CERTIFICATION OF THE MEMBER STATE * (applicable only for ASR and for beneficiaries established in the European Union) Name Position Entity Telephone Nº E-mail In compliance with Article II.23.1 ( or SESAR FPA II.23.1b) of the GA, it is certified that the information provided by the following Beneficiary( ies ) in the ASR is full, reliable and true. Estonian Road Administration Date and signature Stamp ( optional) * In line with the terms of Art. 22 of the CEF Regulation
ASR-2020-2018-EE-TM-0029-M-
European
Dynamic traffic and truck parking
Commission
Innovation and management
Reporting period: 1 June 2019 - 31
Networks Executive
Agency (INEA)
December 2019
Connecting Europe
Facility
1. INFORMATION ON THE ACTION
Grant Agreement Nº INEA/CEF/TRAN/M2018/1767529
Action number 2018-EE-TM-0029-M
Action title Dynamic traffic and truck parking management
PCI (for energy and
synergy only)
Author of the report
Name Mari-Liis Sepp
Position Project manager
Entity Estonian Road Administration
Telephone Nº +372 5850 2984
E-mail
[email protected]
Reporting period: 1 June 2019 - 31 December 2019
2. INFORMATION ON THE PROGRESS OF THE
ACTION (GA II.23.1.1.c or SESAR FPA II.23.1b.c)
2.1. Overall progress of the Action until the end of the previous reporting
period
Overall
Planned dates (GA) Previous ASR dates Actual dates
technical
progress
achieved at
the end of
Start End Start End Start End the
previous
reporting
period (%)*
01/06/2019 31/12/2023 01/06/2019 31/12/2023 0.00
*Please explain how the percentage of the progress achieved has been estimated/calculated
Calculated according to Annex III of the "Guidance for poor or partial completion": SUM(Technical
Progress Per Activity Per Year * (GA EU Contribution Per Activity / Total GA EU Contribution)).
Overview of progress since the start of the Action
The overview should include a description of the actual progress of the Action and per
activity since the start of the Action until at the end of the previous reporting period,
referring to the main issues, milestones and events that affected the progress.
Activities 1 (project management), 2 (communicationd and dissemination), 3
(transport and ITS study) started in the previous reporting period and are currently
ongoing. In these activities the following milestones have been finished:
PM and SG meeting No 1: planned date 30/06/2019; actual date 20/11/2019
Project communication plan: planned date 31/10/2019; actual date 14/10/2019
Publication of Tender Transport and ITS study report: planned date 01/11/2019; actual
date 02/12/2019
Project opening press/kick-off meeting event: planned date 31/12/2019; actual date
20/11/2019
2018-EE-TM-0029-M_ASR2020_1_draft_20200205_1108 2
Reporting period: 1 June 2019 - 31 December 2019
PM and SG joint meeting no 2 was planned on 31/12/2019 but actual date will be in
the next reporting period. The delay of the first PM and SG meeting was caused due to
the fact that the project manager was hired in September 2019. Because of the first
meeting date was nearly end of previous reporting period the second meeting will be
postponed into the next year. Due to the fact that the project manager was hired in
September 2019 it also cause a small delay of the Transport and ITS study Tender
Publication.
There are not any new taskes that have not initially foreseen in the Action nor any
deviations to the Action's objectives.
2018-EE-TM-0029-M_ASR2020_1_draft_20200205_1108 3
Reporting period: 1 June 2019 - 31 December 2019
2.2. Progress per activity
Overall technical
progress achieved
Previous ASR Start/end
Activity 1 Title Planned Start/End date (GA) Actual Start/End date until the end of the
dates
previous reporting
period (%)*
Project management 01/06/2019 31/12/2023 01/06/2019 31/12/2023 4.00
*Please explain how the percentage of the progress achieved has been estimated/calculated
SUM(Technical Progress Per Activity Per Year * (GA EU Contribution Per Activity / Total GA EU Contribution))
Milestone
Title1 Planned completion date (GA) Previous ASR date Actual completion date Reached (Y/N)
no
PM and SG joint meeting
1 30/06/2019 20/11/2019 Yes
No 1
Explanation for any deviation from planned completion date
The project manager was hired in September 2019. There was not a project manager nor actual need to hold PM and SG joint meeting No 1 before that.
PM and SG joint meeting
2 31/12/2019 30/04/2020 No
No 2
Explanation for any deviation from planned completion date
2018-EE-TM-0029-M_ASR2020_1_draft_20200205_1108 4
Reporting period: 1 June 2019 - 31 December 2019
PM and SG joint meeting No 1 was held on 20/11/2019 and there was no need to call another meeting this year as the first one was delayed.
PM and SG joint meeting
3 30/06/2020 30/09/2020 No
No 3
Explanation for any deviation from planned completion date
PM and SG joint meeting No 2 will be held on 30/04/2020 and there is no need to call another meeting two months later due to the delay of the first meeting.
PM and SG joint meeting
4 31/12/2020 31/12/2020 No
No 4
Explanation for any deviation from planned completion date
PM and SG joint meeting
5 30/06/2021 30/06/2021 No
No 5
Explanation for any deviation from planned completion date
PM and SG joint meeting
6 31/12/2021 31/12/2021 No
No 6
Explanation for any deviation from planned completion date
PM and SG joint meeting
7 30/06/2022 30/06/2022 No
No 7
Explanation for any deviation from planned completion date
PM and SG joint meeting
8 31/12/2022 31/12/2022 No
No 8
Explanation for any deviation from planned completion date
PM and SG joint meeting
9 30/06/2023 30/06/2023 No
No 9
Explanation for any deviation from planned completion date
2018-EE-TM-0029-M_ASR2020_1_draft_20200205_1108 5
Reporting period: 1 June 2019 - 31 December 2019
PM and SG joint meeting
10 31/12/2023 31/12/2023 No
No 10
Explanation for any deviation from planned completion date
2018-EE-TM-0029-M_ASR2020_1_draft_20200205_1108 6
Reporting period: 1 June 2019 - 31 December 2019
Overall technical
progress achieved
Previous ASR Start/end
Activity 2 Title Planned Start/End date (GA) Actual Start/End date until the end of the
dates
previous reporting
period (%)*
Communication and
01/06/2019 31/12/2023 01/06/2019 31/12/2023 6.00
dissemination
*Please explain how the percentage of the progress achieved has been estimated/calculated
SUM(Technical Progress Per Activity Per Year * (GA EU Contribution Per Activity / Total GA EU Contribution))
Milestone
Title1 Planned completion date (GA) Previous ASR date Actual completion date Reached (Y/N)
no
Project opening press /
11 31/12/2019 20/11/2019 Yes
kick off meeting event
Explanation for any deviation from planned completion date
Actual completion date was before planned completition date.
Project communication
12 31/10/2019 14/10/2019 Yes
plan
Explanation for any deviation from planned completion date
Actual completion date was before planned completition date.
Communication support
13 31/05/2020 31/05/2020 No
materials
2018-EE-TM-0029-M_ASR2020_1_draft_20200205_1108 7
Reporting period: 1 June 2019 - 31 December 2019
Explanation for any deviation from planned completion date
Project finalization press /
14 31/10/2023 31/10/2023 No
final meeting event
Explanation for any deviation from planned completion date
2018-EE-TM-0029-M_ASR2020_1_draft_20200205_1108 8
Reporting period: 1 June 2019 - 31 December 2019
Overall technical
progress achieved
Previous ASR Start/end
Activity 3 Title Planned Start/End date (GA) Actual Start/End date until the end of the
dates
previous reporting
period (%)*
Transport and ITS study
for preparation of pilot 1 01/09/2019 01/09/2020 02/09/2019 31/01/2021 0.00
and 2
*Please explain how the percentage of the progress achieved has been estimated/calculated
SUM(Technical Progress Per Activity Per Year * (GA EU Contribution Per Activity / Total GA EU Contribution))
Milestone
Title1 Planned completion date (GA) Previous ASR date Actual completion date Reached (Y/N)
no
Publication of Tender
15 Transport and ITS study 01/11/2019 02/12/2019 Yes
report
Explanation for any deviation from planned completion date
Project manager was hired in September 2019 which was the reason the tender was published a month later.
Assessment of offers
16 Transport and ITS study 01/01/2020 10/01/2020 Yes
report
Explanation for any deviation from planned completion date
Due to the holidays period the assessment process was pushed forward.
2018-EE-TM-0029-M_ASR2020_1_draft_20200205_1108 9
Reporting period: 1 June 2019 - 31 December 2019
Contract signed Transport
17 01/02/2020 23/01/2020 Yes
and ITS study report
Explanation for any deviation from planned completion date
Since there was only one tenderer the process of signing the contract was shorter than expected.
Transport and ITS study
18 01/06/2020 01/06/2020 No
interim report
Explanation for any deviation from planned completion date
Transport and ITS study
19 01/09/2020 01/09/2020 No
final report
Explanation for any deviation from planned completion date
2018-EE-TM-0029-M_ASR2020_1_draft_20200205_1108 10
Reporting period: 1 June 2019 - 31 December 2019
Overall technical
progress achieved
Previous ASR Start/end
Activity 4 Title Planned Start/End date (GA) Actual Start/End date until the end of the
dates
previous reporting
period (%)*
Pilot implementation 1:
dynamic traffic
01/09/2020 01/06/2022 01/09/2020 01/06/2022 0.00
management system in
E265 section km 10-20
*Please explain how the percentage of the progress achieved has been estimated/calculated
SUM(Technical Progress Per Activity Per Year * (GA EU Contribution Per Activity / Total GA EU Contribution))
Milestone
Title1 Planned completion date (GA) Previous ASR date Actual completion date Reached (Y/N)
no
Publication of tender Pilot
20 01/10/2020 01/10/2020 No
1
Explanation for any deviation from planned completion date
Assessment of offers Pilot
21 31/12/2020 31/12/2020 No
1
Explanation for any deviation from planned completion date
2018-EE-TM-0029-M_ASR2020_1_draft_20200205_1108 11
Reporting period: 1 June 2019 - 31 December 2019
22 Contract signed Pilot 1 31/01/2021 31/01/2021 No
Explanation for any deviation from planned completion date
Pilot 1 implemented
23 01/06/2022 01/06/2022 No
solution is in operation
Explanation for any deviation from planned completion date
2018-EE-TM-0029-M_ASR2020_1_draft_20200205_1108 12
Reporting period: 1 June 2019 - 31 December 2019
Overall technical
progress achieved
Previous ASR Start/end
Activity 5 Title Planned Start/End date (GA) Actual Start/End date until the end of the
dates
previous reporting
period (%)*
Pilot implementation 2:
smart (safe and secure)
01/09/2020 01/06/2022 01/09/2020 01/06/2022 0.00
truck parking area in E265
km 1,5
*Please explain how the percentage of the progress achieved has been estimated/calculated
SUM(Technical Progress Per Activity Per Year * (GA EU Contribution Per Activity / Total GA EU Contribution))
Milestone
Title1 Planned completion date (GA) Previous ASR date Actual completion date Reached (Y/N)
no
Publication of tender Pilot
24 01/10/2020 01/10/2020 No
2
Explanation for any deviation from planned completion date
Delivery of the scoping
25 decision and subsequent 31/12/2020 31/12/2020 No
environmental permits
Explanation for any deviation from planned completion date
2018-EE-TM-0029-M_ASR2020_1_draft_20200205_1108 13
Reporting period: 1 June 2019 - 31 December 2019
Assessment of offers Pilot
26 31/12/2020 31/12/2020 No
2
Explanation for any deviation from planned completion date
27 Contract signed Pilot 2 31/01/2021 31/01/2021 No
Explanation for any deviation from planned completion date
Pilot 2 implemented
28 01/06/2022 01/06/2022 No
solution is in operation
Explanation for any deviation from planned completion date
2018-EE-TM-0029-M_ASR2020_1_draft_20200205_1108 14
Reporting period: 1 June 2019 - 31 December 2019
Overall technical
progress achieved
Previous ASR Start/end
Activity 6 Title Planned Start/End date (GA) Actual Start/End date until the end of the
dates
previous reporting
period (%)*
Implementation of
dynamic traffic
management system E265 01/11/2021 01/09/2023 01/11/2021 01/09/2023 0.00
in sections km 0-10 and
km 20-30
*Please explain how the percentage of the progress achieved has been estimated/calculated
SUM(Technical Progress Per Activity Per Year * (GA EU Contribution Per Activity / Total GA EU Contribution))
Milestone
Title1 Planned completion date (GA) Previous ASR date Actual completion date Reached (Y/N)
no
Publication of tender E265
29 01/11/2021 01/11/2021 No
km 0-10 and km 20-30
Explanation for any deviation from planned completion date
Assessment of offers E265
30 01/02/2022 01/02/2022 No
km 0-10 and km 20-30
Explanation for any deviation from planned completion date
2018-EE-TM-0029-M_ASR2020_1_draft_20200205_1108 15
Reporting period: 1 June 2019 - 31 December 2019
Contract signed for E265
31 30/04/2022 30/04/2022 No
km 0-10 and km 20-30
Explanation for any deviation from planned completion date
E265 section solution km
32 0-10 and km 20-30 is in 01/09/2023 01/09/2023 No
operation
Explanation for any deviation from planned completion date
2018-EE-TM-0029-M_ASR2020_1_draft_20200205_1108 16
Reporting period: 1 June 2019 - 31 December 2019
2.3 If total actual costs/units deviates >5% compared to latest Grant
Agreement in force, please explain why
Not applicable
2.4. Description of the Action's and activities' progress planned in the on-
going reporting period and until the end of implementation of the Action
a) Provide a description of the planned progress of the activities in the on-going
reporting period and, where applicable, beyond the on-going reporting period up until
the end of the implementation of the Action (if the on-going reporting period is not the
last one).
b) Highlight and explain any deviation (e.g. on objectives of the Action, the completion
of the planned activities, the cost-breakdown, Action's end date, etc.) in comparison to
the latest grant agreement in force and, where applicable, latest ASR.
c) Identify any expected/foreseen risk(s) that may challenge the actual end date of the
Action and the associated mitigation plan(s).
a) Provide a description of the planned progress of the activities in the on-going
reporting period and, where applicable, beyond the on-going reporting period up until
the end of the implementation of the Action (if the on-going reporting period is not the
last one).
In the on-going period (from 01/01/2020 until 31/12/2020) there are three main
activities: ITS study and preliminary project which will be done during this period and
after that preparations of pilots I and II. In addition, there will be made communication
support materials and environmental impact assessment leading to a permit.
In the next period (from 01/01/2021 until 31/12/2021) the implementation of pilot I
and II are the main activities, also the preparation of tender E265 km 0-10 and 20-30
is on-going.
After that (from 01/01/2022 until 31/12/2022) the implementation of E265 km 0-10
and 20-30 is on-going and pilot I and II will be finished.
In the last period (from 01/01/2023 until 31/12/2023) the implementation of E265 km
0-10 and 20-30 will be done and the project finalisation press/final meeting event will
be held.
b) Highlight and explain any deviation (e.g. on objectives of the Action, the completion
2018-EE-TM-0029-M_ASR2020_1_draft_20200205_1108 17
Reporting period: 1 June 2019 - 31 December 2019
of the planned activities, the cost-breakdown, Action's end date, etc.) in comparison to
the latest grant agreement in force and, where applicable, latest ASR.
Pilot II (truck parking area) is divided into two parts: design project and building the
area. The design part starts in on-going period and the building process starts next
period (from 01/01/2021 until 31/12/2021). Since the parking area needs a building
permit the preparations before building are more time-consuming than expected.
Nevertheless, the end time of pilot II implementation is still as stated in the GA. Any
other deviations are not foreseen.
c) Identify any expected/foreseen risk(s) that may challenge the actual end date of the
Action and the associated mitigation plan(s).
Only the process of building permit may take more time than expected and thus
challenge the actual end date of the activities. Everything is done that the end date of
the Action will not be late.
2018-EE-TM-0029-M_ASR2020_1_draft_20200205_1108 18
Reporting period: 1 June 2019 - 31 December 2019
3. VISIBILITY OF UNION FUNDING (GA II.23.1.1.i or
SESAR FPA II.23.1b.i)
What measures have been taken within the previous reporting period to
publicise the Action, including EU funding (GA II.7.1)?
According to the communication plan the project was introduced to public at the kick-
off meeting and with press release in November 2019. Before that the map and logo as
visual aid were designed which are currently with CEF logo published on ERA website.
In addition, the project was published also in social media.
During the kick-off event, the billboard and presentations had CEF logo, it is also shown
on ERA website https://www.mnt.ee/eng/roads/tallinn-ring-road-e265-its-project.
4. OTHER SOURCES OF EUROPEAN UNION FUNDS
(CEF-E and Synergy only, GA II.23.1.1.m )
If applicable, provide information about other sources of EU funds (CEF,
ERDF, Cohesion Fund, H2020, TEN, EEPR, EIPA, etc.) used for the project of
common interest (e.g. previous or subsequent phases not covered by the
Grant Agreement).
Not applicable
2018-EE-TM-0029-M_ASR2020_1_draft_20200205_1108 19
Reporting period: 1 June 2019 - 31 December 2019
5. COMPLIANCE WITH EU LEGISLATION (GA.II.23.1.1g
and h, or SESAR FPA II.23.1b.g and h)
5.1. Overview of environmental aspects, compliance with EU and national
legislation, issues during the implementation of the Action and measures
taken.
According to the Grant Agreement the implementation of this Activity is subject to the
acquisition of the necessary environmental permission, which will have to be requested
and obtained in advance by the beneficiary. The environmental permission will be done
before the start of the physical intervention during the on-going reporting period (from
01/01/2020 until 31/12/2020) according to the GA.
5.2. Where relevant, information on the compliance with EU legislation
notably on procurement:
- information on the contracts awarded or planned for the implementation of
the Action and on compliance with the requirements set out in GA II.9 and
II.10
- regarding other matters, notably public procurement, competition,
regulatory matters, (CEF-E only) the update of the CBCA decision, etc.
The project’s ITS study and preliminary project tender was closed on 6th January.
There was only one bid from Roadplan OÜ and Warren Concrete OÜ (as a joint bid) and
it qualified as a successful bidder with the price 86 768 € +VAT 20%. The type of
tendering procedure was open procedure and award date was 23.01.2020. All the
information is also in the following link (the procurement register):
https://riigihanked.riik.ee/rhr-web/#/procurement/1622190/general-info.
2018-EE-TM-0029-M_ASR2020_1_draft_20200205_1108 20
Reporting period: 1 June 2019 - 31 December 2019
6. IMPLEMENTATION SCHEDULE, GOVERNANCE
AND MONITORING, OTHER RELEVANT
ADMINISTRATIVE PROVISIONS (GA II.23.1.1.k and l, or
SESAR FPA II.23.1b.k and l)
6.1. In the first ASR, information on implementation schedule, such as critical
path, key performance rates and risk analysis; in subsequent ASR, information
on any modifications and, if applicable, on the progress of the implementation
of the arrangements referred to in previous ASR. If there are changes in the
Action timetable as compared to the latest planning (Grant Agreement or
previous ASR), attach an updated Gantt chart.
Action’s implementation schedule is attached as an Excel file under the name
“timetable”. There is one critical bath which is the whole project’s milestones and
timeline. The Action’s risk analysis is also attached under the name “risk assessment
grid by activities” which was also in the proposal and updated if needed.
2018-EE-TM-0029-M_ASR2020_1_draft_20200205_1108 21
Reporting period: 1 June 2019 - 31 December 2019
Action's implementation technical progress (cumulated %)
2019 2020 2021 2022 2023
Action Current Current Current Current Current
Previous ASR Previous ASR Previous ASR Previous ASR Previous ASR
level ASR ASR ASR ASR ASR
N/A 0 N/A 6 N/A 50 N/A 88 N/A 100
Current Current Current Current Current
Activity Previous ASR Previous ASR Previous ASR Previous ASR Previous ASR
ASR ASR ASR ASR ASR
1
N/A 4 N/A 27 N/A 52 N/A 77 N/A 100
2
N/A 6 N/A 26 N/A 60 N/A 80 N/A 100
3
N/A 0 N/A 62 N/A 100 N/A 100 N/A 100
4
N/A 0 N/A 0 N/A 50 N/A 100 N/A 100
5
N/A 0 N/A 0 N/A 67 N/A 100 N/A 100
6
N/A 0 N/A 0 N/A 0 N/A 50 N/A 100
All the activities and the Action will achieve 100% of technical progress by their actual end dates
2018-EE-TM-0029-M_ASR2020_1_draft_20200205_1108 22
Reporting period: 1 June 2019 - 31 December 2019
6.2. In the first ASR, information on governance and monitoring of the Action,
such as organizational structure, internal coordination, communication and
reporting, and decision making process; in subsequent ASR, information on
any modifications and, if applicable, on the progress of the implementation of
the arrangements referred to in previous ASR.
The ERA in-house project team consists of the following ERA employees:
• Project manager – is responsible for coordinating and organizing project activities
in Estonia. Regular reporting to INEA.
• Head of traffic management centre – implementing traffic and other technical
solutions in the ITS area of the project.
• Financial controller – accounting for project costs, arranging bridge financing and
advising on the management of expense receipts.
• IT architect – preparation of project IT solutions and architectural requirements
and implementation monitoring.
• Communication expert – arranging public communication for the project.
The ERA in-house team has monthly meetings. Depending on the progress of the
project and which Activities are on-going, the necessary team members will be involved
with the meetings. In addition, other support staff will be included if necessary.
During the period which have contractors project manager will attend the weekly
meetings with them and brings information to the in-house team, if necessary, other
will attend the meeting as well.
In ERA there is also weekly briefing between the departments where information about
the project will be discussed if necessary.
6.3. In the first ASR, information on other relevant administrative provisions,
such as quality controls and audits; in subsequent ASR, information on any
modifications and, if applicable, on the progress of the implementation of the
arrangements referred to in previous ASR.
There aren’t any extra quality control measures in ERA. Although, a process map (for
example the procurement process describes which activities are in the process and how
they should be done) is similar to quality standard and it is followed. This Action hasn’t
been audited.
ANNEX: Financial information (GA II.23.1.1.d to f or SESAR FPA II.23.1b.d to f)
2018-EE-TM-0029-M_ASR2020_1_draft_20200205_1108 23
Reporting period: 1 June 2019 - 31 December 2019
CERTIFICATION OF THE MEMBER STATE*
(applicable only for ASR and for beneficiaries established in the European
Union)
Name
Position
Entity
Telephone Nº
E-mail
In compliance with Article II.23.1 (or SESAR FPA II.23.1b) of the GA, it is
certified that the information provided by the following Beneficiary(ies) in
the ASR is full, reliable and true.
Estonian Road Administration
Date and
signature
Stamp (optional)
* In line with the terms of Art. 22 of the CEF Regulation
2018-EE-TM-0029-M_ASR2020_1_draft_20200205_1108 24
REQUEST OF FURTHER PRE-FINANCING PAYMENT
INEA/CEF/TRAN/M2018/1
Grant Agreement Nº
767529
Action number 2018-EE-TM-0029-M
Dynamic traffic and truck
Action title
parking management
Estonian Road
Beneficiary name
Administration
Financial information for the Action
A. Maximum EU contribution (Art. 3) 1,900,000.00 €
B. Pre-financing rate (Art. 4.1.2) 40.00 %
C. Maximum pre-financing payment (Art. 4.1.2)
760,000.00 €
(=B*A)
D. Maximum ceiling for the sum of pre-financing
1,520,000.00 €
and interim payments (Art 4.1.3) (=80%*A)
E. Sum of previous pre-financing payments 6,000.00 €
F. Sum of interim payments 0.00 €
Dear Sirs,
Along with the submission of the 2020 ASR for the Action in subject, we hereby
submit a request for further pre-financing. Please find enclosed:
the amount of the previous pre-financing used to cover costs of the Action,
the amount of the requested further pre-financing;
the allocation of the amounts to be paid to each beneficiary and the
methodology used (if applicable)
the financial guarantees (if applicable)
2018-EE-TM-0029-M_ASR2020_1_draft_20200205_1108_Estonian Road
Administration
ENCLOSED
Amount of the previous pre-financing used to cover costs of the Action
G. Total estimated direct eligible costs incurred until the end of
the previous reporting period 11,634.89 €
H. 70% of previous pre-financing payments (=70%*E) 4,200.00 €
Condition of 70% fulfilled (G>=H) Yes
I. Reduction of further pre-financing, if G<H (= H-G) 0.00 €
Amount of the requested further pre-financing
J. Total estimated direct costs eligible declared
until the end of the on-going current report
period 222,634.89 €
K. Total cumulated financing needs until the
end of the on-going current report period 111,317.45 €
L. Further pre-financing payment (=B*K-E)
38,526.98 €
L1. Revised further pre-financing payment if the
condition of the 70% is not fulfilled – article
II.24.1.3 (L-I) 38,526.98 €
L2. Revised further pre-financing if the total
pre-financing exceeds the maximum pre-
financing payment (E+L1<=C) 38,526.98 €
L3. Revised further pre-financing if the sum of
the pre-financings and interim payments
exceeds the ceiling (E+F+L2<=D) 38,526.98 €
M. Final further pre-financing to be paid (=L3) 38,526.98 €
2018-EE-TM-0029-M_ASR2020_1_draft_20200205_1108_Estonian Road
Administration
Indrek Gailan
Majandus- ja
Kommunikatsiooniministeerium
[email protected] Meie 07.02.2020 nr 1-21/20/7297-1
Suur-Ameerika 1
10122, Tallinn
Riigi kinnituskiri projekti vahearuandele
Seoses Tallinna ringtee „Dynamic traffic and truck parking management” projektiga peab
Maanteeamet esitama eelmise perioodi (juuni 2019 kuni detsember 2019) vahearuande, mille
üheks osaks on riigi kinnituskiri. Palume tutvuda vahearuande raporti ja selle lisadega ning seejärel
Majandus- ja Kommunikatsiooniministeeriumi esindajal täita ja käsitsi allkirjastada kinnituskiri
(dokument pealkirjaga „MS certification ASR_1”) ning saata paberkujul Maanteeametile.
Lugupidamisega
(allkirjastatud digitaalselt)
Andres Urm
juhataja
taristu arendamise osakond
Lisad: Report ASR_1, Request of further pre-financing payment_Estonian Road Administration
ASR_1, Financial Annex ASR_1, MS certification ASR_1
Mari-Liis Sepp
58502984
[email protected]
Teelise 4 / 10916 Tallinn / 6119 300 / Registrikood 70001490 / www.mnt.ee /
[email protected], 620 1200 (kliendiinfo) /
[email protected]; 611 9300 (teedealased küsimused)