CERTIFICATION OF THE MEMBER STATE * (applicable only for ASR and for beneficiaries established in the European Union) Name Position Entity Telephone Nº E-mail In compliance with Article II.23.1 ( or SESAR FPA II.23.1b) of the GA, it is certified that the information provided by the following Beneficiary( ies ) in the ASR is full, reliable and true. Estonian Road Administration Date and signature Stamp ( optional) * In line with the terms of Art. 22 of the CEF Regulation
Indrek Gailan
Majandus- ja
Kommunikatsiooniministeerium
[email protected] Meie 09.02.2021 nr 1.1-6/21/3456-1
Suur-Ameerika tn 1
10122, Tallinn, Harju maakond
Riigi kinnituskiri projekti vahearuandele
Austatud hr Gailan
Seoses Tallinna ringtee „Dynamic traffic and truck parking management” projektiga peab
Maanteeamet esitama eelmise perioodi (jaanuar 2020 kuni detsember 2020) vahearuande, mille
üheks osaks on riigi kinnituskiri. Palume tutvuda vahearuande raporti ja selle lisadega ning seejärel
Majandus- ja Kommunikatsiooniministeeriumi esindajal täita ja käsitsi allkirjastada kinnituskiri
(dokument pealkirjaga „MS certification ASR_1”) ning saata originaaldokumendina tagasi.
Juhime tähelepanu, et vahearuande perioodi ajal oli Transpordiamet veel moodustamata, mistõttu
rahastuse saajaks on märgitud Maanteeamet (ingl k Estonian Road Administration).
Lugupidamisega
(allkirjastatud digitaalselt)
Andres Urm
juhataja
taristu arendamise osakond
Lisa: Report ASR_1, Request of further pre-financing payment_Estonian Road Administration
ASR_1, Financial Annex ASR_1, MS certification ASR_1
Mari-Liis Sepp
58502984
[email protected]
Valge 4 / 11413 Tallinn / 620 1200 /
[email protected] / www.transpordiamet.ee
Registrikood 70001490
ASR-2021-2018-EE-TM-0029-M-
European
Dynamic traffic and truck parking
Commission
Innovation and management
Reporting period: 1 January 2020 -
Networks Executive
Agency (INEA)
31 December 2020
Connecting Europe
Facility
1. INFORMATION ON THE ACTION
Grant Agreement Nº INEA/CEF/TRAN/M2018/1767529
Action number 2018-EE-TM-0029-M
Action title Dynamic traffic and truck parking management
PCI (for energy and
synergy only)
Author of the report
Name Mari-Liis Sepp
Position Project manager
Entity Estonian Road Administration
Telephone Nº +372 5850 2984
E-mail
[email protected]
Reporting period: 1 January 2020 - 31 December 2020
2. INFORMATION ON THE PROGRESS OF THE
ACTION (GA II.23.1.1.c or SESAR FPA II.23.1b.c)
2.1. Overall progress of the Action until the end of the previous reporting
period
Overall
Planned dates (GA) Previous ASR dates Actual dates
technical
progress
achieved at
the end of
Start End Start End Start End the
previous
reporting
period (%)*
01/06/2019 31/12/2023 01/06/2019 31/12/2023 01/06/2019 31/12/2023 8.00
*Please explain how the percentage of the progress achieved has been estimated/calculated
Calculated according to Annex III of the "Guidance for poor or partial completion": SUM(Technical
Progress Per Activity Per Year * (GA EU Contribution Per Activity / Total GA EU Contribution)).
Overview of progress since the start of the Action
The overview should include a description of the actual progress of the Action and per
activity since the start of the Action until at the end of the previous reporting period,
referring to the main issues, milestones and events that affected the progress.
Which activities started, were ongoing, complete?
Activities 1 (project management), 2 (communication and dissemination), 3 (transport
and ITS study), 4 (pilot implementation 1), 5 (pilot implementation 2) started in the
reporting period (01/01/2020-31/12/2020) and were on-going. Activity 3 has
completed as the final milestone – transport and ITS study final report – ended on
09/09/2020.
Which milestones were planned to be complete and were finally completed?
The following milestones have been finished:
2018-EE-TM-0029-M_ASR2021_1_draft_20210209_1021 2
Reporting period: 1 January 2020 - 31 December 2020
• Assessment of offers Transport and ITS study report planned date 01/01/2020;
actual date 10/01/2020
• Contract signed Transport and ITS study report planned date 01/02/2020; actual
date 23/01/2020
• Action Status Report (ASR) planned date 31/03/2020; actual date 17/02/2020
• Communication support materials planned date 31/05/2020; actual date
20/04/2020
• Transport and ITS study interim report planned date 01/06/2020; actual date
04/06/2020
• PM and SG joint meeting no 3 planned date 30/06/2020; actual date 17/09/2020
• Transport and ITS study final report planned date 01/09/2020; actual date
09/09/2020
• Publication of tender Pilot 1 (design) planned date 01/10/2020; actual date
22/10/2020
• Publication of tender Pilot 2 (design) planned date 01/10/2020; actual date
17/08/2020
• PM and SG joint meeting no 4 planned date 31/12/2020; actual date have not
occurred
• Assessment of offers Pilot 1 (design) planned date 31/12/2020; actual date
04/12/2020
• Delivery of the scoping decision and subsequent environmental permits planned
date 31/12/2020; actual date 06/05/2020
• Assessment of offers Pilot 2 (design) planned date 31/12/2020; actual date
22/09/2020
• Contract signed Pilot 1 (design) planned date 31/01/2021; actual date
03/01/2021
• Contract signed Pilot 2 (design) planned date 31/01/2021; actual date
22/09/2020
Reasons for delays for milestones and/or activities if any and the impact for
activity’s/Action’s end dates or other activities?
PM and SG joint meeting no 3 was planned on 30/06/2020 but since the first PS and
SG joint meeting was delayed others have also postponed and the actual date was
17/09/2020.
PM and SG joint meeting no 4 was planned on 31/12/2020 but since the first PS and
SG joint meeting was delayed others have also postponed to next reporting period.
These delays have no impact for activity’s nor Action’s end dates or other activities.
Some milestones actual dates were also early completed, for example, delivery of the
scoping decision and subsequent environmental permits planned date 31/12/2020;
actual date 06/05/2020.
Any task not foreseen initially but needed to achieve the Action’s objectives/scope?
After Transport and ITS study the beneficiary decided to divide Pilot 1 and 2 tenders
into two: design and building process. This change is important so it will be easier to
2018-EE-TM-0029-M_ASR2021_1_draft_20210209_1021 3
Reporting period: 1 January 2020 - 31 December 2020
calculate the building cost and the works will be more percise in the tender. This
decision will not interfere in the objectives and goals of the Action. During the reporting
period the pilot 1 and 2 tender included design tender. The building tender and process
will start in 2021 and will end as scheduled.
2018-EE-TM-0029-M_ASR2021_1_draft_20210209_1021 4
Reporting period: 1 January 2020 - 31 December 2020
2.2. Progress per activity
Overall technical
progress achieved
Previous ASR Start/end
Activity 1 Title Planned Start/End date (GA) Actual Start/End date until the end of the
dates
previous reporting
period (%)*
Project management 01/06/2019 31/12/2023 01/06/2019 31/12/2023 01/06/2019 31/12/2023 18.00
*Please explain how the percentage of the progress achieved has been estimated/calculated
SUM(Technical Progress Per Activity Per Year * (GA EU Contribution Per Activity / Total GA EU Contribution))
Milestone
Title1 Planned completion date (GA) Previous ASR date Actual completion date Reached (Y/N)
no
PM and SG joint meeting
1 30/06/2019 20/11/2019 20/11/2019 Yes
No 1
Explanation for any deviation from planned completion date
The project manager was hired in September 2019. There was not a project manager nor actual need to hold PM and SG joint meeting No 1 before that.
PM and SG joint meeting
2 31/12/2019 30/04/2020 07/05/2020 Yes
No 2
Explanation for any deviation from planned completion date
2018-EE-TM-0029-M_ASR2021_1_draft_20210209_1021 5
Reporting period: 1 January 2020 - 31 December 2020
The meeting was organised a week later due to the participants' schedule.
PM and SG joint meeting
3 30/06/2020 30/09/2020 17/09/2020 Yes
No 3
Explanation for any deviation from planned completion date
The meeting was organised two weeks before due to the participants' schedule.
PM and SG joint meeting
4 31/12/2020 31/12/2020 26/02/2021 No
No 4
Explanation for any deviation from planned completion date
The meeting was organised two months later due to the holidays and the amount of information to share at the meeting.
PM and SG joint meeting
5 30/06/2021 30/06/2021 30/06/2021 No
No 5
Explanation for any deviation from planned completion date
PM and SG joint meeting
6 31/12/2021 31/12/2021 31/12/2021 No
No 6
Explanation for any deviation from planned completion date
PM and SG joint meeting
7 30/06/2022 30/06/2022 30/06/2022 No
No 7
Explanation for any deviation from planned completion date
PM and SG joint meeting
8 31/12/2022 31/12/2022 31/12/2022 No
No 8
Explanation for any deviation from planned completion date
PM and SG joint meeting
9 30/06/2023 30/06/2023 30/06/2023 No
No 9
Explanation for any deviation from planned completion date
2018-EE-TM-0029-M_ASR2021_1_draft_20210209_1021 6
Reporting period: 1 January 2020 - 31 December 2020
PM and SG joint meeting
10 31/12/2023 31/12/2023 31/12/2023 No
No 10
Explanation for any deviation from planned completion date
2018-EE-TM-0029-M_ASR2021_1_draft_20210209_1021 7
Reporting period: 1 January 2020 - 31 December 2020
Overall technical
progress achieved
Previous ASR Start/end
Activity 2 Title Planned Start/End date (GA) Actual Start/End date until the end of the
dates
previous reporting
period (%)*
Communication and
01/06/2019 31/12/2023 01/06/2019 31/12/2023 01/06/2019 31/12/2023 25.00
dissemination
*Please explain how the percentage of the progress achieved has been estimated/calculated
SUM(Technical Progress Per Activity Per Year * (GA EU Contribution Per Activity / Total GA EU Contribution))
Milestone
Title1 Planned completion date (GA) Previous ASR date Actual completion date Reached (Y/N)
no
Project opening press /
11 31/12/2019 20/11/2019 20/11/2019 Yes
kick off meeting event
Explanation for any deviation from planned completion date
Actual completion date was before planned completition date.
Project communication
12 31/10/2019 14/10/2019 14/10/2019 Yes
plan
Explanation for any deviation from planned completion date
Actual completion date was before planned completition date.
Communication support
13 31/05/2020 31/05/2020 20/04/2020 Yes
materials
2018-EE-TM-0029-M_ASR2021_1_draft_20210209_1021 8
Reporting period: 1 January 2020 - 31 December 2020
Explanation for any deviation from planned completion date
Actual completion date was before planned completition date.
Project finalization press /
14 31/10/2023 31/10/2023 31/10/2023 No
final meeting event
Explanation for any deviation from planned completion date
2018-EE-TM-0029-M_ASR2021_1_draft_20210209_1021 9
Reporting period: 1 January 2020 - 31 December 2020
Overall technical
progress achieved
Previous ASR Start/end
Activity 3 Title Planned Start/End date (GA) Actual Start/End date until the end of the
dates
previous reporting
period (%)*
Transport and ITS study
for preparation of pilot 1 01/09/2019 01/09/2020 02/09/2019 31/01/2021 02/09/2019 09/09/2020 100.00
and 2
*Please explain how the percentage of the progress achieved has been estimated/calculated
SUM(Technical Progress Per Activity Per Year * (GA EU Contribution Per Activity / Total GA EU Contribution))
Milestone
Title1 Planned completion date (GA) Previous ASR date Actual completion date Reached (Y/N)
no
Publication of Tender
15 Transport and ITS study 01/11/2019 02/12/2019 02/12/2019 Yes
report
Explanation for any deviation from planned completion date
Project manager was hired in September 2019 which was the reason the tender was published a month later.
Assessment of offers
16 Transport and ITS study 01/01/2020 10/01/2020 10/01/2020 Yes
report
Explanation for any deviation from planned completion date
Due to the holidays period the assessment process was pushed forward.
2018-EE-TM-0029-M_ASR2021_1_draft_20210209_1021 10
Reporting period: 1 January 2020 - 31 December 2020
Contract signed Transport
17 01/02/2020 23/01/2020 23/01/2020 Yes
and ITS study report
Explanation for any deviation from planned completion date
Since there was only one tenderer the process of signing the contract was shorter than expected.
Transport and ITS study
18 01/06/2020 01/06/2020 04/06/2020 Yes
interim report
Explanation for any deviation from planned completion date
The interim report was few days late due to the COVID-19 situation.
Transport and ITS study
19 01/09/2020 01/09/2020 09/09/2020 Yes
final report
Explanation for any deviation from planned completion date
The final report was few days late due to the COVID-19 situation.
2018-EE-TM-0029-M_ASR2021_1_draft_20210209_1021 11
Reporting period: 1 January 2020 - 31 December 2020
Overall technical
progress achieved
Previous ASR Start/end
Activity 4 Title Planned Start/End date (GA) Actual Start/End date until the end of the
dates
previous reporting
period (%)*
Pilot implementation 1:
dynamic traffic
01/09/2020 01/06/2022 01/09/2020 01/06/2022 22/10/2020 01/06/2022 0.00
management system in
E265 section km 10-20
*Please explain how the percentage of the progress achieved has been estimated/calculated
SUM(Technical Progress Per Activity Per Year * (GA EU Contribution Per Activity / Total GA EU Contribution))
Milestone
Title1 Planned completion date (GA) Previous ASR date Actual completion date Reached (Y/N)
no
Publication of tender Pilot
20 01/10/2020 01/10/2020 22/10/2020 Yes
1
Explanation for any deviation from planned completion date
There were discussions in the Estonian Road Administration how to formalise the tender since the transport and ITS study showed the need of bigger budget.
The tender was divided into two tenders - design and building process tenders. The decision-making took some time which is the reason of the milestone daley.
Assessment of offers Pilot
21 31/12/2020 31/12/2020 04/12/2020 Yes
1
Explanation for any deviation from planned completion date
The tender took less time than expected.
2018-EE-TM-0029-M_ASR2021_1_draft_20210209_1021 12
Reporting period: 1 January 2020 - 31 December 2020
22 Contract signed Pilot 1 31/01/2021 31/01/2021 03/01/2021 Yes
Explanation for any deviation from planned completion date
The contract signing took less time than expected.
Pilot 1 implemented
23 01/06/2022 01/06/2022 01/06/2022 No
solution is in operation
Explanation for any deviation from planned completion date
2018-EE-TM-0029-M_ASR2021_1_draft_20210209_1021 13
Reporting period: 1 January 2020 - 31 December 2020
Overall technical
progress achieved
Previous ASR Start/end
Activity 5 Title Planned Start/End date (GA) Actual Start/End date until the end of the
dates
previous reporting
period (%)*
Pilot implementation 2:
smart (safe and secure)
01/09/2020 01/06/2022 01/09/2020 01/06/2022 06/05/2020 01/06/2022 0.00
truck parking area in E265
km 1,5
*Please explain how the percentage of the progress achieved has been estimated/calculated
SUM(Technical Progress Per Activity Per Year * (GA EU Contribution Per Activity / Total GA EU Contribution))
Milestone
Title1 Planned completion date (GA) Previous ASR date Actual completion date Reached (Y/N)
no
Publication of tender Pilot
24 01/10/2020 01/10/2020 17/08/2020 Yes
2
Explanation for any deviation from planned completion date
The activity was started earlier so there will be enough time to process the building permit after the design process.
Delivery of the scoping
25 decision and subsequent 31/12/2020 31/12/2020 06/05/2020 Yes
environmental permits
Explanation for any deviation from planned completion date
The environmental permit was delivered earlier so we could start the design tender process.
2018-EE-TM-0029-M_ASR2021_1_draft_20210209_1021 14
Reporting period: 1 January 2020 - 31 December 2020
Assessment of offers Pilot
26 31/12/2020 31/12/2020 22/09/2020 Yes
2
Explanation for any deviation from planned completion date
Tender took less time than expected.
27 Contract signed Pilot 2 31/01/2021 31/01/2021 13/10/2020 Yes
Explanation for any deviation from planned completion date
Contract signing took less time than expected.
Pilot 2 implemented
28 01/06/2022 01/06/2022 01/06/2022 No
solution is in operation
Explanation for any deviation from planned completion date
2018-EE-TM-0029-M_ASR2021_1_draft_20210209_1021 15
Reporting period: 1 January 2020 - 31 December 2020
Overall technical
progress achieved
Previous ASR Start/end
Activity 6 Title Planned Start/End date (GA) Actual Start/End date until the end of the
dates
previous reporting
period (%)*
Implementation of
dynamic traffic
management system E265 01/11/2021 01/09/2023 01/11/2021 01/09/2023 01/11/2021 01/09/2023 0.00
in sections km 0-10 and
km 20-30
*Please explain how the percentage of the progress achieved has been estimated/calculated
SUM(Technical Progress Per Activity Per Year * (GA EU Contribution Per Activity / Total GA EU Contribution))
Milestone
Title1 Planned completion date (GA) Previous ASR date Actual completion date Reached (Y/N)
no
Publication of tender E265
29 01/11/2021 01/11/2021 01/11/2021 No
km 0-10 and km 20-30
Explanation for any deviation from planned completion date
Assessment of offers E265
30 01/02/2022 01/02/2022 01/02/2022 No
km 0-10 and km 20-30
Explanation for any deviation from planned completion date
2018-EE-TM-0029-M_ASR2021_1_draft_20210209_1021 16
Reporting period: 1 January 2020 - 31 December 2020
Contract signed for E265
31 30/04/2022 30/04/2022 30/04/2022 No
km 0-10 and km 20-30
Explanation for any deviation from planned completion date
E265 section solution km
32 0-10 and km 20-30 is in 01/09/2023 01/09/2023 01/09/2023 No
operation
Explanation for any deviation from planned completion date
2018-EE-TM-0029-M_ASR2021_1_draft_20210209_1021 17
Reporting period: 1 January 2020 - 31 December 2020
2.3 If total actual costs/units deviates >5% compared to latest Grant
Agreement in force, please explain why
Activity 3 Transport and ITS study for preparation of pilot 1 and 2
Transport and ITS study showed that the implementation will be more
expensive. Since there was a budget surplus the remaining amount should be
added to activity 4 and 5 budgets.
Activity 4 Pilot implementation 1: dynamic traffic management system in E265
section km 10-20
Transport and ITS study showed that the implementation will be more
expensive.
Activity 6 Implementation of dynamic traffic management system E265 in
sections km 0-10 and km 20-30
Transport and ITS study showed that the implementation will be more expensive
than expected, on of many reasons is the cost of construction of portals above
the road (6 driving lanes).
2.4. Description of the Action's and activities' progress planned in the on-
going reporting period and until the end of implementation of the Action
a) Provide a description of the planned progress of the activities in the on-going
reporting period and, where applicable, beyond the on-going reporting period up until
the end of the implementation of the Action (if the on-going reporting period is not the
last one).
b) Highlight and explain any deviation (e.g. on objectives of the Action, the completion
of the planned activities, the cost-breakdown, Action's end date, etc.) in comparison to
the latest grant agreement in force and, where applicable, latest ASR.
c) Identify any expected/foreseen risk(s) that may challenge the actual end date of the
Action and the associated mitigation plan(s).
Which activities will start, continue, be completed?
In the on-going reporting period (from 01/01/2021 until 31/12/2021) main activities
include design process of km 0-30 VMS signs and pilot 2 (parking area). In addition,
the preparation of building process tenders – pilot 1, pilot 2 and E265 km 0-10 and 20-
30 – will start.
After that (from 01/01/2022 until 31/12/2022) the implementation of E265 km 0-10
and 20-30 is on-going and pilot I and II will be completed.
In the last period (from 01/01/2023 until 31/12/2023) the implementation of E265 km
2018-EE-TM-0029-M_ASR2021_1_draft_20210209_1021 18
Reporting period: 1 January 2020 - 31 December 2020
0-10 and 20-30 will be done and the project finalisation press/final meeting event will
be held.
Which activity/milestone/task will never be completed and the reasons why (reduction
of scope)?
There aren’t any activities/milestones/tasks that will never be completed.
Which any expected/foreseen risk(s) that may challenge the actual end date of the
Action and the associated mitigation plan(s)?
At this point there are some expected risks that may challenge the actual end date of
some milestones. For example, the end date of implementing pilot 1 and 2 (expected
date 01/06/2022). These milestones could be delayed due to the weather conditions in
Estonia – it is difficult to build anything in the wintertime. In addition, the process of
building permit of pilot 2 may take more time than expected. Thus, the actual date
could be in late September 2022. Nevertheless, everything is done that the end date of
the milestones will not be late.
2018-EE-TM-0029-M_ASR2021_1_draft_20210209_1021 19
Reporting period: 1 January 2020 - 31 December 2020
3. VISIBILITY OF UNION FUNDING (GA II.23.1.1.i or
SESAR FPA II.23.1b.i)
What measures have been taken within the previous reporting period to
publicise the Action, including EU funding (GA II.7.1)?
During the ongoing reporting period there were animated video about the project. It
also was published in social media ERA's Facebook page. It had 36 likes and over 3600
views. A press release was issued to complete Transport and ITS study, please see
thepress release here: https://www.mnt.ee/et/node/7469.
Both animated video and Transport and ITS study can be found on ERA's project's page
(https://www.mnt.ee/eng/roads/tallinn-ring-road-e265-its-project).
4. OTHER SOURCES OF EUROPEAN UNION FUNDS
(CEF-E and Synergy only, GA II.23.1.1.m )
If applicable, provide information about other sources of EU funds (CEF,
ERDF, Cohesion Fund, H2020, TEN, EEPR, EIPA, etc.) used for the project of
common interest (e.g. previous or subsequent phases not covered by the
Grant Agreement).
Not applicable
2018-EE-TM-0029-M_ASR2021_1_draft_20210209_1021 20
Reporting period: 1 January 2020 - 31 December 2020
5. COMPLIANCE WITH EU LEGISLATION (GA.II.23.1.1g
and h, or SESAR FPA II.23.1b.g and h)
5.1. Overview of environmental aspects, compliance with EU and national
legislation, issues during the implementation of the Action and measures
taken.
According to the Grant Agreement the implementation of this Activity is subject to the
acquisition of the necessary environmental permission, which will have to be requested
and obtained in advance by the beneficiary. The environmental permission was
declared and signed by Environmental Board on 06/05/2020.
5.2. Where relevant, information on the compliance with EU legislation
notably on procurement:
- information on the contracts awarded or planned for the implementation of
the Action and on compliance with the requirements set out in GA II.9 and
II.10
- regarding other matters, notably public procurement, competition,
regulatory matters, (CEF-E only) the update of the CBCA decision, etc.
The project’s pilot 1 design tender was closed on 30th November. Please see the
tender: https://riigihanked.riik.ee/rhr-web/#/procurement/2475992/general-info
There were two offers: Roadplan 117 645€ +VAT and Trafiction 59 664€ +VAT.
Our estimated cost was a little bit lower but due to the market situation (the majority of
road design companies have a lot of work), the offers were a bit higher. Although, we
can manage with the lower bidder offer (Trafiction). The contract was signed on 3rd
January 2021 and lasts until May 2021.
In addition, we are also in the process of Activity 5 – truck parking area design. The
design tender was published 17.08.2020 and the contract was signed on 15.10.2020
with Roadplan OÜ with price of 53 460€ +VAT. Please see the tender:
https://riigihanked.riik.ee/rhr-web/#/procurement/2218272/general-info The work will
be done by May 2021.
2018-EE-TM-0029-M_ASR2021_1_draft_20210209_1021 21
Reporting period: 1 January 2020 - 31 December 2020
2018-EE-TM-0029-M_ASR2021_1_draft_20210209_1021 22
Reporting period: 1 January 2020 - 31 December 2020
6. IMPLEMENTATION SCHEDULE, GOVERNANCE
AND MONITORING, OTHER RELEVANT
ADMINISTRATIVE PROVISIONS (GA II.23.1.1.k and l, or
SESAR FPA II.23.1b.k and l)
6.1. In the first ASR, information on implementation schedule, such as critical
path, key performance rates and risk analysis; in subsequent ASR, information
on any modifications and, if applicable, on the progress of the implementation
of the arrangements referred to in previous ASR. If there are changes in the
Action timetable as compared to the latest planning (Grant Agreement or
previous ASR), attach an updated Gantt chart.
Action’s implementation schedule is attached as an Excel file under the name
“timetable”. There is one critical bath which is the whole project’s milestones and
timeline. The Action’s risk analysis is also attached under the name “risk assessment
grid by activities” which was also in the proposal and updated if needed.
2018-EE-TM-0029-M_ASR2021_1_draft_20210209_1021 23
Reporting period: 1 January 2020 - 31 December 2020
Action's implementation technical progress (cumulated %)
2019 2020 2021 2022 2023
Action Current Current Current Current Current
Previous ASR Previous ASR Previous ASR Previous ASR Previous ASR
level ASR ASR ASR ASR ASR
0 0 6 8 50 35 88 88 100 100
Current Current Current Current Current
Activity Previous ASR Previous ASR Previous ASR Previous ASR Previous ASR
ASR ASR ASR ASR ASR
1
4 4 27 18 52 41 77 71 100 100
2
6 6 26 25 60 32 80 66 100 100
3
0 0 62 100 100 100 N/A 100 N/A 100
4
N/A 0 0 0 50 41 100 100 N/A 100
5
N/A 0 0 0 67 38 100 100 N/A 100
6
N/A 0 N/A 0 0 0 50 50 100 100
All the activities and the Action will achieve 100% of technical progress by their actual end dates
2018-EE-TM-0029-M_ASR2021_1_draft_20210209_1021 24
Reporting period: 1 January 2020 - 31 December 2020
6.2. In the first ASR, information on governance and monitoring of the Action,
such as organizational structure, internal coordination, communication and
reporting, and decision making process; in subsequent ASR, information on
any modifications and, if applicable, on the progress of the implementation of
the arrangements referred to in previous ASR.
The ERA in-house project team consists of the following ERA employees:
• Project manager – is responsible for coordinating and organizing project activities
in Estonia. Regular reporting to INEA.
• Head of traffic management centre – implementing traffic and other technical
solutions in the ITS area of the project.
• Financial controller – accounting for project costs, arranging bridge financing and
advising on the management of expense receipts.
• IT architect – preparation of project IT solutions and architectural requirements
and implementation monitoring.
• Communication expert – arranging public communication for the project.
The ERA in-house team has monthly meetings. Depending on the progress of the
project and which Activities are on-going, the necessary team members will be involved
with the meetings. In addition, other support staff will be included if necessary.
During the period which have contractors project manager will attend the weekly
meetings with them and brings information to the in-house team, if necessary, other
will attend the meeting as well.
In ERA there is also weekly briefing between the departments where information about
the project will be discussed if necessary.
6.3. In the first ASR, information on other relevant administrative provisions,
such as quality controls and audits; in subsequent ASR, information on any
modifications and, if applicable, on the progress of the implementation of the
arrangements referred to in previous ASR.
There aren’t any extra quality control measures in ERA. Although, a process map (for
example the procurement process describes which activities are in the process and how
they should be done) is similar to quality standard and it is followed. This Action hasn’t
been audited.
ANNEX: Financial information (GA II.23.1.1.d to f or SESAR FPA II.23.1b.d to f)
2018-EE-TM-0029-M_ASR2021_1_draft_20210209_1021 25
Reporting period: 1 January 2020 - 31 December 2020
CERTIFICATION OF THE MEMBER STATE*
(applicable only for ASR and for beneficiaries established in the European
Union)
Name
Position
Entity
Telephone Nº
E-mail
In compliance with Article II.23.1 (or SESAR FPA II.23.1b) of the GA, it is
certified that the information provided by the following Beneficiary(ies) in
the ASR is full, reliable and true.
Estonian Road Administration
Date and
signature
Stamp (optional)
* In line with the terms of Art. 22 of the CEF Regulation
2018-EE-TM-0029-M_ASR2021_1_draft_20210209_1021 26
REQUEST OF FURTHER PRE-FINANCING PAYMENT
INEA/CEF/TRAN/M2018/1
Grant Agreement Nº
767529
Action number 2018-EE-TM-0029-M
Dynamic traffic and truck
Action title
parking management
Estonian Road
Beneficiary name
Administration
Financial information for the Action
A. Maximum EU contribution (Art. 3) 1,900,000.00 €
B. Pre-financing rate (Art. 4.1.2) 40.00 %
C. Maximum pre-financing payment (Art. 4.1.2)
760,000.00 €
(=B*A)
D. Maximum ceiling for the sum of pre-financing
1,520,000.00 €
and interim payments (Art 4.1.3) (=80%*A)
E. Sum of previous pre-financing payments 44,526.98 €
F. Sum of interim payments 0.00 €
Dear Sirs,
Along with the submission of the 2021 ASR for the Action in subject, we hereby
submit a request for further pre-financing. Please find enclosed:
the amount of the previous pre-financing used to cover costs of the Action,
the amount of the requested further pre-financing;
the allocation of the amounts to be paid to each beneficiary and the
methodology used (if applicable)
the financial guarantees (if applicable)
2018-EE-TM-0029-M_ASR2021_1_draft_20210209_1021_Estonian Road
Administration
ENCLOSED
Amount of the previous pre-financing used to cover costs of the Action
G. Total estimated direct eligible costs incurred until the end of
the previous reporting period 151,690.40 €
H. 70% of previous pre-financing payments (=70%*E) 31,168.89 €
Condition of 70% fulfilled (G>=H) Yes
I. Reduction of further pre-financing, if G<H (= H-G) 0.00 €
Amount of the requested further pre-financing
J. Total estimated direct costs eligible declared
until the end of the on-going current report
period 1,173,527.20 €
K. Total cumulated financing needs until the
end of the on-going current report period 586,763.60 €
L. Further pre-financing payment (=B*K-E)
190,178.46 €
L1. Revised further pre-financing payment if the
condition of the 70% is not fulfilled – article
II.24.1.3 (L-I) 190,178.46 €
L2. Revised further pre-financing if the total
pre-financing exceeds the maximum pre-
financing payment (E+L1<=C) 190,178.46 €
L3. Revised further pre-financing if the sum of
the pre-financings and interim payments
exceeds the ceiling (E+F+L2<=D) 190,178.46 €
M. Final further pre-financing to be paid (=L3) 190,178.46 €