EUROPEAN COMMISSION
Brussels, 23.9.2022
C(2022) 6856 final
SENSITIVE*: COMP Operations
Subject: State Aid SA.103936 (2022/N) – Estonia
TCF: Support for investments in the food industry to ensure security
of energy supply
Excellency,
1. PROCEDURE
(1) By electronic notification of 1 August 2022, Estonia notified aid in the form of
limited amounts of aid (Regulation of the Ministry of Rural Affairs "Support for
investments in the food industry to ensure security of energy supply", the
“measure”) under the Temporary Crisis Framework for State aid measures to
support the economy following the aggression against Ukraine by Russia (the
“Temporary Crisis Framework”)1. Estonia provided additional information on 12
August, 9 and 13 September 2022.
(2) Estonia exceptionally agrees to waive its rights deriving from Article 342 of the
Treaty on the Functioning of the European Union (“TFEU”), in conjunction with
Article 3 of Regulation 1/19582 and to have this Decision adopted and notified in
English.
*
Distribution only on a 'Need to know' basis - Do not read or carry openly in public places. Must be
stored securely and encrypted in storage and transmission. Destroy copies by shredding or secure
deletion. Full handling instructions: https://europa.eu/!db43PX
1
Communication from the Commission on the Temporary Crisis Framework for State aid measures to
support the economy following the aggression against Ukraine by Russia (OJ C 131 I, 24.3.2022, p.
1), as amended by Commission Communication C/2022/5342 (OJ C 280, 21.7.2022, p. 1).
2
Regulation No 1 determining the languages to be used by the European Economic Community (OJ
17, 6.10.1958, p. 385).
Urmas Reinsalu
Välisminister
Islandi väljak 1
15049 Tallinn
EESTI/ESTONIA
Commission européenne/Europese Commissie, 1049 Bruxelles/Brussel, BELGIQUE/BELGIË - Tel. +32 22991111
2. DESCRIPTION OF THE MEASURE
(3) Estonia considers that the Russian aggression against Ukraine, the sanctions
imposed by the European Union (EU) and its international partners and the
counter-measures taken by Russia (‘the current crisis’) so far affects the real
economy. The current crisis created significant economic uncertainties, disrupted
trade flows and supply chains and led to exceptionally large and unexpected price
increases, especially in natural gas and electricity, but also in numerous other
input and raw materials and primary goods, including in the agri-food sector.
Estonia considers that the food and beverages industries are severely impacted by
the current crisis: their production process is heavily dependent on electricity and
gas3, whose prices are currently 3.6 and respectively 4.3 times higher than the
same period of 20214. The measure aims to remedy the liquidity shortage faced
by undertakings in the food and beverages sectors that are directly or indirectly
affected by the serious disturbance of the economy caused by the Russian
aggression against Ukraine, the sanctions imposed by the EU or by its
international partners, as well as by the economic counter measures taken so far
by Russia, and thereby to support investments to ensure security of energy supply.
(4) Estonia confirms that the aid under the measure is not conditioned on the
relocation of a production activity or of another activity of the beneficiary from
another country within the EEA to the territory of the Member State granting the
aid. This is irrespective of the number of job losses actually occurred in the initial
establishment of the beneficiary in the EEA.
(5) The compatibility assessment of the measure is based on Article 107(3)(b) TFEU,
in light of sections 1 and 2.1 of the Temporary Crisis Framework.
2.1. The nature and form of aid
(6) The measure provides aid in the form of direct grants.
2.2. Legal basis
(7) The legal basis for the measure is the Regulation of the Ministry of Rural Affairs
"Support for investments in the food industry to ensure security of energy supply,
(‘Toiduainetööstuse investeeringutoetus energia varustuskindluse tagamiseks’,
the “legal basis”), adopted on 16 August 2022.
2.3. Administration of the measure
(8) The Agricultural Registers and Information Board (“ARIB”) is responsible for
administering the measure.
3
Estonia submits that in the food, beverages and tobacco sector, the final consumption of natural gas
and electricity represents 77-80% of the total energy final consumption (Source: KE0240: ENERGY
BALANCE SHEET by Year, Indicator and Type of fuel/energy).
4
Source: Gas Market Overview Q2 2022. Estonia submits that the country does not produce any gas
and its whole demand for gas is met by importing from Russia and Lithuania. Import of gas from
Russia to Europe has been significantly reduced, from April 2022 onwards, to approximately a third
of the maximum capacity.
2
2.4. Budget and duration of the measure
(9) The estimated budget of the measure is EUR 14 million.
(10) The scheme is co-financed5 by the European Agricultural Fund for Rural
Development (EAFRD). The Estonian authorities confirm that the rules
applicable under this Fund will be respected.
(11) The measure entered into force on 16 August 2022. However, pursuant to Article
15, paragraph 7 of the legal basis, aid may be granted under the measure as from
the notification of the Commission’s decision approving the measure until no
later than 31 December 2022.
2.5. Beneficiaries
(12) The beneficiaries of the measure are micro, small, medium-sized6 and large7
undertakings operating in Estonia for at least one financial year at the time of the
application for aid that are affected by the current crisis (Article 3, paragraph 1, of
the legal basis). However, credit institutions or other financial institutions are
excluded as eligible final beneficiaries.
(13) The Estonian authorities estimate that the number of beneficiaries will be
approximately 100.
(14) Pursuant to Article 4 of the legal basis, undertakings are eligible if they:
(a) do not have arrears of state tax or, if the payment of the debt of the state
tax has been deferred, the tax arrears for which the due date has expired
have been paid;
(b) have not been sanctioned for certain criminal offences listed in the legal
basis8;
(c) have not received and are not simultaneously applying for direct support9
for the same costs from the Estonian budget, other European Union or
foreign funds, or other non-repayable State aid;
(d) liquidation proceedings have not been initiated and no interim trustee in
bankruptcy has been initiated or declared bankrupt pursuant to the
5
85% of the budget of the scheme is financed by the EAFRD, while the remaining 15% is financed by
the Estonian budget.
6
As defined in Annex I to Commission Regulation (EU) No 651/2014 of 17 June 2014 (“GBER”)
declaring certain categories of aid compatible with the internal market in application of Articles 107
and 108 of the Treaty (OJ L 187, 26.6.2014, p. 1).
7
Estonia clarifies that a large undertaking is an undertaking which had less than 750 employees in the
financial year immediately preceding the application and whose sales revenue in that financial year
were less than EUR 200 million.
8
Pursuant to Article 4, paragraph 2, of the legal basis, the criminal offences that affect the eligibility
are those under Articles 66(1), 66(2) and 66(6) of the Animal Protection Act, Article 37 of the
Fertilisers Act, Articles 120, 120(1), 126 and 126(4) of the Waste Act, Article 53(1), 53(2), 53(3),
53(5) and 53(6) of the Food Act, Articles 33, 34 and 35 of the Feed Act, Articles 52(1), 55(1), 209,
210, 211, 212, 213, 294, 296, 298 (1), 300(1), 364, 365, 372 and 375 of the Penal Code.
9
The Estonian authorities clarify that this provision does not include aid received (or applied for) in the
form of loans and guarantees.
3
applicable national bankruptcy law at least three years after the payment
by the ARIB of the last instalment of support, if the applicant is a micro or
small enterprise, and for at least five years as of the payment by the ARIB
of the last instalment of support if the applicant is a medium-sized
enterprise or a large enterprise. This is a requirement which must be met
by both the applicant and the beneficiary. If the applicant or beneficiary
does not meet the eligibility condition, the ARIB is obliged to recover
100% of the aid.
(e) the aggregated assessment of the financial indicators of the applicant in
accordance with the economic sustainability assessment model10 set out in
Annex 1 to the legal basis is at least 0.6155;
(f) have repaid the aid previously received from the Estonian budget or other
European Union or foreign funds that was subject to recovery or, in case
of deferred repayment, have paid this latter.
(15) Estonia confirms that the aid under the measure is not granted to undertakings
under sanctions adopted by the EU, including but not limited to: (i) persons,
entities or bodies specifically named in the legal acts imposing those sanctions;
(ii) undertakings owned or controlled by persons, entities or bodies targeted by
sanctions adopted by the EU; or (iii) undertakings active in industries targeted by
sanctions adopted by the EU, insofar as the aid would undermine the objectives of
the relevant sanctions.
(16) Estonia confirms that the measure may not in any way be used to undermine the
intended effects of sanctions imposed by the EU or its international partners and
will be in full compliance with the anti-circumvention rules of the applicable
regulations11. In particular, natural persons or entities subject to the sanctions will
not benefit directly or indirectly from the measure.
2.6. Sectoral and regional scope of the measure
(17) The measure is open only to undertakings operating in the sectors included in
subsection 10 (food production) and 11 (beverages production) of Section C12 of
the EMTAK13 to the extent that they are engaged in the processing of agricultural
products.
(18) For the purpose of the measure, an undertaking will be deemed to be operating in
the sectors identified in recital (17) if, as declared in the commercial register, that
undertaking’s main activity falls within one of those sectors in the financial year
immediately preceding the submission of the application.
10
The model assesses the economic sustainability of the applicant for the future, i.e. whether the current
financial indicators indicate a possible default over the next three years (from the last full financial
year).
11
For example, Article 12 of Council Regulation (EU) No 833/2014 of 31 July 2014 concerning
restrictive measures in view of Russia's actions destabilising the situation in Ukraine (OJ L 229,
31.7.2014, p. 1).
12
Excluding subsection 102 of Section C (processing and storage of fish, crustaceans and molluscs).
13
The Estonian equivalent version of the NACE codes.
4
(19) The measure applies to the whole territory of Estonia.
2.7. Basic elements of the measure
(20) The overall objective of the measure is to ensure that undertakings whose
activities have been affected by the increased input prices due to the Russian
aggression against Ukraine (recital (12) and which are active in the processing of
food and beverages (recital (17)), will be able to ensure security of the food
supply chain and the continuity of the food and beverage industries. The objective
of the measure is to support undertakings facing liquidity shortages because of the
current crisis and to support investments that help ensure security of energy
supply. Support will be given to the purchase of equipment and the construction
of a building necessary to ensure the security of energy supply and the purchase
of a generator for use as a temporary power source.
(21) Aid will be granted on the basis of a written application submitted from
21 September 2022 to 5 October 2022 to the ARIB, who will verify that all the
eligibility conditions listed in recitals (12) and (14) are met and will assess the
applications against six evaluation criteria which are further subdivided into
several sub-criteria varying depending on the size of the applicant (i.e. micro,
small enterprise or medium-sized and large enterprises), detailed in Annexes II
and III to the legal basis14.
(22) Applications that will not reach the minimum score15 will be rejected. If the
number of successful applications does not exceed the budget under recital (9), all
the applications that reach the minimum score may be satisfied. However, if the
budget under recital (9) is exceeded, only those applications ranking higher in the
scoring mechanism may be satisfied.
(23) Beneficiaries may implement the activities financed under the measure within two
years as of the ARIB decision to approve the application.
(24) The aid provides liquidity support for investments. Pursuant to Article 5 of the
legal basis, costs that are eligible under the measure are those concerning the
following activities, to the extent the investment object is located in Estonia:
(a) purchase of (i) the necessary equipment to ensure security of energy
supply and (ii) a generator to be used as a temporary power source16;
(b) construction of a building that pursues the objective of security of energy
supply17.
14
The cumulative evaluation criteria against which applications are assessed are: investment aimed at
the production of products with higher added value; investment made to increase the share of sales of
products to foreign markets; investments made for the use of renewable energy; investments made to
increase resource efficiency; investments related to risk management; investments with higher self-
financing.
15
According to Article 15, paragraph 3, of the legal basis, the minimum score will be set at 30% of the
score achieved by the best applicant.
16
Costs that are eligible for these activities may be the cost of the equipment, training for the
installation, adjustment or use of the equipment by the seller, software and information technology
equipment necessary for the use of the device and the cost of its installation or set-up by the seller.
5
(25) Conversely, Article 7 of the legal basis lists costs that are not eligible for aid
under the measure. These include notably: the remuneration for the work
performed by the applicant or his/her employee; expenses incurred for the
performance of preparatory work for applying for support; the cost of purchasing
the means of transport and its trailer; the cost of purchasing standard smart and
hardware and means of communication, including a mobile phone; expenses or
interest expenses related to entry into the contract or insurance; lease payment.
(26) Pursuant to Article 6, paragraph 4, of the legal basis, assets purchased under the
measure must be new. An exception to this rule is granted to beneficiaries that are
micro or small enterprises, provided that all the following conditions are met: the
equipment is not older than three years at the time of submission of the
application, the purchase of the equipment has not been subject to support from
the Estonian budget or other European Union or external resources or other non-
repayable State aid, and the price of the equipment does not exceed its market
value and is lower than the price of the new equivalent equipment.
(27) Aid may be granted in the form of direct grants. Based on Article 9 of the legal
basis, the amount of the grants are the following:
(a) micro and small undertakings may receive between 15% and 40% of the
eligible costs described in recital (24). Aid may not exceed EUR 250 000
per applicant at any given point in time;
(b) medium-sized undertakings may receive between 15% and 30% of the
eligible costs described in recital (24). Aid may not exceed EUR 500 000
(gross, that is, before any deduction of tax or other charges) per applicant
at any given point in time;
(c) large undertakings may receive between 15% and 20% of the eligible
costs described in recital (24). Aid may not exceed EUR 500 000 (gross,
that is, before any deduction of tax or other charges) per applicant at any
given point in time.
(28) Pursuant to Article 9, paragraph 5, of the legal basis, if two beneficiaries belong
to the same corporate group by virtue of a dominant influence18, they are deemed
to be one undertaking19 which together can apply for support.
(29) The Estonian authorities confirm that the aid under recital (1)(b) will not be partly
or entirely passed on to primary producers and is not fixed on the basis of the
price or quantity of products purchased from primary producers or put on the
market by the undertakings concerned or purchased from primary producers,
unless, in the latter case, the products were either not put on the market or were
used for non-food purposes such as distillation, methanization or composting by
the undertakings concerned.
17
Costs that are eligible for this activity may be those related to the construction, expansion,
reconstruction, establishment and installation of the building. All the works must be carried out in
compliance with the conditions and the procedures provided for in the Estonian Building Code.
18
As defined in Section 2(4) of the Estonian Competition Act.
19
As defined in Annex I to the GBER.
6
2.8. Cumulation
(30) The aid ceilings and cumulation maxima fixed under the measure will apply
regardless of whether the support for the aided project is financed entirely from
State resources or partly financed by the European Structural and Investment
Funds (ESIF).
(31) The Estonian authorities confirm that aid granted under the measure may be
cumulated with aid under de minimis Regulation20, provided the provisions and
cumulation rules of this regulation are respected.
(32) The Estonian authorities confirm that aid under the measure may be cumulated
with aid under the following measures: SA.5680421, SA.5702822, SA.5867823,
SA.5874824, SA.6066625, SA.6269026, SA.10063627 and SA.10216728. These
measures were approved by the Commission under the Temporary Framework for
State aid measures to support the economy in the current COVID-19 outbreak29
(COVID-19 Temporary Framework) and the aid under the measure may be
20
Commission Regulation (EU) No 1407/2013 of 18 December 2013 on the application of Articles 107
and 108 of the Treaty on the Functioning of the European Union to de minimis aid (OJ L 352,
24.12.2013, p. 1).
21
Commission Decision C(2020) 2075 final of 30 March 2020 in case SA.56804 (2020/N) – “State
Loan Guarantees and subsidised loan scheme under the Temporary Framework for State aid measures
to support the economy in the current COVID-19 outbreak”.
22
Commission Decision C(2020) 2848 final of 28 April 2020 in case SA.57028 (2020/N) – “Estonian
aid schemes in the form of guarantees on loans, loans and subsidised interest rates for loans under
Section 3.1 of the Temporary Framework for State aid measures to support the economy in the
current COVID-19 outbreak”.
23
Commission Decision C(2020) 6957 final of 6 October 2020 in case SA.58678 (2020/N) –
“COVID-19: Exceptional temporary support due to the COVID-19 outbreak for the food processing
sector”.
24
Commission Decision C(2020) 9071 final of 9 December 2020 in case SA.58748 (2020/N) –
“COVID-19: Amendment to SA.56804 (2020/N) – State Loan Guarantees and subsidised loan
scheme under the Temporary Framework for State aid measures to support the economy in the current
COVID-19 outbreak, and to SA.57028 (2020/N) Estonian aid schemes in the form of guarantees on
loans, loans and subsidised interest rates for loans under Section 3.1 of the Temporary Framework for
State aid measures to support the economy in the current COVID-19 outbreak”.
25
Commission Decision C(2021) 1792 final of 15 March 2021 in case SA.60666 (2020/N) –
“COVID-19: Exceptional temporary support due to the COVID-19 outbreak for farmers”.
26
Commission Decision C(2021) 3008 final of 23 April 2021 in case SA.62690 (2021/N) – “COVID-19
– Amendments to schemes SA.56804, SA.57028 and SA.59278”.
27
Commission Decision C(2021) 9162 final of 7 December 2021 in case SA.100636 (2021/N) –
“COVID-19: Exceptional support to dairy and pigmeat producers due to the COVID-19 outbreak”.
28
Commission Decision C(2022) 2286 final of 6 April 2022 in case SA.102167 (2022/N) – “COVID-
19: Re-introduction of measure 1 of scheme SA.56804 and measure 1 of scheme SA.57028, as
already amended”.
29
Communication from the Commission - Temporary framework for State aid measures to support the
economy in the current COVID-19 outbreak (OJ C 91I, 20.3.2020, p. 1), as amended by Commission
Communications C(2020) 2215 (OJ C 112I, 4.4.2020, p. 1), C(2020) 3156 (OJ C 164, 13.5.2020, p.
3), C(2020) 4509 (OJ C 218, 2.7.2020, p. 3), C(2020) 7127 (OJ C 340I, 13.10.2020, p. 1), C(2021)
564 (OJ C 34, 1.2.2021, p. 6), and C(2021) 8442 (OJ C 473, 24.11.2021, p. 1).
7
cumulated with these measures provided the respective cumulation rules are
respected.
(33) The Estonian authorities confirm that aid granted under the measure may be
cumulated with aid granted under other measures approved by the Commission
under other sections of the Temporary Crisis Framework, provided the provisions
in those specific sections are respected.
(34) The Estonian authorities confirm that if the beneficiary receives aid on several
occasions or in several forms under the measure or aid under other measures
approved by the Commission under section 2.1 of the Temporary Crisis
Framework, the overall maximum cap per undertaking, as set out in point 41(a) of
that framework, will be respected.
2.9. Monitoring and reporting
(35) The Estonian authorities confirm that they will respect the monitoring and
reporting obligations laid down in section 3 of the Temporary Crisis Framework
(including the obligation to publish relevant information on each individual aid
above EUR 100 000 granted under the measure on the comprehensive national
State aid website or Commission’s IT tool within 12 months from the moment of
granting30).
3. ASSESSMENT
3.1. Lawfulness of the measure
(36) By notifying the measure before putting it into effect (recital (11)), the Estonian
authorities have respected their obligations under Article 108(3) TFEU.
3.2. Existence of State aid
(37) For a measure to be categorised as aid within the meaning of Article 107(1)
TFEU, all the conditions set out in that provision must be fulfilled. First, the
measure must be imputable to the State and financed through State resources.
Second, it must confer an advantage on its recipients. Third, that advantage must
be selective in nature. Fourth, the measure must distort or threaten to distort
competition and affect trade between Member States.
(38) The measure is imputable to the State, since it is administered by the ARIB
(recital (8)) and it is based on the legal basis described in recital (7). It is financed
through State resources, since it is financed by public funds (recital (9) and
footnote 5).
(39) The measure confers an advantage on its beneficiaries in the form of direct grants
(recital (6)). The measure thus confers an advantage on those beneficiaries which
they would not have had under normal market conditions.
30
Referring to information required in Annex III to the GBER and Annex III to Commission Regulation
(EU) No 702/2014 of 25 June 2014 declaring certain categories of aid in the agricultural and forestry
sectors and in rural areas compatible with the internal market in application of Articles 107 and 108 of
the Treaty on the Functioning of the European Union (OJ L 193, 1.7.2014, p. 1).
8
(40) The advantage granted by the measure is selective, since it is awarded only to
certain undertakings, namely those active in the economic sectors described in
recital (17) that are affected by the current crisis (recital (12)).
(41) The measure is liable to distort competition, since it strengthens the competitive
position of its beneficiaries. It also affects trade between Member States, since
those beneficiaries are active in sectors in which intra-Union trade exists.
(42) In view of the above, the Commission concludes that the measure constitutes aid
within the meaning of Article 107(1) TFEU. The Estonian authorities do not
contest that conclusion.
3.3. Compatibility
(43) Since the measure involves aid within the meaning of Article 107(1) TFEU, it is
necessary to consider whether that measure is compatible with the internal
market.
(44) Pursuant to Article 107(3)(b) TFEU the Commission may declare compatible
with the internal market aid “to remedy a serious disturbance in the economy of a
Member State”.
(45) By adopting the Temporary Crisis Framework on 23 March 2022, the
Commission acknowledged (in section 1) that the military aggression against
Ukraine by Russia, the sanctions imposed by the EU or its international partners
and the counter measures taken, for example by Russia, have created significant
economic uncertainties, disrupted trade flows and supply chains and led to
exceptionally large and unexpected price increases, especially in natural gas and
electricity, but also in numerous other input and raw materials and primary goods,
including in the agri-food sector. Those effects taken together have caused a
serious disturbance of the economy in all Member States, including in the
economy of Estonia. The Commission concluded that State aid is justified and
can be declared compatible with the internal market on the basis of Article
107(3)(b) TFEU for a limited period if it serves to remedy the liquidity shortage
faced by undertakings that are directly or indirectly affected by the serious
disturbance of the economy caused by the Russian military aggression against
Ukraine, the sanctions imposed by the EU or by its international partners, as well
as the economic counter measures taken so far, for example by Russia.
(46) The measure aims at supporting undertakings facing liquidity shortages because
of the current crisis and investments that help ensure security of energy supply at
a time when a wide range of economic sectors are affected, the normal
functioning of markets is severely disturbed leading to severe disturbances of the
real economy of Member States, including in the economy of Estonia. More
specifically, the measure aims to provide liquidity support for investments by
undertakings active in the processing of food and beverages, which have been
affected by the current crisis, due to the fact that their production process is
heavily dependent on electricity and the gas imported from Russia, the price of
both of which have increased drastically (recital (3)).
(47) The measure is one of a series of measures conceived at national level by the
Estonian authorities to remedy a serious disturbance in their economy. The
importance of the measure to support undertakings facing liquidity shortages
9
because of the current crisis and to support investments that help ensure security
of energy supply is widely accepted by economic commentators and the measure
is of a scale which can be reasonably anticipated to produce effects across the
entire Estonian economy. Furthermore, the measure has been designed to meet
the requirements of a specific category of aid described in section 2.1 of the
Temporary Crisis Framework.
(48) The Commission accordingly considers that the measure is necessary, appropriate
and proportionate to remedy a serious disturbance in the economy of a Member
State and meets all the relevant conditions of the Temporary Crisis Framework. In
particular:
the aid takes the form of direct grants (recital (6));
the overall nominal value of the grants will not exceed EUR 500 000 per
undertaking (EUR 250 000 for micro and small undertakings); all figures
used must be gross, that is, before any deduction of tax or other charges
(recital (27)). The measure therefore complies with point 41(a) of the
Temporary Crisis Framework;
aid is granted under the measure on the basis of a scheme with an
estimated budget as indicated in recital (9). The measure therefore
complies with point 41(b) of the Temporary Crisis Framework;
aid will be granted under the measure no later than 31 December 2022.
The measure therefore complies with point 41(c) of the Temporary Crisis
Framework;
aid will be granted only to undertakings affected by the current crisis
(recital (12)). The measure therefore complies with point 41(d) of the
Temporary Crisis Framework;
aid under the measure cannot be conditional on being partly or entirely
passed on to primary producers, fixed on the basis of the price or quantity
of products put on the market by the undertakings concerned or purchased
from primary producers, unless, in the latter case, the products were either
not put on the market or were used for non-food purposes such as
distillation, methanization or composting by the undertakings concerned
(recital (29)). The measure therefore complies with point 41(e) of the
Temporary Framework.
(49) The Estonian authorities confirm that, pursuant to point 32 of the Temporary
Crisis Framework, the aid under the measure is not conditioned on the relocation
of a production activity or of another activity of the beneficiary from another
country within the EEA to the territory of the Member State granting the aid. This
is irrespective of the number of job losses actually occurred in the initial
establishment of the beneficiary in the EEA (recital (4)).
(50) The Estonian authorities confirm that, pursuant to point 33 of the Temporary
Crisis Framework, the aid under the measure will not be granted to undertakings
under sanctions adopted by the EU, including but not limited to: a) persons,
entities or bodies specifically named in the legal acts imposing those sanctions; b)
undertakings owned or controlled by persons, entities or bodies targeted by
sanctions adopted by the EU; or c) undertakings active in industries targeted by
10
sanctions adopted by the EU, insofar as the aid would undermine the objectives of
the relevant sanctions (recital (15)).
(51) The Estonian authorities confirm that the monitoring and reporting rules laid
down in section 3 of the Temporary Crisis Framework will be respected (recital
(35)). The Estonian authorities further confirm that the aid under the measure may
only be cumulated with other aid, provided the specific provisions in the sections
of the Temporary Crisis Framework, the COVID-19 Temporary Framework and
the cumulation rules of the relevant regulation are respected (recitals (31) to (33)).
(52) The Estonian authorities also confirm that the rules under the EAFRD will be
respected (recital (10)).
(53) The Commission therefore considers that the measure is necessary, appropriate
and proportionate to remedy a serious disturbance in the economy of a Member
State pursuant to Article 107(3)(b) TFEU since it meets all the relevant conditions
of the Temporary Crisis Framework.
4. CONCLUSION
The Commission has accordingly decided not to raise objections to the aid on the
grounds that it is compatible with the internal market pursuant to Article 107(3)(b) of the
Treaty on the Functioning of the European Union.
The decision is based on non-confidential information and is therefore published in full
on the Internet site: http://ec.europa.eu/competition/elojade/isef/index.cfm.
Yours faithfully,
For the Commission
Margrethe VESTAGER
Executive Vice-President
11
Alo Aasma Teie 28.07.2022 nr 5.4-2/685
Maaeluministeerium Meie 27.09.2022 nr 12.1-3/6188-3
[email protected]
Euroopa Komisjoni otsus
toiduainetööstuse
investeeringutoetuse energia
varustuskindluse tagamiseks kohta
Austatud härra Aasma
Edastame Euroopa Komisjoni 23.09.2022 otsuse SA.103936 abimeetme „Toiduainetööstuse
investeeringutoetus energia varustuskindluse tagamiseks“ kohta (otsus lisatud).
Lugupidamisega
(allkirjastatud digitaalselt)
Kaur Kajak
halduspoliitika asekantsler
Lisa: Euroopa Komisjoni otsus
Lisaadressaat: Põllumajanduse Registrite ja Informatsiooni Amet
Maris Kalda 611 3525
[email protected]
Suur-Ameerika 1 / 10122 Tallinn / 611 3558 /
[email protected] / www.rahandusministeerium.ee
registrikood 70000272