3:54 PM
To: Linas Baliuckas <
[email protected]>;
[email protected]
Subject: RE: Kadaka tee 181 korstna lennuohutuse valgustuse uuendamine
Hi!
Confirming Linas letter. Flight department may write their requirements also, I see that change process
might be done in several ways, it is just question of agreement between us and work producer.
Vladislav Mašatin
Tootmisjuht
AS Utilitas Tallinn
Tel: +372 610 7458
Mob: +372 520 9454
Punane 36, 13619 Tallinn
[email protected]
www.utilitas.ee
From: Linas Baliuckas [mailto:
[email protected]]
Sent: Thursday, February 1, 2018 3:16 PM
To:
[email protected]
Cc: Vladislav Mašatin
Subject: RE: Kadaka tee 181 korstna lennuohutuse valgustuse uuendamine
Importance: High
Hi,
Just now talk with the Client regarding Your questions.
Regarding terms of construction Client at the moment do not know exactly but roughly terms will be
2018-05 – 2018-09, anyway exact data’s, when will be selected Contractor for these works will be agreed
between Utilitas and Flight department separately.
Regarding lamps exchange, so maintenance platforms which also will be changed is installed (and new
designed at same levels) connected with the bolts. So exchange of platforms works will be done peace by
peace. Due to such works sequence air craft warning lamps, we think will be replaced by so that on each
level during exchange period will be two-three lamps in operation and other replaced, after that changed
other ones.
Due to such approach chimney will be not left without warning lights at all, just for some period will be
with limited lamps quantity.
Cables for lamps electricity supply will be installed also parallelly to existing one and just during day time
reconnected this will not disturb lamps operation during night.
Linas Baliuckas
Projektų vadovas
Project manager
UAB TEC Industry
Pramonės pr. 6, Kaunas, LT-51267 Lietuva
Mob. +37061497936
[email protected] / www.tec.lt
From: Andres Lainoja [mailto:
[email protected]]
Sent: Thursday, February 1, 2018 12:56 PM
To:
[email protected]
Subject: RE: Kadaka tee 181 korstna lennuohutuse valgustuse uuendamine
Tere!
Palun infot, kui pikk aeg jääb vanade tulede eemaldamise ja uute paigaldamise ja sisselülitamise vahele?
Kuna tegu on tõusu- ja maandumiskoridori alla jääva domineeriva takistusega, on oluline teada, kas
planeeritavalt on korsten mingil ööl pime, et saaksime piloote hoiatada.
Ette tänades
Andres Lainoja
Lennuliiklusteeninduse ja lennuväljade osakonna vaneminspektor