Tarbijakaitse ja Tehnilise Järelevalve Amet · 27. veebruar 2013
- Viit
- 13-0131-008
- Registreeritud
- 27. veebruar 2013
- Dokumendi liik
- Väljaminev kiri
- Adressaat
- European Commission - TEN-T Executive Agency (TEN-T EA)
- Funktsioon
- 6.1S Raudtee valdkonna arendustegevus ja standardiseerimine (2009-2013) (Suletud)
- Sari
- 6.1-7S Muud EL kaasfinantseeritavad projektid (Suletud)
- Toimik
- 13-0131
- Vastutaja
- Jaak Simon (Transpordi investeeringute osakond)
Sisu (failidest)
2012 2013 2014 2015
ID Task Name Start Finish Duration
märts apr mai juuni juuli aug sept okt nov dets jaan veebr märts apr mai juuni juuli aug sept okt nov dets jaan veebr märts apr mai juuni juuli aug sept okt nov dets jaan veebr märts apr mai juuni juuli aug sept okt nov dets
Study for for economic model of later managendent
1 26.03.2012 10.12.2012 37w 1d
of the railway (Joint Venture Study)
2 International co-ordination 2.04.2012 24.05.2012 7w 4d
3 Compilation of Terms of Reference 26.03.2012 4.06.2012 10w 1d
4 Procurement procedures 3.07.2012 6.09.2012 9w 3d
5 Signing of service contract 25.10.2012 25.10.2012 0w
6 Compilation of works 25.10.2012 25.02.2013 17w 5d
7 Approval of Final Report 26.02.2013 26.02.2013 0w
Strategic Environmental Impact Assessment
8 (including Environmental Impact Assessment) 1.03.2012 26.10.2012 34w 2d
preparation
Initiation of strategic environmental impact
9 assessment and environmental impact 27.04.2012 17.05.2012 3w
assessment (SEA/EIA)
10 Preparation of tender documentation 1.03.2012 30.06.2012 17w 3d
11 Procurement of Terms of Reference 23.03.2012 27.04.2012 5w 1dd
12 Compilation of Terms of Reference 28.04.2012 30.06.2012 9w 1d
13 Approval of Terms of Reference 1.07.2012 6.08.2012 5w 2d
14 Procurement procedures 31.01.2013 25.04.2013 12w 1d
15 Signing of service contract 26.04.2013 26.04.2013 0w
16 Compilation of SEA/EIA 26.04.2013 31.12.2015 140w
17 Announcement of cross-border SEA 1.06.2013 23.06.2013 3w 2d
18 Drawing up of SEA/EIA program 26.04.2013 24.08.2013 17w 2d
19 Publication of SEA/EIA program 25.02.2014 26.04.2014 8w 5d
20 Approval of SEA/EIA program 27.04.2014 27.04.2014 0w
21 Drawing up SEA/EIA 26.10.2013 6.02.2014 14w 6d
22 Approval of preliminary SEA/EIA report 7.02.2014 21.02.2014 2w 1d
23 Publication of preliminary SEA/EIA report 22.02.2014 23.04.2014 8w 5d
24 Amendment of SEA/EIA report 24.04.2014 23.06.2014 8w 5d
25 Submission of SEA/EIA report 24.06.2014 24.06.2014 0w
26 Publication of amended SEA/EIA report 25.06.2014 23.08.2014 8w 4d
27 Approval of SEA/EIA report 24.08.2014 31.12.2015 70w 5d
ANNEX I
Amendment proposal Justification
1. Article II.2.1 Completion date of the SEA/EIA are time consuming processes and
Action: 31/12/2012 will not be finalised before 2015. As a
contingency in case the public consultation
may take time it is advisable to prolong the
Action until the end of eligibility period.
2. Article II.2.3 Activity 2 will be renamed Due to estimated costs the spatial planning
as Environmental and Legal Studies with and preliminary design will be undertaken
additional Milestones added as a separate Action. The Milestones must
be rearranged to illustrate the actual stages
of planned activities.
3. Article II.2.3 Activity descriptions: SEIA SEA was not part of Activity 1 and will be
will be removed from Activity 1 undertaken as SEA/EIA during Activity 2
4. Article II.2.3 Activity descriptions: SEA/EIA and JVS must be undertaken due to
Existing description of Activity 2 will be considerations detailed in the proposal.
completely rewritten Other considerations will be undertaken as
a separate Action.
5. Article II.2.3 Milestones: Milestones are Activity Milestones will be rewritten to
added for SEA/EIA and JVS reflect the actual progress of projected
actions.
6. Article II.3.3 Indicative Breakdown of Activity 1 was completed with lesser costs
Estimated Eligible Costs of the Action by than originally anticipated. The cost
Activity: Will be redrawn to reflect the breakdown is redrawn to reflect both the
actual costs incurred during Activity 1 actual costs incurred during the
and the projected costs of Activity 2 implementation of the Action and the
projected cost breakdown related to
amendment of Activity 2.
ANNEX I