Hello Mr. Rali,
in attachment I'm sending you plan for november. For december is plan not ready yet, we want to start changing conductors in station Keila and continue works on section Keila - Paaskyla. Working together on open line and station is the best solution, because of traffic suspension on open line Keila - Paaskyla, station Keila will not be so busy as normally and even only one platform can be needed for trains.
Best regards,
Tomas Krcma
EZ Praha
________________________________________
Odesílate: Mati Räli [
[email protected]]
Odesláno: 15. října 2012 20:11
To: Krčma Tomáš
Cc: Sergei Andrejev
Předmět: RE: inspection kontaktvork VA-KE, KE-KL
Dear Mr Krčma.
Thank you for the message. 2nd half of November is for us acceptable. For these sections should be applied also using permits from us (kasutusluba). Also, if it's possible, can You send us also working plans of November and December this year?
Best regards,
Mati Räli
ETSA
-----Original Message-----
From: Krčma Tomáš [mailto:
[email protected]]
Sent: Monday, October 15, 2012 8:41 PM
To: Mati Räli
Cc:
[email protected]
Subject: inspection kontaktvork VA-KE, KE-KL
Dear Mr. Rali,
I'd like to inform you, that we expect section Vasalemma (excl.) - Keila (excl.) to be finished and technical inspection organized on 19.11.2012 and section Klooga (incl.) - Keila (excl.) on 26.11.2012. Exact term we will know in november dependent on situation on building site.
I also appologize for not sending you "Ehitamise alustamise teatis" for sections Vasalemma - Lillekyla" on time. I'm sending now in attachment.
Best regards,
Tomas Krcma
manager
EZ Praha a.s., Tallinn office
Laki 26
Tallinn 12915
Phone (EST): +372 539 29 109
Phone (CZ): +420 602 472 131