Rahandusministeerium · 15. märts 2022
Sisu (failidest)
Ref. Ares(2022)2151051 - 24/03/2022
EUROPEAN
COMMISSION
Brussels, 4.3.2022
C(2022) 1433 final
ANNEX
SENSITIVE*
EMBARGO UNLIMITED
ANNEX
to the
Commission Decision
approving the Operational Arrangements between the Commission and Estonia
pursuant to Regulation (EU) 2021/241
Distribution only on a ‘Need to know’ basis - Do not read or carry openly in public places. Must be
stored securely and encrypted in storage and transmission. Destroy copies by shredding or secure
deletion. Full handling instructions https://euiOpa.eu/idb43PX
EN EN
ANNEX
Recovery anti Resilience Facility
Operational arrangements between the European Commission and Estonia
These operational arrangements enter into force on the signature date between:
(1) The European Commission, 200, rue de la Loi, B-1049 Bruxelles, Belgium, which is
represented for the purpose of the signature of this operational arrangements by
Commissioner Paolo Gentiioni;
hereinafter referred to as the “Commission”
on the one part,
and
(2) Republic of Estonia, represented by the Minister of Finance Keit Pentus-Rosimannus;
hereinafter referred to as “Estonia”
on the other part,
hereinafter separately referred to as a “Party” and collectively as the “Parties”,
WHEREAS:
(1) Regulation (EU) 2021/241 of the European Parliament and of the Council of 12 February
2021, establishing the Recovery and Resilience Facility (the “RRF Regulation”)
established the Recovery and Resilience Facility to provide Member States with financial
support with a view to achieving the milestones and targets of reforms and investments
as set out in their recovery and resilience plans.
(2) In accordance with Article 18(1) of the RRF Regulation, Estonia submitted to the
Commission a recovery and resilience plan (the “RRP”). By virtue of Council
Implementing Decision of 29 October 2021 on the approval of the assessment of the
recovery and resilience plan for Estonia (ST 12532/21; ST 12532/21 ADD 1; ST 12532/21
ADD 1 COR 1 REV 1), (the “Council Implementing Decision”) the Council approved the
1
assessment of the RRP and determined a financial contribution of EUR 969 299 213
linked to the satisfactory fulfilment of milestones and targets.
(3) Pursuant to Article 20(6) of the RRF Regulation, the Parties should enter into operational
arrangements to further specify the elements mentioned therein.
The Parties have agreed the following:
1. ARRANGEMENTS AND TIMETABLE FOR MONITORING AND
IMPLEMENTATION AND THE RELEVANT INDICATORS RELATING TO
THE FULFILMENT OF THE ENVISAGED MILESTONES AND TARGETS
1.1. To facilitate smooth cooperation and the effective implementation of the RRP, the
Parties agree to maintain regular exchanges in relation to the implementation of the
relevant reforms and investment projects.
1.2. Estonia designates the Ministry of Finance of the Republic of Estonia as the Coordinator
(the “Coordinator”) to act as the interlocutor of the Commission for the overall
implementation of the RRP and of these Operational Arrangements. The Coordinator is
responsible at national level for coordinating and monitoring the effective
implementation of the measures envisaged and the achievement of the objectives set in
the RRP.
1.3. The Commission designates the Recovery and Resilience Task Force and the
Directorate General for Economic and Financial Affairs as the interlocutors for the
monitoring of the implementation of the RRP on behalf of the Commission.
1.4. The Coordinator and the Commission shall hold at least quarterly exchanges to take
stock of progress on the implementation of the RRP. Such exchanges may take place in
person in Estonia or in Brussels. They may also take place virtually or, if both Parties
agree, via written form. While maintaining the capacity to hold physical or virtual
meetings at short notice, such meetings should ordinarily be planned a minimum of 10
days in advance, with a defined agenda.
1.5. The exchanges to take stock of progress on the implementation of the RRP shall, as a
standing item on the agenda, discuss the timeline for payment requests as set out in
Section 3. The Coordinator shall assess and inform the Commission of any significant
risks to the timeline for the completion of any milestone or targets, notably where that
may have implications for the timeline of the associated payment request.
1.6. The Coordinator and the Commission may organise meetings on ad hoc topics outside
of the exchanges to take stock of progress on the implementation of the RRP. Such ad-
hoc meetings are encouraged to discuss investments and reforms in the RRP that may
2
raise specific implementation challenges. These meetings shall take place in a timely
manner to identify possible implementation issues. Ad-hoc meetings may also be
required to discuss specific implementation issues that cut across multiple components
(e.g. compliance with the Do No Significant Harm principle), to ensure consistency
across the RRP.
1.7. The Coordinator may nominate specific government entities that are in charge of the
actual implementation of specific reforms and investments. As part of the monitoring of
the RRP, the Commission may ask the Coordinator to organise technical meetings with
such nominated entities to seek further information. The Coordinator shall be in copy of
all exchanges and shall be invited to all technical meetings that may take place. These
technical meetings may take place on a more regular basis than the meetings with the
Coordinator, to enable a more frequent monitoring of the reforms and investments
included under each component of the RRP and to identify possible implementation
issues in advance of the exchanges. An overview of the technical meetings that are
taking place will be discussed in the meetings with the Coordinator.
1.8. While respecting internal processes and timing, and in order to facilitate the
implementation of the RRP and the assessment of payment requests, the Coordinator or
nominated specific government entities are encouraged to share with the Commission
any relevant information on the progress in the implementation of the RRP, in order to
discuss in a timely manner its alignment with the relevant provisions in the Council
Implementing Decision.
1.9. Annex I to these Operational Arrangements further specifies the milestones, targets and
relevant indicators laid down in the Council Implementing Decision to measure the
progress towards the achievement of the reforms and investment projects of the RRP.
1.10. Annex II to these Operational Arrangements further specifies the arrangements and
timetable for monitoring laid down in the Council Implementing Decision.
1.11. In accordance with Article 27 of the RRF Regulation, Estonia shall report in the context
of the European Semester on the progress made in the achievement of its RRP, including
these Operational Arrangements and on the common indicators set out in accordance
with Article 29(4) of the RRF Regulation. Such reporting shall take place each year, by
30 April and 15 October on the progress made in the achievement of the RRP, including
these Operational Arrangements, and by 28 February and 31 August on those common
indicators. Annexes I and II specify the arrangements for the reporting linked to these
Operational Arrangements. The Commission and Estonia have agreed that common
indicators 4 and 13, as specified in the Annex to the delegated act adopted under Article
29(4) of the RRF Regulation, are not relevant in the context of the Estonian RRP.
1.12. In order to ensure effective coordination and complementarity of Union funding in
accordance with Article 28 of the RRF Regulation, Estonia shall include in such
3
reporting any investment or reform supported under its RRP that has or is receiving
funding from any other Union programme and the relevant amount. In order to establish
a mechanism of coordination, the Commission and Estonia shall discuss as relevant the
coordination and complementarity with other Union funding during their exchanges.
1.13. In the context of Article 28 of the RRF Regulation, the Commission and Estonia agree
to jointly organise an annual event with the participation of those responsible for
implementing the RRP and other relevant stakeholders, to discuss complementarity,
synergy, coherence and consistency between the implementation of the RRP and the
other Union programmes. In addition, this event may serve as a horizontal platform to
exchange views on the state of implementation of the RRP in view of ensuring close
cooperation between all actors involved.
2. ARRANGEMENTS FOR ACCESS TO DATA
2.1. The arrangements that Estonia has proposed in order to ensure full access by the
Commission to relevant underlying data are set out in the Council Implementing
Decision.
2.2. Annex I specifies the minimum information (i.e. verification mechanisms) that supports
the due justification of the request for payment. Estonia shall send this information to
the Commission together with the payment request. Where relevant, the Commission
may request samples of the evidence. In accordance with Article 24(3) of the RRF
Regulation, the satisfactory fulfilment of milestones and targets shall presuppose that
measures related to previously satisfactorily fulfilled milestones and targets have not
been reversed by the Member State. Estonia shall notify the Commission of any change
in the documentation identified in the verification mechanism in Annex I on which that
assessment was made, which is of a material nature to affect such assessment or the
assessment of future milestones and targets.
2.3. Additionally, Estonia shall ensure that, upon request, the Commission has full access to
the underlying relevant data that supports the due justification of the request for
payment, both for the assessment of the request for payment in accordance with Article
24(3) of the RRF Regulation and for audit and control purposes in accordance with
Article 22(2)(e) of the RRF Regulation. This information will be provided to the
Commission by the Ministry of Finance.
3. TIMELINE FOR PAYMENT REQUESTS
In accordance with Article 24 of the RRF Regulation, upon completion of the relevant agreed
milestones and targets indicated in the RRP, Estonia shall submit a duly justified request for
payment of the financial contribution. The relevant milestones and targets for each instalment
4
are contained in the Council Implementing Decision. The indicative timeline for such payment
requests is the following:
Financial Contribution
Expected date of submission of
Amount payment request
(quarter and year)
First Instalment EUR 145 394 882 Q2 2022
Second Instalment EUR 145 394 882 Q4 2022
Third Instalment EUR 145 394 882 Q3 2023
Fourth Instalment EUR 145 394 882 Q3 2024
Fifth Instalment EUR 145 394 882 Q2 2025
Sixth Instalment EUR 145 394 882 QI 2026
Seventh Instalment EUR 96 929 921 Q3 2026
4. AMENDMENTS
The Operational Arrangements may be modified by mutual consent between the Parties. Such
amendments may take place by an exchange of letters. The Parties consent that the entities
designated as the Coordinator and the interlocutors for the monitoring of the implementation of
the RRP on behalf of the Commission in Clause 1.2 and 1.3 respectively may be amended by
notification.
For the Commission For Estonia
Represented by
Commissioner for Economy
Signed on Signed on
22. 03. 2022
5
Annex I
Milestones, Targets and Related Indicators
Non-Repayable Support
Qualitative Quantitative indicators Date for Responsibility for Further
Seq. Related measure (reform Milestone ƒ
Name indicators (for targets) completion reporting and specification (if Verification mechanism Milestone and target description
№ or investment) Target
(for milestones) implementation necessary)
Unit Baseline Goal Quarter Year
Summary document duly A call for proposals to support the
ustifying how the milestone digital transformation of businesses,
(including all the constitutive together with the award criteria, shall
elements) was satisfactorily be published by the Ministry of
fulfilled. Economic Affairs and
This document shall include as Communications.
an annex a copy of the The evaluation criteria and the
publication of the call for conditions for granting support shall be
proposals demonstrating defined on the basis of an analysis of
Call for proposals Ministry of
1.1 Digital Publication of the alignment with the the needs of Estonian companies and
with award criteria Economic Affairs
1 transformation Milestone notice of the call Q2 2022 requirements of the description the expected impact of the measure.
and award and
in enterprises for proposals of the milestone and, in Eligibility criteria shall also ensure that
conditions Communications
particular, containing the the selected projects comply with the
selection criteria that ensure ‘Do no significant harm' Technical
compliance with the ‘Do no Guidance (2021/C58/01) through the
significant harm’ Technical use of an exclusion list and the
Guidance (2021/C58/01 ), as requirement of compliance with the
specified in the CID Annex. relevant ED and national
environmental legislation.
Summary document duly Number of enterprises to which grants
ustifying how the target shall be awarded by the Ministry of
(including all the constitutive Economic Affairs and Communications
Number of elements) was satisfactorily to support their digital transformation
Ministry of
1.1 Digital enterprises fulfilled. in accordance with the call for
Economic Affairs
2 transformation Target Award of grants being 0 110 Q4 2023 This document shall include as proposals.
and
in enterprises awarded a an annex the award contracts
Communications
grant showing that the supported
investments comply with the
terms of reference.
Ministry of Summary document duly Number of enterprises to which grants
1.1 Digital Number of
Economic Affairs ¡ustifying how the target shall be awarded by the Ministry of
3 transformation Target Award of grants enterprises 110 230 Q4 2025
and (including all the constitutive Economic Affairs and Communications
in enterprises being
Communications to support their digital transformation
6
Non-Repayable Support
Qualitative Quantitative indicators Date for Responsibility for Further
Seq. Related measure (reform Milestone /
Name indicators (for targets) completion reporting and specification (if Verification mechanism Milestone and target description
№ or investment) Target
(for milestones) implementation necessary)
Unit Baseline Goal Quarter Year
awarded a elements) was satisfactorily in accordance with the call for
grant fulfilled. proposals.
This document shall include as
an annex the award contracts
showing that the supported
investments comply with the
temis of reference, in addition
to those already submitted
under Target 2.
Summary document duly The work on the adoption of
iustifying how the milestone international standards and best
(including all the constitutive practices for the use of digital
elements) was satisfactorily technologies in construction and the
Adoption of fulfilled. management of buildings shall be led
international This document shall include as and co-ordinated by the Ministry of
Adoption of Ministry of
1.2 standards and best an annex the following Economic Affairs and
international Economic Affairs
4 Development Milestone practices for the Q4 2024 documentary evidence: Communications, with the introduction
standards and best and
of e-construction use of digital a) copy of the secondary of a construction data classification
practices Communications
technologies in egislation introducing a system, the creation of a publicly
construction construction data classification available database for construction
system; materials and construction products
o) certificate of completion of and the introduction of building
the database and the link to information modelling in the field of
the database. property maintenance.
Summary document duly The public services provided for in the
¡ustifying how the milestone e-construction development plan shall
(including all the constitutive be developed, operational and made
elements) was satisfactorily public on the e-construction platform.
fulfilled. Training material shall also be made
Entry into service This document shall include as available to users.
of interfaces an annex the following This includes services related to the
Availability of Ministry of
1.2 between the e- documentary evidence: built environment - such as building
public services on Economic Affairs
5 Development Milestone construction Q4 2025 a) the e-construction and planning permits, building registry
the e-construction and
of e-construction platform and the development plan; (logbook), and the renovation
platform Communications
related public b) for each of the services passport.
services provided on the e-construction
platform, a description of the
corresponding services
accessible and a summary of
the training material (both with
the corresponding web links).
7
Non-Repayable Support
Qualitative Quantitative indicators Date for Responsibility for Further
Seq. Related measure {reform Milestone/
Name indicators (for targets) completion reporting and specification (if Verification mechanism Milestone and target description
№ or investment) Target
(for milestones) implementation necessary)
Unit Baseline Goal Quarter Year
Summary document duly Number of completed projects for
ustifying how the target development and/or implementation of
(including all the constitutive digital construction tools and
elements) was satisfactorily prototypes of innovative digital
fulfilled. solutions drawing on the e-
Completion of Ministry of This document shall include as construction platform.
1.2 Number of
development and Economic Affairs an annex a list of projects,
6 Development Target projects 0 120 Q4 2025
prototyping and each with a short description of
of e-construction completed
projects Communications the project and its contribution
to the development of digital e-
construction services, as well
as a reference to the project
web page with an approved
project final report
Summary document duly Number of projects developing an
ustifying how the target eFTI platform which have received a
1.3 eFTI (electronic (including all the constitutive positive grant decision.
Ministry of
Development Freight Transport Number of elements) was satisfactorily
Economic Affairs
7 of digital Target Information) projects 0 5 Q2 2023 fulfilled.
and
waybills platforms launched This document shall include as
Communications
services development an annex the grant decisions
for each of the projects
launched.
Summary document duly Number of projects enabling transport
justifying how the target and logistics operators to be
(including all the constitutive connected to eFTI platforms and use
1.3
eCMR (electronic Ministry of elements) was satisfactorily eCMR which have received a positive
Development Number of
Consignment Economic Affairs fulfilled. grant decision.
8 of digital Target projects 0 270 Q4 2024
Note) interface and This document shall include as
waybills launched
developments Communications an annex a list of the projects
services
launched, each with the date
of the launch and a reference
number of the grant decision.
Summary document duly Number of eFTI and eCMR projects
ustifying how the target completed, contributing to the
1.3 (including all the constitutive deployment of digital waybills.
Ministry of
Development Number of elements) was satisfactorily
Total number of Economic Affairs
9 of digital Target projects 0 275 Q4 2025 fulfilled.
projects completed and
waybills completed This document shall include as
Communications
services an annex a list of the projects,
each with a reference number
of the completion report.
8
Non-Repayable Support
Qualitative Quantitative indicators Date for Responsibility for Further
Seq. Related measure (reform Milestone /
Name indicators (for targets) completion reporting and specification (if Verification mechanism Milestone and target description
№ or investment) Target
(for milestones) implementation necessary)
Unit Baseline Goal Quarter Year
Summary document duly An external body shall analyse the
lustifying how the milestone impact of the support measure on the
Adoption of ex
[including all the constitutive road freight transport sector and
1.3 post evaluation
Ex-post evaluation Ministry of elements) was satisfactorily deliver an evaluation report, which
Development report by the
of the development Economic Affairs fulfilled. shall be adopted by the Ministry of
10 of digital Milestone Ministry of Q2 2026
and deployment of and This document shall include as Economic Affairs and
waybills Economic Affairs
the digital waybills Communications an annex the copy of the ex Communications.
services and
post evaluation report adopted
Communications
by the Ministry anda
corresponding web link.
Copy of the publication in the The secondary legislation necessary
Official Journal (or in the public for the application and allocation of
information system of the support shall enter into force. The
Ministry of Education) of the conditions for support shall be
secondary legislation and established through a ministerial
reference to the relevant deaee, which shall be coordinated
Entry into force of provisions indicating the entry with the Ministry of Finance and the
1.4 Skills secondary into force, accompanied by a State Shared Service Centre.
reform for the legislation setting Entry into force of Ministry of document duly justifying how The ministerial decree shall consist of
11 digital Milestone out the terms of secondary Q2 2022 Education & the milestone (including all the the following elements:
transformation support for the legislation Research constitutive elements) was objective of the measure,
of businesses development of satisfactorily fulfilled description of supported activities,
digital skills • beneficiaries and target groups,
• conditions for implementation,
- eligible costs and used
simplifications.
- conditions for payments,
■ conditions for reporting and
monitoring.
Summary document duly Number of people enrolled in training
justifying how the target activities supported under this
(including all the constitutive measure, consisting of awareness
1.4 Skills elements) was satisfactorily raising for SME managers, and
reform for the Ministry of fulfilled. upskilling and retraining for ICT
Enrolment in Number of
12 digital Target 0 500 Q4 2023 Education & This document shall include as specialists. A minimum of 35% of
training activities participants
transformation Research an annex an anonymised list of participants enrolled in these training
of businesses participants, indicating for each activities shall be women.
their gender and the name of
the training they have been
enrolled for.
9
Non-Repayable Support
Qualitative Quantitative indicators Date for Responsibility for Further
Seq. Related measure (reform Milestone
Name indicators (for targets) completion reporting and specification (if Verification mechanism Milestone and target description
№ or investment) Target
(for milestones) implementation necessary)
Unit Baseline Goal Quarter Year
Summary document duly Number of people having completed
justifying how the target their training course through the
(including all the constitutive training activities supported under this
1.4 Skills elements) was satisfactorily measure, including awareness-raising
reform for the Ministry of fulfilled. for SME managers, and upskilling and
Completion of Number of
13 digital Target 0 2000 Q2 2026 Education & This document shall include as retraining for ICT specialists. A
training activities participants
transformation Research an annex an anonymised list of minimum of 35% of participants having
of businesses the individual certificates completed these training activities
showing which of the training shall be women.
courses to improve digital skills
were completed.
Summary document duly Number of upskilling and retraining
justifying how the target modules developed with detailed
(including all the constitutive training content, structure and training
Number of elements) was satisfactorily materials to provide training related to
curricula fulfilled. digital skills. New curricula developed
1.4 Skills
registered This document shall include as for these modules shall be registered
reform for the Number of new Ministry of
in Estonia’s an annex, for each of the 5 in Estonia's Education Information
14 digital Target upskilling and 0 5 Q4 2023 Education &
Education upskilling and retraining System (EHIS).
transformation retraining modules Research
Information modules, a summary of the
of businesses
System training, its contribution to
(EHIS). improving digital skills,
including its content (copy of
curricula), and the
coresponding web link.
Summary document duly Number of established qualification
justifying how the target standards for ICT specialists from the
(including all the constitutive national register of qualification
Number of elements) was satisfactorily standards which have been analysed
qualification fulfilled, in particular describing and adapted as and if needed.
1.4 Skills
Review of standards the analysis and adaptations
reform for the Ministry of
qualification analysed made to the qualification
15 digital Target 0 5 Q4 2024 Education &
standards for ICT and standards.
transformation Research
specialists. adapted as This document shall include as
of businesses
and if an annex a list of renewed
needed qualification standards and link
to the website, where the
renewed qualification
standards are published.
10
Non-Repayable Support
Qualitative Quantitative indicators Date for Responsibility for Further
Seq. Related measure (reform Milestone
Name indicators (for targets) completion reporting and specification (if Verification mechanism Milestone and target description
№ or investment) Target
(for milestones) implementation necessary)
Unit Baseline Goal Quarter Year
A summary document duly The preparatory tasks needed to draw
justifying how the milestone up export strategies shall be
(including all the constitutive completed. These tasks include:
elements) was satisfactorily - an analysis of which external
fulfilled. markets are important to develop
This document shall include as strategies,
an annex the following - an analysis of the interests of
1.5 Supporting the
documentary evidence: businesses,
competitiveness of
a) the analysis of the interests ■ a mapping of the needs of exporting
enterprises in foreign Preparation of the
Completion of Ministry of Foreign of businesses; enterprises to increase their
16 markets Milestone development of Q2 2022
preparatory tasks Affairs з) the mapping of needs of competitiveness on export markets,
strategies
exporting enterprises and their the ranking of the needs.
1.5.1 Country and regional
ranking;
strategies
c) justification for the selection
of external markets for which
strategies are to be drawn up
based on the aforementioned
analysis, mapping and ranking
of interests/needs and the
value added to be achieved.
Summary document duly Tenders for drawing up strategies and
ustifying how the milestone product packages with a view to
(including all the constitutive obtaining detailed market information
elements) was satisfactorily on foreign markets shall be carried out
1.5 Supporting the fulfilled. by the Ministry of Foreign Affairs. The
competitiveness of This document shall include as corresponding contracts shall be
enterprises in foreign an annex a copy of the signed.
Procurement of Signature of Ministry of Foreign
17 markets Milestone Q2 2024 publication of the call for
studies contracts Affairs
tenders demonstrating
1.5.1 Country and regional alignment with the
strategies requirements of the description
of the milestone and the list of
the contracts signed containing
references to the selection
criteria.
1.5 Supporting the In the context of Summary document duly Number of national and/or regional
competitiveness of this measure, justifying how the target export strategies which shall be
enterprises in foreign Number of country Number of ‘pro-active smart (including all the constitutive developed. These strategies shall
Ministry of Foreign
18 markets Target and regional export strategies 0 13 Q2 2026 advice for elements) was satisfactorily contain comprehensive analyses and
Affairs
strategies published companies’ shall fulfilled, including an provide pro-active smart advice for
1.5.1 Country and regional mean enhanced explanation of how the pro- companies entering and operating in
strategies digital experience foreign markets.
11
Non-Repayable Support
Qualitative Quantitative indicators Date for Responsibility for Further
Seq. Related measure (reform Milestone ƒ
Name indicators (for targets) completion reporting and specification (if Verification mechanism Milestone and target description
№ or investment) Target
(for milestones) implementation necessary)
Unit Baseline Goal Quarter Year
for enterprises active smart advice has been
seeking to enter achieved.
or establish This document shall include as
themselves in an annex a copy of each
overseas markets. strategy and the corresponding
An enhanced web link.
digital experience
means a digital
environment
accessible to all
registered
enterprises to a)
test their export
capacity, b) check
entry
'equirements into
strategic markets
and c) the
availability of
support.
1.5 Supporting A summary document duly A preparatory analysis allowing the
the ustifying how the milestone definition of the content and the
competitiveness of (including all the constitutive locations of the business centres shall
enterprises Preparatory elements) was satisfactorily be prepared by the Ministry of Foreign
in foreign analysis to define Delivery of a fulfilled. Affairs. The analysis shall reveal
Ministry of Foreign
19 markets Milestone the content and the preparatory Q2 2022 This document shall include as where to set up business centres to
Affairs
locations of analysis an annex the analytical report increase demand for Estonian-made
1.5.2 innovative business centres enabling the selection of products and services in export
business content and locations including markets.
centres in key the corresponding value added
export markets for export to be achieved.
1.5 Supporting A summary document duly Number of business centres opened
the ¡ustifying how the target by the Ministry of Foreign Affairs to
competitiveness of (including all the constitutive support companies in entering and
enterprises elements) was satisfactorily operating in important export markets,
in foreign Number of Number of fulfilled. as well as to help them to promote
Ministry of Foreign
20 markets Target business centres business 0 Ί Q2 2026 This document shall include as Estonian-made products and services
Affairs
opened centres an annex a list of the business in a way that takes into account the
1.5.2 Innovative centres opened with links to specificities of local business
business their web presence or (if any) environment and culture.
centres in key recent activities, information on
export markets physical premises and
12
Non-Repayable Support
Qualitative Quantitative indicators Date for Responsibility for Further
Seq. Related measure (reform Milestone /
Name indicators (for targets) completion reporting and specification (if Verification mechanism Milestone and target description
№ or investment) Target
(for milestones) implementation necessary)
Unit Baseline Goal Quarter Year
employees, as well as any Key
°erformance Indicators or
other numerical targets to be
achieved by the business
centres in the medium term.
A summary document duly Based on an analysis, fire Ministry of
justifying how the milestone Foreign Affairs shall select global
(including all the constitutive digital mission destinations and impact
elements) was satisfactorily groups to increase the added value of
fulfilled. Estonian digital services exports,
1.5 Supporting the
This document shall include as ncrease the export capacity of
competitiveness of Setting-up of Decisions on the
an annex the following Estonian companies, among which
enterprises in foreign impact groups and composition of the
documentary evidence: ICT companies in particular, and
markets selection of impact groups and Ministry of Foreign
21 Milestone Q2 2022 a) list of global digital mission attract additional foreign investments
destinations for the destinations of Affairs
destinations for innovation.
1.5.3 Global e-export global digital the global digital
a) explanation of the selection
impact groups and virtual missions missions
of impact groups, expert
stages
profiles and mission
destinations, including the
selection criteria, the
underlying analysis and the
expected value added.
A summary document duly At least 14 missions shall be carried
justifying how the target out by the global impact groups set up
[including all the constitutive by the Ministry of Foreign Affairs to
elements) was satisfactorily increase the added value of Estonian
fulfilled. digital services exports, increase the
Number of This document shall include as export capacity of Estonian
1.5 Supporting the missions carried an annex the following companies, among which ICT
competitiveness of out by the global documentary evidence: companies in particular, and attract
Total of
enterprises in foreign impact groups and a) list of missions carried out, additional foreign investments for
number of
markets number of major Ministry of Foreign including the location and innovation.
22 Target missions 0 29 Q2 2026
events in which Affairs target audience, any Estonia shall be represented through
and events
1.5.3 Global e-export Estonia was corresponding web links, and virtual stages’ in at least 15 events.
carried out
impact groups and virtual represented mission reports for each of the
stages through 'virtual missions;
stages’ b) list of virtual stages in
business events including their
location and target audience,
any corresponding web links
and a short description of each
event.
13
Non-Repayable Support
Qualitative Quantitative indicators Date for Responsibility for Further
Seq. Related measure (reform Milestone /
Name indicators (for targets) completion reporting and specification (if Verification mechanism Milestone and target description
№ or investment) Target
(for milestones) implementation necessary)
Unit Baseline Goal Quarter Year
A summary document duly The Ministry of the Environment shall
justifying how the milestone reform the existing Working Group on
Ministry of the
(including all the constitutive Green Technology (set up in 2020)
Environment
elements) was satisfactorily into the RRP's Green Transition Task
Creation of a
fulfilled. Force to coordinate the measures on
Green Transition Ministry of
2.1 Green Set up of a task This document shall include as he green transition of companies, and
Task Force to Economic Affairs
23 transition of Milestone force and working Q4 2021 an annex the following mprove cooperation and exchange of
implement and and
enterprises groups documentary evidence: nformation among the public sector,
monitor the green Communications
a) adopted decision on stakeholders and interest groups. The
transition
establishing the RRP’s Green necessary working groups shall be set
Ministry of Rural
Transition Task Force up for specific measures.
Affairs
b) mandate of the Task Force
and of its working groups.
Summary document duly The Green Transition Task Force shall
Ministry of the
justifying how the milestone review the existing Circular Economy
Environment
(including ail the constitutive activities and different action plans into
Adoption of the elements) was satisfactorily a single Circular Economy Action Plan
Ministry of
2.1 Green Circular Economy Circular Economy fulfilled. that will lead the Estonian transition to
Economic Affairs
24 transition of Milestone Action Plan by the Action Plan Q4 2022 This document shall include as Circular Economy.
and
enterprises Green Transition adopted an annex the copy of the
Communications
Task Force adopted Circular Economy
Action Plan and a link to the
Ministry of Rural
website where the action plan
Affairs
can be accessed.
Copy of the publication in the The secondary legislation necessary
relevant public ministerial for the application and allocation of
documentation system of the support shall enter into force. It shall
secondary legislation and contain provisions ensuring that any
reference to the relevant action supported under this measure
provisions (a) indicating the is focused on areas contributing to the
Entry into force of
Ministry of entry into force and (b) reduction of greenhouse gas
secondary
Education & ensuring that any action emissions or the adaptation to climate
2.2 Green skills to support legislation setting Entry into force of
Research supported under this measure change.
25 the green transition of Milestone out the terms of secondary Q2 2022
is focused on areas
enterprises support for the legislation
Ministry of the contributing to the reduction of
development of
Environment greenhouse gas emissions or
green skills
the adaptation to climate
change, accompanied by a
document duly justifying how
the milestone (including all the
constitutive elements) was
satisfactorily fulfilled.
14
Non-Repayable Support
Qualitative Quantitative indicators Date for Responsibility for Further
Seq. Related measure (reform Milestone /
Name indicators (for targets) completion reporting and specification (if Verification mechanism Milestone and target description
№ or investment) Target
(for milestones) implementation necessary)
Unit Baseline Goal Quarter Year
Summary document duly Number of upskilling and retraining
justifying how the target modules developed including detailed
(including all the constitutive training content, structure and training
elements) was satisfactorily materials to provide training related to
fulfilled. green skills.
This document shall include as
2.2 Green skills to support Number of Ministry of
Number of an annex, for each of the
26 the green transition of Target upskilling and 0 5 Q4 2023 Education &
modules upskilling and retraining
enterprises retraining modules Research
modules, a summary of the
training, its contribution to
improving green skills,
including its content, structure,
and the list of the training
materials developed.
Summary document duly Number of people having completed
justifying how the target one of the training courses supported
(including all the constitutive through this measure.
elements) was satisfactorily
People taking part fulfilled.
2.2 Green skills to support Ministry of
in upskilling and Number of This document shall include as
27 the green transition of Target 0 2830 Q2 2026 Education &
retraining participants an annex an anonymised list of
enterprises Research
programmes the individual certificates
proving which of the training
courses to improve green
competences the certificate
holders have completed.
Summary document duly A project manager shall be recruited
justifying how the milestone and a broad-based group of
(including all the constitutive stakeholders shall be set up to
elements) was satisfactorily coordinate investment planning and
fulfilled. implementation. The role of the project
This document shall include as manager shall be set out to gather
Establishment of a Ministry of the
2.3 Green Recruitment of a an annex the following information from market participants
working group to Environment
technologies project manager documentary evidence: and design the necessary support
28 Milestone plan and set up the Q4 2021
development and set up of a a) work contract concluded measures and procurement. The
development Environmental
programme working group with the project manager (with working group shall be composed of
programme Investment Centre
personal or sensitive parties involved in the development of
information blacked out); entrepreneurship and shall undertake
b) a list of members of the to meet at least three times a year to
working group with their take stock of developments in
function; investment-related activities and
provide recommendations for further
15
Non-Repayable Support
Qualitative Quantitative indicators Date for Responsibility for Further
Seq. Related measure (reform Milestone /
Name indicators (for targets) completion reporting and specification (if Verification mechanism Milestone and target description
№ or investment) Target
(for milestones) implementation necessary)
Unit Baseline Goal Quarter Year
c) meeting schedule of the action. The working group shall draw
working group; up provisions related to the selection
d) copy of the document of actions to be supported under the
containing the plan development programme in such a
determining how the selection way that it is ensured that each action
criteria for actions to be directly contributes either to lowering
supported will be set. greenhouse gas emissions or
supporting adaptation to climate
change.
Summary document duly The public procurement processes for
ustifying how the milestone at least 5 development clusters shall
(including all the constitutive be completed and the contracts shall
elements, notably the number be awarded to the winning parties.
of start-ups having participated Support measures shall be designed
in the call for proposals) was and their first rounds shall be opened
satisfactorily fulfilled. to at least 10 start-ups. The selection
This document shall include as processes shall ensure that each
Contracts signed an annex the following supported action directly contributes
Set up of the Ministry of the
2.3 Green for all development documentary evidence: either to lowering greenhouse gas
Green Environment
technologies clusters and a) contracts signed by the emissions or supporting adaptation to
29 Milestone Technologies Q2 2024
development support measures contractor and the competent climate change.
Development Environmental
programme designed and authority for at least 5
Programme Investment Centre
opened development clusters;
b) copy of the publication of
the call for proposals for start
ups ensuring that each
supported action directly
contributes either to lowering
greenhouse gas emissions or
supporting adaptation to
climate change.
Summary document duly Number of clusters supported by the
ustifying how the target development programme.
(including all the constitutive
Number of clusters
Ministry of the elements) was satisfactorily
2.3 Green supported through
Environment fulfilled.
technologies the Green Number of
30 Target 0 5 Q2 2026 This document shall include as
development Technology clusters
Environmental an annex the certificates of
programme Development
Investment Centre completion signed by the
Programme
contractor and the competent
authority demonstrating that
the cluster developments have
16
Non-Repayable Support
Qualitative Quantitative indicators Date for Responsibility for Further
Seq. Related measure (reform Milestone /
Name indicators (for targets) completion reporting and specification (if Verification mechanism Milestone and target description
№ or investment) Target
(for milestones) implementation necessary)
Unit Baseline Goal Quarter Year
been completed and the
dusters are operational, and
specifying their location.
Summary document duly Number of start-ups supported by the
ustifying how the target development programme and which
(including all the constitutive have received resources from private
elements) was satisfactorily investors during or after the
fulfilled. devetopment programme.
Number of start This document shall include as
ups supported an annex a list of supported
through the Green Ministry of the start-ups showing for each the
2.3 Green
Technology Environment name, the registry code in the
technologies Number of
31 Target Development 0 10 Q2 2026 commercial register, the
development start-ups
Programme and Environmental supported actions and the
programme
which have Investment Centre resources received from
received private private investors; with extracts
investment from the companies’ financial
statements showing the
resources they have attracted
from private investors during or
after the development
orogramme.
Copy of the publication in the The conditions for granting support
Official Journal of the shall be enacted by a decree of the
ministerial decree setting out responsible minister. The
the terms and conditions of requirements set shall include
grant eligibility, and reference eligibility criteria to ensure that the
to the relevant provisions selected projects comply with the 'Do
Entry into force of indicating the entry into force, no significant harm' Technical
2.4 Modernisation
the ministerial Ministry of accompanied by a document Guidance (2021 /С58/01 ) by means of
of the business Entry into force of
decree setting out Economic Affairs duly justifying how the an exclusion list and compliance with
32 models in Milestone the ministerial Q2 2022
the terms and and milestone (including all the relevant EU and national
manufacturing decree
conditions of grant Communications constitutive elements) was environmental legislation. The
companies
eligibility satisfactorily fulfilled. selection/eligibility criteria shall specify
This document shall include as that the supported activities and/or
an annex the extract of the enterprises contribute to a climate
official documents containing neutral economy, resilience and
the selection criteria that climate change adaptation including
ensure compliance with the circular economy objectives such as
Do no significant harm’ in-house implementation of circular
17
Non-Repayable Support
Qualitative Quantitative indicators Date for Responsibility for Further
Seq. Related measure (reform Milestone
Name indicators (for targets) completion reporting and specification (if Verification mechanism Milestone and target description
№ or investment) Target
(for milestones) implementation necessary)
Unit Baseline Goal Quarter Year
Technical Guidance economy principles, transfer of
(2021/C58/O1), as specified in transport and storage of companies to
the CID Annex.ln the case of new foundations.
ETS installations, this
document shall contain the
following information:
1) a unique identifier, the
name, the location, the
Installation ID/Aircraft Operator
ID in the European Union
Transaction Log (EUTL) as
established by Art. 5 of the
Commission Regulation (EU)
389/2013;
2) the projected level of GHG
emissions per unit of product
for awarded projects with
activities under the EU ETS;
3) brief description of the
project and technologies
used.ln case the projected
GHG emissions are not
expected to decrease to
significantly below benchmark,
an explanation of the reasons
why this is not possible should
be provided.
Summary document duly Projects having received a grant
justifying how the target disbursement in accordance with the
(including all the constitutive eligibility conditions set out in the call
elements) was satisfactorily for proposals to introduce business
fulfilled. models that support the transition to a
Ministry of
2.4 Modernisation This document shall include as climate-neutral economy, resilience
Economic Affairs
of the business an annex a list of projects and adaptation to climate change,
Number of projects Number of and
33 models in Target 0 70 Q4 2025 having received a grant including circular economy objectives.
supported projects Communications
manufacturing disbursement showing, for
companies each item, the beneficiaries,
Enterprise Estonia
the reference number of the
payment order, the area of
intervention/action supported
and a brief summary of the
expected contribution to the
18
Non-Repayable Support
Qualitative Quantitative indicators Date for Responsibility for Further
Seq. Related measure (reform Milestone /
Name indicators (for targets) completion reporting and specification (if Verification mechanism Milestone and target description
№ or investment) Target
(for milestones) implementation necessary)
Unit Baseline Goal Quarter Year
transition to a climate-neutral
economy, resilience and
adaptation to climate change,
including circular economy
objectives.
In the case of ETS
installations, this document
shall contain the unique
identifier, the name, the
location, the Installation
ID/Aircraft Operator ID in the
European Union Transaction
Log (EUTL) as established by
Art. 5 of the Commission
Regulation (EU) 389/2013.
Summary document duly Call for proposals to support resource
ustifying how the milestone efficient green technologies and the
(including all the constitutive valorisation of bio-resources shall be
elements) was satisfactorily published and open for applications,
fulfilled. ‘ncluding eligibility criteria to ensure
This document shall include as that the selected projects comply with
an annex a copy of the the ‘Do no significant harm' Technical
publication of the call for Guidance (2021/C58/01 ) by means of
proposals demonstrating an exclusion list and compliance with
Ministry of the
alignment with the relevant EU and national
Environment
requirements of the description environmental legislation. The
of the milestone and, in selectlon/eligibility criteria shall specify
Publication of the Environmental
2.5 Deployment Publication of call particular, containing the that the supported activities and/or
notice for calls for Investment Centre
34 of resource-efficient green Milestone for proposals for Q2 2022 selection criteria that ensure enterprises contribute to a climate
proposals for
technologies grants compliance with the ‘Do no neutral economy, resilience and
grants Ministry of Rural
significant harm' Technical climate change adaptation
Affairs
Guidance (2021/C58/01), as
specified in the CID Annex.
PRIA
In the case of ETS
installations, this document
shall contain the following
information:
1) a unique identifier, the
name, the location, the
Installation ID/Aircraft Operator
ID in the European Union
Transaction Log (EUTL) as
19
Non-Repayable Support
Qualitative Quantitative indicators Date for Responsibility for Further
Seq. Related measure (reform Milestone /
Name indicators (for targets) completion reporting and specification (if Verification mechanism Milestone and target description
№ or investment) Target
(for milestones) implementation necessary)
Unit Baseline Goal Quarter Year
established by Art. 5 of the
Commission Regulation (Ell)
389/2013;
2) the projected level of GHG
emissions per unit of product
for awarded projects with
activities under the EU ETS;
3) brief description of the
project and technologies
used.In case the projected
GHG emissions are not
expected to decrease to
significantly below benchmark,
an explanation of the reasons
why this is not possible should
be provided.
Ministry of the Summary document duly Award of the contracts to at least 25
Environment ustifying how the target projects selected under the
(including all the constitutive competitive call for proposals, for
elements) was satisfactorily green technologies for industrial plants
fulfilled. and for valorisation of bio-resources,
This document shall include as in compliance with the temis of
Environmental
an annex the following reference
Number of Investment Centre documentary evidence:
2.5 Deployment
contracts awarded Contracts a) copy of the financing
35 of resource-efficient green Target 0 25 Q4 2023
following the call awarded decisions (contracts) awarded;
technologies
for proposals o) an explanation of the
Ministry of Rural correspondence of the
supported investments to the
Affairs
terms of reference.
PRIA
Ministry of the Summary document duly Number of completed projects to
Environment justifying how the milestone mprove resource efficiency through
(including all the constitutive the enhancement of green
2.5 Deployment
Number of projects Number of Environmental elements) was satisfactorily technologies and bio-resources, on
36 of resource-efficient green Target 0 25 Q2 2026
completed projects Investment Centre fulfilled. This document shall the basis of calls for proposals and
technologies
include as an annex the final established eligibility criteria.
Ministry of Rural reports of the projects signed
Affairs by the beneficiary and
20
Non-Repayable Support
Qualitative Quantitative indicators Date for Responsibility for Further
Seq. Related measure (reform Milestone /
Name indicators (for targets) completion reporting and specification (if Verification mechanism Milestone and target description
№ or investment) Target
(for milestones) implementation necessary)
Unit Baseline Goal Quarter Year
approved by the competent
PRIA authority demonstrating that
the projects have been
completed and are in line with
the requirements of the target.
Summary document duly A contractual agreement shall be
ustifying how the milestone signed between the Ministry of
(including all the constitutive Economic Affairs and Communications
elements) was satisfactorily and SmartCap to manage the Green
fulfilled. Fund, which shall contain:
This document shall include as - Investment objectives to invest in
an annex the contract signed enterprises and activities contributing
Signature of Ministry of by the Ministry of Economic to a climate-neutral economy and to
contractual Economic Affairs Affairs and Communications improving resilience to climate
agreement and and SmartCap to manage the change, including awareness-raising
between the Signature of Communications Green Fund demonstrating measures,
37 2.6 Green Fund Milestone Ministry of contractual Q4 2021 alignment with the Eligibility criteria for compliance with
Economic Affairs agreement SA Kred Ex/ requirements of the milestone the 'Do no significant harm’ Technical
and Enterprise Estonia and, in particular, containing Guidance (2021/C58/01 ) of supported
Communications the selection criteria that beneficiaries through the use of
and SmartCap SmartCap ensure compliance with the sustainability proofing, an exclusion
'Do no significant harm' list and the requirement of compliance
Technical Guidance with the relevant EU and national
(2021 /С58/01 ), as specified in environmental legislation.
the CID Annex and the
relevant Union and national
environmental legislation.
Summary document duly SmartCap shall adopt the investment
justifying how the milestone policy for the Green Fund, in line with
(including all the constitutive the contractual agreement signed
elements) was satisfactorily between the Ministry of Economic
Ministry of fulfilled. Affairs and Communications and
Adoption of the Economic Affairs This document shall include as SmartCap, including the investment
Investment policy
investment policy and an annex the adopted objectives and the eligibility criteria to
38 2.6 Green Fund Milestone document adopted Q4 2021
document by Communications investment policy in line with ensure compliance with the ‘Do no
by SmartCap
SmartCap the requirements of the significant harm’ Technical Guidance
milestone and, in particular, (2021 /С58/01 ) of supported
SmartCap containing the selection criteria beneficiaries under this measure
that ensure compliance with through the use of sustainability
the 'Do no significant harm' proofing, the requirement of
Technical Guidance compliance with the relevant EU and
21
Non-Repayable Support
Qualitative Quantitative indicators Date for Responsibility for Further
Seq. Related measure (reform Milestone /
Name indicators (for targets) completion reporting and specification (if Verification mechanism Milestone and target description
№ or investment) Target
(for milestones) implementation necessary)
Unit Baseline Goal Quarter Year
(2021/C58/01), as specified in national environmental legislation, and
the CID Annex. the requirement for beneficiaries that
derived more than 50% of their
revenues during the preceding
financial year from activities or assets
in the exclusion list to adopt and
publish green transition plans.
Summary document duly At least EUR 60 million shall be
justifying how the target invested by the Green Fund in venture
(including all the constitutive capital funds or enterprises in line with
elements) was satisfactorily the investment policy.
fulfilled.
This document shall include as
an annex a list of investments
Volume of
Ministry of by the Green Fund showing for
investments in Volume of
Economic Affairs each item the amount
venture capital invested 60 000
39 2.6 Green Fund Target 0 Q4 2024 and invested, the beneficiaries
funds or equity capital (in 000
Communications (final recipients of funds), the
investments in EUR)
area of intervention/action
enterprises
SmartCap supported and a brief
description of the expected
contribution to a climate
neutral economy and to
improving resilience to climate
change, including awareness
raising measures.
Summarydocumentduly At least EUR 100 million shall be
justifying how the target nvested by the Green Fund in venture
(including all the constitutive capital funds or enterprises in line with
elements) was satisfactorily the investment policy.
fulfilled.
Volume of This document shall include as
Ministry of
investments in Volume of an annex a list of investments
Economic Affairs
venture capital invested 60 000 00 100 000 by the Green Fund in addition
40 2.6 Green Fund Target Q2 2026 and
funds or equity capital (in 0 000 to those under Target 39
Communications
investments in EUR) showing for each item the
enterprises amount invested, the
SmartCap
beneficiaries, the area of
intervention/action supported
and a brief description of the
expected contribution to a
climate-neutral economy and
22
Non-Repayable Support
Qualitative Quantitative indicators Date for Responsibility for Further
Seq. Related measure (reform Milestone /
Name indicators (for targets) completion reporting and specification (if Verification mechanism Milestone and target description
№ or investment) Target
(for milestones) implementation necessary)
Unit Baseline Goal Quarter Year
to improving resilience to
climate change, including
awareness-raising measures.
Copy of the publication in the Development of project selection
Official Journal of the criteria, and entry into force of the
ministerial decree on the ministerial decree on the conditions for
conditions for granting support granting support for projects related to
for projects related to integrated green hydrogen
integrated green hydrogen technologies. The terms of reference
technologies, and reference to for this support shall include eligibility
the relevant provisions (a) criteria that ensure that the objectives
indicating the entry into force of the selected projects comply with
and (b) ensuring compliance the ‘Do no significant harm’ Technical
with the ‘Do no significant Guidance (2021/C58/01) through the
harm’ Technical Guidance use of an exclusion list and the
(2021/C58/01 ), as specified in requirement of compliance with the
Ministry of the CID Annex, accompanied relevant EU and national
Economic Affairs by a document duly justifying environmental legislation.
2.7 Creating Entry into force of and how the milestone (including
opportunities for the ministerial Communications all the constitutive elements)
Entry into force of
the uptake of decree setting out was satisfactorily fulfilled.
41 Milestone the ministerial Q4 2022
renewables-based green the terms and Ministry of the In the case of ETS
decree
hydrogen conditions for Environment nstallations, this document
technologies granting support shall contain the following
Environmental information:
Investment Centre 1) a unique identifier, the
name, the location, the
Installation ID/Aircraft Operator
ID in the European Union
Transaction Log (EUTL) as
established by Art. 5 of the
Commission Regulation (EU)
389/2013;
2) the projected level of GHG
emissions per unit of product
for awarded projects with
activities under the EU ETS;
3) brief description of the
project and technologies used.
23
Non-Repayable Support
Qualitative Quantitative indicators Date for Responsibility for Further
Seq. Related measure (reform Milestone
Name indicators (for targets) completion reporting and specification (if Verification mechanism Milestone and target description
№ or investment) Target
(for milestones) implementation necessary)
Unit Baseline Goal Quarter Year
In case the projected GHG
emissions are not expected to
decrease to significantly below
benchmark, an explanation of
the reasons why this is not
possible should be provided.
Summary document duly The necessary equipment for green
ustifying how the milestone hydrogen production shall be
(including all the constitutive purchased, installed and put in
elements) was satisfactorily operation by project promoters
fulfilled. selected in the call for proposals.
This document shall include as
an annex the following
documentary evidence:
a) certificates of completion
signed by the contractor and
Ministry of
the project promoter
Economic Affairs
demonstrating that the
and
2.7 Creating equipment has been installed,
Technologies and Procurement, Communications
opportunities for is operational and is in line
equipment to installation and
the uptake of with the requirements for this
42 Milestone create complete start of operation QI 2025 Ministry of the
renewables-based green measure described in the CID
green hydrogen of technologies Environment
hydrogen annex;
value chains and equipment
technologies b) a list of equipment showing
Environmental
for each item the type, the
Investment Centre
reference number and the
location;
c) in the case of ETS
installations, the unique
identifier, the name, the
location, the Installation
ID/Aircraft Operator ID in the
European Union Transaction
Log (EUTL) as established by
Art. 5 of the Commission
Regulation (EU) 389/2013;
2.7 Creating Grants allocated to Ministry of Summary document duly Grants shall be allocated to
opportunities for renewables-based Economic Affairs justifying how the target investments in renewables based
49490
43 the uptake of Target green hydrogen EUR 0 Q2 2026 and (including all the constitutive green hydrogen technologies in line
000
renewables-based green technologies Communications elements) was satisfactorily with the investment policy,
hydrogen representing at fulfilled.
24
Non-Repayable Support
Qualitative Quantitative indicators Date for Responsibility for Further
Seq. Related measure (reform Milestone /
Name indicators (for targets) completion reporting and specification (if Verification mechanism Milestone and target description
№ or investment) Target
(for milestones) implementation necessary)
Unit Baseline Goal Quarter Year
technologies least EUR 49.49 Ministry of the This document shall include as representing at least EUR 49.49
million Environment an annex a list of investments million
in renewables based green
Environmental hydrogen technologies
Investment Centre showing for each item the
allocated grant amount, the
beneficiaries and the location
and a short description of the
project.
Summary document duly Creation of a Data Management Team
justifying how the milestone in Statistics Estonia through the
(including all the constitutive recruitment of expert staff tasked with
elements) was satisfactorily coordinating the data governance
Setting up a data fulfilled. framework and supporting other public
management team This document shall include as authorities. In addition, posts shall be
in the Statistical Establishment of an annex the following created at the Ministry of Economic
3.1 Creation and Ministry of
Office, the Ministry the necessary documentary evidence: Affairs and Communications and at
development of a centre Economic Affairs
of Economic organisational a) a copy of the description of the State Information System Agency
44 of excellence for data Milestone Q4 2021 and
Affairs and structure for the responsibilities (job to carry out development projects. By
governance and open Communications
Communications coordinating data description) of the newly the end of 2021, at least five people
data
and the State management recruited employees across shall be recruited across the three
Information the three entities; entities.
System Authority b) details about the newly
established teams, such as
their composition and when
employees were recruited on
their new job.
Summary document duly Number of completed projects
justifying how the target contributing to ensuring an improved
(including all the constitutive reusability of data from public
elements) was satisfactorily institutions, with up-to-date and
fulfilled. accurate descriptions of databases
3.1 Creation and Ministry of
Completion of data This document shall include as and datasets.
development of a centre Economic Affairs
quality Number of an annex a list of projects
45 of excellence for data Target 0 430 Q2 2025 and
improvement projects showing for each item the
governance and open Communications
projects information about the
data
concerned dataset(s) (typically
a brief description of the
dataset(s), data holder and
volume of the data) and the
nature of the improvements.
25
Non-Repayable Support
Qualitative Quantitative indicators Date for Responsibility for Further
Seq. Related measure (reform Milestone /
Name indicators (for targets) completion reporting and specification (if Verification mechanism Milestone and target description
№ or investment) Target
(for milestones) implementation necessary)
Unit Baseline Goal Quarter Year
Summary document duly The number of datasets made public
ustifying how the target on the National Open Data Portal and
(including all the constitutive thus available from the EU Open Data
3.1 Creation and Ministry of elements) was satisfactorily portal shall be increased from 707 on
Publication of
development of a centre Number of Economic Affairs fulfilled. 13 August 2021 to 2600.
datasets on the
46 of excellence for data Target published 707 2600 Q4 2025 and This document shall include as
national open data
governance and open datasets Communications an annex a list of newly
portal
data published datasets showing for
each item the date of
publication, a short description
and a link.
Summary document duly Number of citizen life event services
ustifying how the target and/or proactive services launched
(including all the constitutive online.
elements) was satisfactorily The corresponding IT solutions
fulfilled. enabling the provision of the services
This document shall include as shall be operational at least in the
3.2 Development of Ministry of an annex the following basic parts of a given service and are
Launch of personal Number of
event services and Economic Affairs documentary evidence: subject to a further development
life event services services
47 proactive digital Target 0 2 Q4 2022 and a) a description of each of the during the implementation of the
and/or pro-active which are
public services for Communications life event services launched measure.
services operational
individuals online, with the date of the The selection of concerned services
launch and a link; shall be based on the development
b) extract of the relevant parts olan for personal life event and
of the technical specifications proactive services.
of the IT tools and reports of
their testing upon development
completion.
Summary document duly Number of citizen life event services
justifying how the target and/or proactive services launched
(including all the constitutive online.
elements) was satisfactorily The corresponding IT solutions
fulfilled. enabling the provision of the services
3.2 Development of Ministry of
Number of This document shall include as shall be operational at least in the
event services and Launch of personal Economic Affairs
services an annex the following basic parts of a given service and are
48 proactive digital Target event services and 2 10 Q4 2025 and
which are documentary evidence: subject to a further development
public services for pro-active services Communications
operational a) a description of each of the during the implementation of the
individuals
life event services launched measure.
online in addition to those The selection of concerned services
under target 47, with the date shall be based on the development
of the launch and a link; plan for personal life event and
proactive services.
26
Non-Repayable Support
Qualitative Quantitative indicators Date for Responsibility for Further
Seq. Related measure (reform Milestone /
Name indicators (for targets) completion reporting and specification (if Verification mechanism Milestone and target description
№ or investment) Target
(for milestones) implementation necessary)
Unit Baseline Goal Quarter Year
b) extract of the relevant parts
of the technical specifications
of the IT tools and reports of
their testing upon development
completion.
Summary document duly Number of IT development projects
justifying how the target contributing to the implementation of
(including all the constitutive the business event services and
elements) was satisfactorily gateway that have successfully
fulfilled. deployed new developments online.
This document shall include as These development projects shall be
an annex the following either directly related to the
Number of documentary evidence: development of the digital gateway for
Deployment of IT
projects a) a description of the project entrepreneurs or to the development
developments Ministry of
that have and the corresponding of business-event services, which
3.3 Development of event contributing to the Economic Affairs
successfull developments successfully additionally include the development
49 services and digital Target implementation of 0 1 Q4 2022 and
y deployed deployed online, including their of various related systems for
gateway for entrepreneurs the business event Communications
new contribution to the interfacing with the digital gateway. As
services and
developme implementation of the business a result of each development project,
gateway
nts online event services and gateway; at least a minimally functional IT
o) steering group's protocol solution shall be completed (i.e., the IT
stating the completion of the IT solution shall be operational at least in
developments and their the basic parts for the end users
testing, and receipt for key (entrepreneurs) and shall be able to
works performed: provide feedback for further
c) link to the tools, as development needs during the reform
accessible to the users. implementation period or afterwards).
Summary document duly Number of IT development projects
ustifying how the target contributing to the implementation of
(including all the constitutive the business event services and
elements) was satisfactorily gateway that have successfully
Number of
Deployment of IT fulfilled. deployed new developments online.
projects
developments Ministry of This document shall include as These development projects shall be
3.3 Development of that have
contributing to the Economic Affairs an annex the following either directly related to the
event services and successfull
50 Target implementation of 1 10 Q4 2025 and documentary evidence: development of the digital gateway for
digital gateway for y deployed
the business event Communications a) a description of the projects entrepreneurs or to the development
entrepreneurs new
services and and the corresponding of business-event services, which
developme
gateway developments successfully additionally include the development
nts online
deployed online (in addition to of various related systems for
those under target 49), interfacing with the digital gateway. As
including their contribution to a result of each development project,
the implementation of the at least a minimally functional IT
Tl
Non-Repayable Support
Qualitative Quantitative indicators Date for Responsibility for Further
Seq. Related measure (reform Milestone /
Name indicators (for targets) completion reporting and specification (if Verification mechanism Milestone and target description
№ or investment) Target
(for milestones) implementation necessary)
Unit Baseline Goal Quarter Year
business event services and solution shall be completed (i.e., the IT
gateway; solution shall be operational at least in
b) steering group's protocol the basic parts for the end users
stating the completion of the IT (entrepreneurs) and shall be able to
developments and their provide feedback for further
testing, and receipt for key development needs during the reform
works performed; mplementation period or afterwards).
c) link to the tools, as
accessible to the users.
Summary document duly Number of digital public services
justifying how the target available through the platform of the
(including all the constitutive virtual assistant.
elements) was satisfactorily
fulfilled.
Number of This document shall include as
public an annex the following
Ministry of
Access to digital digital documentary evidence:
3,4 #Burokratt programme Economic Affairs
public services services a) a description of the digital
51 (national virtual assistant Target 0 1 Q2 2022 and
through the virtual accessible public service accessible
platform and ecosystem) Communications
assistant platform through the through the platform of the
virtual virtual assistant;
assistant b) proof of the access to the
service through the virtual
assistant;
c) a link to the service, as
accessible to the users via a
browser.
Summary document duly Number of service environments in
ustifying how the target which the virtual assistant shall be
(including all the constitutive operational. A “service environment"
elements) was satisfactorily refers to a website of public
fulfilled. authorities.
Introduction of the Ministry of This document shall include as
Number of
3.4 #Bürokratt programme Bürokraft virtual Economic Affairs an annex:
service
52 (national virtual assistant Target assistant in digital 0 18 Q4 2025 and a) a list of the service
environmen
platform and ecosystem) public services Communications environments in which the
ts
environments virtual assistant is operational
(with the corresponding web
links);
b) proof that new service
environments are accessible
through Bürokraft
28
Non-Repayable Support
Qualitative Quantitative indicators Date for Responsibility for Further
Seq. Related measure (reform Milestone Z
Name indicators (for targets) completion reporting and specification (if Verification mechanism Milestone and target description
№ or investment) Target
(for milestones) implementation necessary)
Unit Baseline Goal Quarter Year
Summary document duly Number of digital public services
justifying how the target available through the platform of the
(including all the constitutive virtual assistant.
elements) was satisfactorily
fij ¡filled.
This document shall include as
Number of
an annex for the services
public
Ministry of addressed in addition to those
Access to digital digital
3.4 #Bürokratt programme Economic Affairs under target 51:
public services services
53 (national virtual assistant Target 1 20 Q4 2025 and a) a description of the digital
through the virtual accessible
platform and ecosystem) Communications public services accessible
assistant platform through the
through the platform of the
virtual
virtual assistant;
assistant
b) proof of the access to the
services through the virtual
assistant;
c) links to the services, as
accessible to the users via a
browser.
Summary document duly Basic IT services provided/shared
justifying how the milestone centrally shall open for subscription by
(including all the constitutive new users (ministries and other
elements) was satisfactorily authorities).
fulfilled.
This document shall include as
an annex the following
Opening of shared documentary evidence:
Ministry of
3.5 Reconfiguration of Development of server hosting and a) a description of the
Economic Affairs
basic digital services and centrally computer organisational changes carried
54 Milestone Q3 2022 and
safe transition to cloud delivered/shared IT workstation out to centralise the delivery of
Communications
infrastructure base services services to public basic IT services;
authorities b) the list and the description
of the services delivered
centrally as a result of these
changes;
c) certificates of completion of
the works for the development
of centrally delivered/shared IT
base services.
29
Non-Repayable Support
Qualitative Quantitative indicators Date for Responsibility for Further
Seq. Related measure (reform Milestone /
Name indicators (for targets) completion reporting and specification (if Verification mechanism Milestone and target description
№ or investment) Target
(for milestones) implementation necessary)
Unit Baseline Goal Quarter Year
Summary document duly plumber of information systems for
justifying how the target which the migration to the private
(including all the constitutive doud infrastructure shall be
elements) was satisfactorily completed.
fulfilled.
This document shall include as
Number of
an annex the following
Deployment of information Ministry of
3.5 Reconfiguration of documentary evidence:
national private systems Economic Affairs
basic digital services and a) certificates of completion
55 Target cloud infrastructure migrated to 0 10 Q4 2023 and
safe transition to cloud signed by the contractor and
by public the national Communications
infrastructure the competent authority
authorities private
demonstrating that the national
cloud
private cloud is operational;
b) a description of the
information systems migrated
to the national private cloud
including the date of
completion of the migration.
Summary document duly It shall become possible to host and
justifying how the milestone operate information systems migrated
(including all the constitutive to the private cloud from the data
Completion of the elements) was satisfactorily embassy. New hardware and licenses
extension of the Ministry of fulfilled. shall be acquired and set up for this
3.5 Reconfiguration of Extension of the
national private Economic Affairs This document shall include as purpose.
basic digital services and cloud infrastructure
56 Milestone cloud to the Q4 2023 and an annex proof of the
safe transition to cloud to the data
infrastructure of Communications acquisition of new hardware
infrastructure embassy
Estonia's data and licenses specifically aimed
embassy for the extension of the
national private cloud to the
infrastructure of the data
embassy.
Summary document duly Number of critical systems migrated to
justifying how the target the National Cloud Data Embassy
(including all the constitutive infrastructure and platform. Critical
Migration of critical Ministry of
3.5 Reconfiguration of elements) was satisfactorily systems are systems that are vital to
systems to the Number of Economic Affairs
basic digital services and fulfilled. the state's sustainability.
57 Target national cloud critical 0 10 Q4 2024 and
safe transition to cloud This document shall include as
infrastructure of systems Communications
infrastructure an annex a description of the
the data embassy
critical systems migrated to the
national doud infrastructure of
the data embassy, including
30
Non-Repayable Support
Qualitative Quantitative indicators Date for Responsibility for Further
Seq. Related measure (reform Milestone f
Name indicators (for targets) completion reporting and specification (if Verification mechanism Milestone and target description
№ or investment) Target
(for milestones) implementation necessary)
Unit Baseline Goal Quarter Year
the certificate of completion of
the migration.
Summary document duly Number of comprehensive security
justifying how the target tests carried out by the Information
Central security Ministry of (including all the constitutive System Authority - the test results
3.5 Reconfiguration of
testing of public Number of Economic Affairs elements) was satisfactorily shall be summarised in reports.
basic digital services and
58 Target authorities' tests 0 16 Q4 2024 and fulfilled.
safe transition to cloud
information performed Communications This document shall include as
infrastructure
systems an annex the reports
summarising each of the tests
performed.
Copy of the publication in the The following steps shall be completed
Official Journal for primary to allow the Centre for Strategic
legislation and the secondary Analysis to access and process data
Entry into force of legislation, and copy of the relevant to the detection and
the amendment of amendments to relevant prevention of money laundering and
Provision in the
the Money administrative acts that are terrorist financing:
law indicating the
Laundering and critical for achieving the (1) an amendment of the Money
3.6 Establishing the date of entry into
Terrorist Financing objectives described in the Laundering and Terrorist Financing
strategic analysis of force of amended
Prevention Act and Ministry of Finance milestone and in the CID and Prevention Act shall be published in
59 money laundering and Milestone act and entry into Q4 2024
of other legislative, reference to the relevant the Riigi Teataja and enter into force,
terrorist financing in force of other
administrative and provisions indicating the entry (2) amendments to the statutes of the
Estonia legislative,
contractual into force, accompanied by a relevant national datasets shall enter
administrative and
changes needed document duly justifying how into force,
contractual acts
for the Centre for the milestone (including all the (3) amendments to the terms and
Strategic Analysis constitutive elements) was conditions of Financial Intelligence
satisfactorily fulfilled, with Unit data exchange contracts shall be
appropriate links to the signed by the contracting parties.
underlying evidence.
Summary document duly The development of the ICT system
Development of
justifying how the milestone allowing real-time analysis to detect
the new real-time
(including all the constitutive and prevent money laundering shall
3.7 Information system for ICT analysis
Delivery of the new elements) was satisfactorily be completed. The system shall be
real-time strategic system for the
ICT system to the fulfilled. operational and used by the Financial
60 analysis of money Milestone Centre for Q2 2026 Ministry of Finance
Financial This document shall include as Intelligence Unit.
laundering and terrorist Strategic Analysis,
Intelligence Unit an annex the following
financing and delivery to the
documentary evidence:
Financial
a) certificates of completion
Intelligence Unit
signed by the contractor and
31
Non-Repayable Support
Qualitative Quantitative indicators Date for Responsibility for Further
Seq. Related measure (reform Milestone /
Name indicators (for targets) completion reporting and specification (if Verification mechanism Milestone and target description
№ or investment) Target
(for milestones) implementation necessary)
Unit Baseline Goal Quarter Year
the competent authority
demonstrating that the project
has been completed, is
operational and is in line with
the requirements of the
milestone;
b) examples of strategic
analysis produced by the
system and used by the
Financial Intelligence Unit or
other Law Enforcement
Authorities and/or statistics on
the functioning of the system.
Summary document duly Number of new sites (residential,
justifying how the target companies, establishments) covered
(including all the constitutive by VHCN (and which have thus the
elements) was satisfactorily possibility to get a connection of at
fulfilled. least 100 Mbps) thanks to the
This document shall include as measure.
Ministry of
Rollout of very high an annex a list of supported
3.8 Construction of very Economic Affairs
capacity Number of projects showing for each item
61 high capacity broadband Target 0 4000 Q4 2023 and
broadband network sites the beneficiaries of the
networks Communications
to new sites funding, the concerned
geographical area and the
number of sites which have
become eligible for Very High
Capacity Networks (with a
connection of at least 100
Mbps).
Summary document duly Number of additional sites (residential,
justifying how the target companies, establishments) covered
(including all the constitutive by VHCN (and which have thus the
elements) was satisfactorily possibility to get a connection of at
Ministry of fulfilled. least 100 Mbps) thanks to the
Rollout of very high
3.8 Construction of very Economic Affairs This document shall include as measure.
capacity Number of
62 high capacity broadband Target 4000 8097 Q4 2025 and an annex a list of supported
broadband network sites
networks Communications projects showing for each item
to new sites
the beneficiaries of the
funding, the concerned
geographical area, and the
number of sites which have
become eligible for Very High
32
Non-Repayable Support
Qualitative Quantitative indicators Date for Responsibility for Further
Seq. Related measure (reform Milestone /
Name indicators (for targets) completion reporting and specification (if Verification mechanism Milestone and target description
№ or investment) Target
(for milestones) implementation necessary)
Unit Baseline Goal Quarter Year
Capacity Networks (with a
connection of at least 100
Mbps), in addition to those
under target 61.
Summary document duly Conclusion of a cooperation
ustifying how the milestone agreement by SA KredEx/Enterprise
(including all the constitutive Estonia with county development
elements) has been centres by which in each county of
Conclusion of the
satisfactorily fulfilled. This Estonia SA KredEx/Enterprise Estonia
cooperation
Conclusion of the The renovation document shall include as an shall provide at least one trained
agreement
cooperation advice in annex the following specialist in the county development
stipulating Ministry of
agreement Harjumaa county documentary evidence: centre who shall provide advice on
conditions for Economic Affairs
4.1 Energy efficiency between SA is expected to be a) copies of the cooperation renovation.
63 Milestone cooperation Q4 2022 and
promotion KredEx/ Enterprise provided by the agreements between SA
between SA Communications
Estonia and county SA KredEx/Enterprise Estonia and
Kredex/Enterprise
development KredEx/Enterprise each of the 14 county
Estonia and county
centres Estonia. development centres;
development
b) documentary confirmation
centres
from SA KredEx/Enterprise
Estonia that renovation advice
is being provided directly in
Harjumaa county.
Summary document duly SA KredEx/Enterprise Estonia shall
Digital tools to ustifying how the milestone update the Housing homepage to
facilitate access to (including all the constitutive ensure fast, up-to-date and
information on elements) has been operational information for those
renovation satisfactorily fulfilled. This interested in renovation and for
Ministry of
including Operational user- document shall demonstrate applicants.
Economic Affairs
4.1 Energy efficiency visualising the friendly renovation that the Housing homepage Online digital tools shall be made
64 Milestone Q4 2024 and
promotion results of the website and pricing has been updated and the available to allow parties interested in
Communications
renovation and models digital tools as specified in the renovation to visualise the possible
estimating the cost milestone have been outcome and calculate the potential
of renovation have completed and are operational costs with and without support
become and include the link to the schemes when adding the parameters
operational homepage and the digital of their building.
tools.
Ministry of Summary document duly SA KredExiEnterpnse Estonia shall
Publication of calls
Publication of calls Economic Affairs ¡ustifying how the milestone publish calls for applications aimed at
4.2 Support for renovation for applications for
65 Milestone for housing Q2 2022 and (including all the constitutive improving the energy efficiency of
of apartment buildings residential
renovation grants Communications elements) has been residential apartment buildings. The
apartment
satisfactorily fulfilled. support shall be differentiated between
33
Non-Repayable Support
Qualitative Quantitative indicators Date for Responsibility for Further
Seq. Related measure (reform Milestone ƒ
Name indicators (for targets) completion reporting and specification (if Verification mechanism Milestone and target description
№ or investment) Target
(for milestones) implementation necessary)
Unit Baseline Goal Quarter Year
buildings This document shall indude as regions on the basis of the value of the
renovation grants an annex the following real estate, with a higher rate of
documentary evidence: support in regions with low average
a) copy of the publication of property value.
the call for applications Support shall be granted to renovation
including the technical projects that achieve an improvement
specifications showing that the of at least one energy efficiency class
call is in line with the or, in the case of complete
requirements of the milestone renovations, at least the energy
and of the description of the efficiency class C. The renovations
investment in the CID; shall correspond to at least medium
b) a description of the process depth renovations representing an
of obtaining and presenting ex average level of primary energy
ante and ex-post Energy savings of at least 30% as set out in
Performance Certificates. European Commission
Recommendation (EU) 2019/786. The
results shall be certified by ex-ante
and ex-post Energy Performance
Certificates.
Summary document duly At least 2 600 dwellings shall be
ustifying how the target renovated and achieve an
(including all the constitutive improvement of at least one energy
elements) has been efficiency class or, in the case of
satisfactorily fulfilled. complete renovations, at least the
This document shall indude as energy efficiency class C. The
an annex the following renovations shall correspond to at
documentary evidence: least medium-depth renovations
a) aggregated energy representing an average level of
Ministry of
performance certificate before primary energy savings of at least
Dwellings with Economic Affairs
4.2 Support for renovation Number of and after the renovation action; 30% as set out in European
66 Target improved energy 0 2600 Q4 2024 and
of apartment buildings dwellings b) the list of apartment Commission Recommendation (EU)
performance Communications
buildings together with the 2019/786. The results shall be certified
number of dwellings renovated by ex-ante and ex-post Energy
and, for each apartment Performance Certificates.
building, the renovation actions
completed, the registration
numbers of the energy
performance certificates before
and after the renovation action,
and expected energy saving
achieved.
34
Non-Repayable Support
Qualitative Quantitative indicators Date for Responsibility for Further
Seq. Related measure (reform Milestone /
Name indicators (for targets) completion reporting and specification (if Verification mechanism Milestone and target description
№ or investment) Target
(for milestones) implementation necessary)
Unit Baseline Goal Quarter Year
Summary document duly Annual emissions of at least 2 200
justifying how the target tons of CO2 equivalent have been
(including all the constitutive saved. The target shall be measured
elements) has been as the decrease of the greenhouse
satisfactorily fulfilled. gas (GHG) emissions as a sum of all
This document shall include as the renovation projects finished by
an annex the following 2024. The energy efficiency class for
documentary evidence: each renovated building shall be
a) overview of the renovation measured at the latest in 2025; and
actions carried out; their annual greenhouse gas
b) aggregated energy emissions estimated on this basis. The
Ministry of performance certificates before baseline shall refer to the estimated
Estimated annual
tons of Economic Affairs and after the renovation action greenhouse gas emissions of the
4.2 Support for renovation reduction of
67 Target N/A C02eq/yea 0 2200 Q2 2026 and to demonstrate gain in energy building prior to renovation. It shall be
of apartment buildings greenhouse gas
r Communications efficiency class; assessed if the activities of the support
emissions
c) a calculation based on the measure have been carried out and all
model of SA the necessary documents have been
KredEx/Enterprise Estonia for submitted by the apartment
energy consumption associations (such as Energy
demonstrating the decrease of Performance Certificate, audit). The
the greenhouse gas (GHG) calculation of the GHG emission
emissions as a sum of all the savings result shall be based on the
renovation projects finished by model of SA Kredex/Enterprise
2024. Estonia for energy consumption and
other relevant data. The results
achieved shall be delivered at the end
of the supporting activities.
Summary document duly SA KredEx/Enterprise Estonia shall
justifying how the milestone publish calls for applications aimed at
(including all the constitutive improving the energy efficiency of
elements) has been private residential buildings. The
satisfactorily fulfilled. support shall be differentiated between
Ministry of This document shall include as regions on the basis of the value of the
4.3 Support for renovation Economic Affairs an annex the following real estate, with a higher rate of
Published calls for
68 of small residential Milestone Publication of calls Q2 2022 and documentary evidence: a) the support in regions with low average
renovation grant
buildings Communications selection criteria, which include property value.
regional differentiation as well Support shall be granted to renovation
the requirement to achieve an projects that achieve an improvement
improvement of energy of energy efficiency or, in the case of
efficiency or, in the case of complete renovations, at least the
complete renovations, at least energy efficiency class C. The results
the energy efficiency class C; shall be certified by ex-ante and ex-
35
Non-Repayable Support
Qualitative Quantitative indicators Date for Responsibility for Further
Seq. Related measure (reform Milestone /
Name indicators (for targets) completion reporting and specification (if Verification mechanism Milestone and target description
№ or investment) Target
(for milestones) implementation necessary)
Unit Baseline Goal Quarter Year
3) the process of obtaining and post SA KredEx Energy Performance
presenting ex-ante and ex-posl calculations.
Energy Performance
Certificates.
Summary document duly At least 80 dwellings shall be
ustifying how the target renovated, and achieve an
[including all the constitutive improvement of energy efficiency or, in
elements) has been the case of complete renovations, at
satisfactorily fulfilled. least the energy efficiency class C.
This document shall include as The results shall be certified by ex
Ministry of
an annex the list of dwellings ante and ex-post KredEx Energy
4.3 Support for renovation Dwellings with Economic Affairs
Number of renovated and, for each Performance calculations.
69 of small residential Target improved energy 0 80 Q4 2024 and
dwellings dwelling, the renovation
buildings performance Communications
actions completed, the
registration numbers of the
energy performance
certificates before and after the
renovation action, and
expected energy saving
achieved.
Copy of the Government The Government shall adopt a
decision on investments decision on making the necessary
Government
needed to alleviate the nveslments to alleviate the defence
decision on Ministry of
defence related height related height restrictions on wind
4.4 Boosting the green investments Adoption of the Economic Affairs
restrictions on wind parks, parks.
70 transition in the energy Milestone needed to alleviate decision of the Q2 2021 and
accompanied by a document
economy the defence related Government Communications
duly justifying how the
height restrictions
milestone (including all the
on wind parks
constitutive elements) was
satisfactorily fulfilled.
Adoption of the Government decision on the Government decision on initiating the
decision of the initiation of the preparation preparation process of the National
Government on the process of the National Development Plan of the Energy
initiation of the Development Plan of the Sector shall be approved, defining the
Ministry of
4.4 Boosting the green preparation Adoption of the Energy Sector, defining the responsible entity (ies) and setting the
Economic Affairs
71 transition in the energy Milestone process of the decision of the Q4 2021 responsible entity(ies) and relevant deadlines. The development
and
economy National Government setting the relevant deadlines, plan shall address, inter alia, the
Communications
Development Plan and reference to the relevant objectives of increasing renewable
of the Energy provisions indicating the entry energy production, energy efficiency
Sector, the into force, accompanied by a and maintaining and improving
designation of document duly justifying how security of supply, as well as the
36
Non-Repayable Support
Qualitative Quantitative indicators Date for Responsibility for Further
Seq. Related measure (reform Milestone /
Name indicators (for targets) completion reporting and specification (if Verification mechanism Milestone and target description
№ or investment) Target
(for milestones) implementation necessary)
Unit Baseline Goal Quarter Year
those responsible the milestone (including all the cessation of the use of oil shale for
and deadlines constitutive elements) was electricity production in 2035 and the
satisfactorily fulfilled. phasing out of shale oil production by
2040.
Summary document duly Guidance materials necessary for
ustifying how the target facilitating and incentivising the
(including all the constitutive installation of renewable energy
elements) has been generating installations and energy
Entry into force of
satisfactorily fulfilled. storage facilities shall be published
the relevant
This document shall include as and relevant primary and/or secondary
primary and/or
Provision in the an annex the following legislation shall enter into force to
secondary
law indicating the documentary evidence: •emove the barriers to installation of
legislation and
entry into force of a) if relevant, a copy of the renewable energy facilities such as
publication of
the relevant Ministry of publication in the Official streamlining permitting procedures
4.4 Boosting the green guidance material
primary and/or Economic Affairs Journal of the relevant primary and other relevant identified barriers.
72 transition in the energy Milestone to alleviate the Q4 2024
entry into force of and and/or secondary legislation,
economy barriers for the
secondary Communications and reference to the relevant
installation of
legislation and orovisions indicating the entry
renewable energy
publication of into force;
generating
guidance material b) if relevant, a copy of the
installations and
publication of guidance
energy storage
material necessary for
facilities
facilitating and incentivising the
installation of renewable
energy generating installations
and energy storage facilities
Copy of the National The National Development Plan of the
Development Plan of the Energy Sector shall be approved by
Energy Sector as approved by the Government. The plan shall
the Government, accompanied include the actions related to the
by a document duly justifying phase-out of the use of oil shale for
Adoption of the
how the milestone (including electricity production in 2035 and of
National Ministry of
4.4 Boosting the green all the constitutive elements) shale oil production by 2040. It shall
Development Plan Document adopted Economic Affairs
73 transition in the energy Milestone Q4 2025 was satisfactorily fulfilled, in also include targets for electricity
of the Energy by the Government and
economy particular, how the actions and generation capacity to be replaced
Sector by the Communications
targets included in the plan with renewable energy.
Government
contribute to the phase-out of
the use of oil shale for
electricity production in 2035
and of shale oil production by
2040 and for electricity
37
Non-Repayable Support
Qualitative Quantitative indicators Date for Responsibility for Further
Seq. Related measure (reform Milestone /
Name indicators (for targets) completion reporting and specification (if Verification mechanism Milestone and target description
№ or investment) Target
(for milestones) implementation necessary)
Unit Baseline Goal Quarter Year
generation capacity to be
replaced with renewable
energy.
Summary document duly A co-financing agreement for
4.5 Programme justifying how the milestone electricity network investments shall
to strengthen the (including all the constitutive be concluded between the Ministry of
electricity grid elements) has been Economic Affairs and Communications
to increase Signature of satisfactorily fulfilled. and Elering AS. The contract shall set
renewable network Signature of a Ministry of This document shall include as out the expected results and
energy investment co contract with the Economic Affairs an annex a copy of the co deadlines.
74 Milestone Q1 2022
production financing contract transmission and financing agreement for
capacity and with transmission system operator Communications electricity network investments
adapt to climate system operator between the Ministry of
change (such as Economic Affairs and
protection Communications and Elering
against storms) AS setting out the expected
results and deadlines.
Summary document duly Increase in the connection capacities
justifying how the target for renewable energy installations in
(including all the constitutive the Estonian electricity transmission
elements) was satisfactorily network by at least 310 MW.
fulfilled.
This document shall include as
4.5 Programme
an annex the following
to strengthen the
documentary evidence:
electricity grid Additional
a) certificates of completion
to increase renewable energy
signed by the contractor and
renewable connection Additional Ministry of
Elering AS demonstrating that
energy capacity created connection Economic Affairs
75 Target 0 310 Q2 2026 the projects have been
production via investments capacity and
completed, are operational and
capacity and into the (MW) Communications
in line with the requirements of
adapt to climate transmission
the target;
change (such as network
b) documents signed by
protection
Elering AS verifying that the
against storms)
connection capacities for
renewable energy installations
in the Estonian electricity
transmission network have
increased by at least 310 MW
overall.
38
Non-Repayable Support
Qualitative Quantitative indicators Date for Responsibility for Further
Seq. Related measure (reform Milestone
Name indicators (for targets) completion reporting and specification (if Verification mechanism Milestone and target description
№ or investment) Target
(for milestones) implementation necessary)
Unit Baseline Goal Quarter Year
Summary document duly An open call shall be published by the
ustifying how the milestone Environmental Investment Centre to
(including all the constitutive support the grid connection costs of
elements) has been companies producing electricity from
satisfactorily fulfilled. renewable sources in industrial sites.
This document shall include as The call shall be based on project
an annex a copy of the call for selection criteria and award conditions
proposals containing the that ensure that the selected projects
selection criteria that ensure comply with the ‘Do no significant
compliance with the 'Do no rarm Technical Guidance
significant harm’ Technical (2021/C58/01 ) through the use of an
Guidance (2021/058/01), as exclusion list and the requirement of
specified in the CID Annex. compliance with the relevant EU and
In the case of ETS national environmental legislation.
nstallations, this document
shall contain the following
Publication of a
nformation:
4.6 Programme call for proposals Ministry of
1) a unique identifier, the
to boost energy for projects Call for proposals Economic Affairs
76 Milestone Q4 2022 name, the location, the
production in boosting energy published and
Installation ID/Aircraft Operator
industrial areas production in Communications
ID in the European Union
Industrial sites
Transaction Log (EUTL) as
established by Art. 5 of the
Commission Regulation (EU)
389/2013;
2) the projected level of GHG
emissions per unit of product
for awarded projects with
activities under the EU ETS;
3) brief description of the
project and technologies used.
In case the projected GHG
emissions are not expected to
decrease to significantly below
benchmark, an explanation of
the reasons why this is not
possible should be provided.
Additional Summary document duly Additional connection capacity for
4.6 Programme Connection Ministry of
connection ustifying how the target renewable electricity production in or
to boost energy capacity Economic Affairs
77 Target capacity for 0 28 Q2 2026 [including all the constitutive near industrial sites constructed for at
production in created and
renewable elements) was satisfactorily least 28 MW.
industrial areas (MW) Communications
electricity fulfilled.
39
Non-Repayable Support
Qualitative Quantitative indicators Date for Responsibility for Further
Seq. Related measure (reform Milestone /
Name indicators (for targets) completion reporting and specification (if Verification mechanism Milestone and target description
№ or investment) Target
(for milestones) implementation necessary)
Unit Baseline Goal Quarter Year
production in or This document shall indude as
near industrial an annex certificates of
sites connected to completion signed by the
the grid relevant entities I)
demonstrating that the projects
have been completed, are
operational and in line with the
requirements of the target; and
¡1) certifying that additional
connection capacity for
renewable electricity
production in or near industrial
sites has been constructed for
at least 28 MW.
Summary document duly An open call for proposals shall be
ustifÿing how the milestone published by the Environmental
(including all the constitutive Investment Centre to support pilot
elements) has been energy storage programmes.
satisfactorily fulfilled. The call shall be based on project
This document shall include as selection criteria and award conditions
an annex a copy of the that ensure that the selected projects
publication of the call for comply with the ‘Do no significant
Publication of a proposals demonstrating harm’ Technical Guidance
Ministry of
4.7 Pilot Energy call for proposals alignment with the (2021/C58/01) through the use of an
Call for proposals Economic Affairs
78 Storage Milestone for a pilot energy Q4 2022 requirements of the description exclusion list and the requirement of
published and
Programme storage of the milestone and, in compliance with the relevant EU and
Communications
programme particular, containing the national environmental legislation. The
selection criteria that ensure selection/eligibility criteria shall specify
compliance with the ‘Do no that the supported activities and/or
significant harm' Technical enterprises contribute to climate-
Guidance (2021/C58/01 ), as neutral economy, climate resilience
specified in the CID Annex as and climate change adaptation,
weil as with provisions on including circular economy objectives.
ownership and operation of
storage facilities.
Summary document duly The investment support scheme shall
justifying how the target result in the installation of heat storage
Additional heat Ministry of
4.7 Pilot Energy Capacity (including all the constitutive of at least 35 000 m3 in district heating
storage capacity Economic Affairs
79 Storage Target installed 0 35 000 Q2 2026 elements) was satisfactorily systems.
resulting from and
Programme (m3) fulfilled.
investment support Communications
This document shall include as
an annex certificates of
40
Non-Repayable Support
Qualitative Quantitative indicators Date for Responsibility for Further
Seq. Related measure (reform Milestone /
Name indicators (for targets) completion reporting and specification (if Verification mechanism Milestone and target description
№ or investment) Target
(for milestones) implementation necessary)
Unit Baseline Goal Quarter Year
completion signed by the
relevant entities i)
demonstrating that the projects
have been completed, are
operational and in line with the
requirements of the target; and
ii) certifying installation of heat
storage of at least 35 000 m3 in
district heating systems.
Summary document duly The investment support scheme shall
justifying how the target result in the installation of at least 4
(including all the constitutive MW of electricity storage capacity.
elements) was satisfactorily
fulfilled.
This document shall include as
Additional an annex the certificates of
Ministry of
4.7 Pilot Energy electricity storage Capacity completion signed by the
Economic Affairs
80 Storage Target capacity resulting installed 0 4 Q2 2026 relevant entities:
and
Programme from investment (MW) i) demonstrating that the
Communications
support projects have been completed,
are operational and in line with
the requirements of the target;
and
ii) certifying the installation of
at least 4 MW of electricity
storage capacity.
Summary document duly The Transport and Mobility
justifying how the milestone Development Plan 2021-2035 shall be
(including all the constitutive approved by the Government. It shall
elements) was satisfactorily include the creation of the Tallinn
fulfilled. capital region common transport
Adoption of the This document shall include as system, actions to facilitate uptake of
5.1 Deployment of safe, Adoption of the
Transportand Ministry of an annex the Transport and local biomethane, actions to develop
green, competitive, needs- Transport and
Mobility Economic Affairs Mobility Development Plan sustainable and active urban mobility
81 based and sustainable Milestone Mobility Q1 2022
Development Plan and 2021-2035 as approved by the in bigger towns following the logic of
transport and energy Development Plan
2021-2035 by the Communications Government. integrated transport corridors, planning
infrastructure 2021-2035
Government multimodal infrastructure, increasing
the connections, speed and safety of
rail, making the maritime transport
sector more competitive and greener
and connect it multimodally,
developing faster and safer road
41
Non-Repayable Support
Qualitative Quantitative indicators Date for Responsibility for Further
Seq. Related measure (reform Milestone /
Name indicators (for targets) completion reporting and specification (if Verification mechanism Milestone and target description
№ or investment) Target
(for milestones) implementation necessary)
Unit Baseline Goal Quarter Year
transport. The plan shall include a
target to reduce CO2 emissions by
700 000 tons (or 30%) compared to
2018 levels and reach a share of
renewables in the energy consumed in
the transport sector of 24% by 2035.
Summary document duly The implementation plan shall be
justifying how the milestone approved by the Steering Committee
(including all the constitutive of the Transport and Mobility
elements) was satisfactorily Development Plan 2021-2035.
fulfilled. It shall include the creation of the
This document shall include as Tallinn capital region common
Adoption of the
an annex a copy of the transport system, actions to facilitate
Implementation
adopted implementation plan. uptake of local biomethane, actions to
Plan for green
5.1 Deployment of safe, develop sustainable and active urban
sustainable public Ministry of
green, competitive, needs- Adoption of the mobility in bigger towns following the
transport Economic Affairs
82 based and sustainable Milestone Implementation Q4 2022 logic of integrated transport corridors,
development of the and
transport and energy Plan planning multimodal infrastructure,
Transport and Communications
infrastructure increasing the connections, speed and
Mobility
safety of rail, making the maritime
Development Plan
transport sector more competitive,
2021-2035
greener and connect it multimodally,
developing faster and safer road
transport. The implementation plan
shall include an annual reporting
obligation on the responsible minister
to the Government.
Summary document duly The implementation of key measures
ustifying how the milestone of the Transport and Mobility
(including all the constitutive Development Plan shall be completed,
elements) was satisfactorily including building and extending the
Implementation of
fulfilled. electrified railway lines from Tallinn to
several key
5.1 Deployment of safe, Implementation of This document shall include as Tartu and harmonising the public
measures of the Ministry of
green, competitive, needs- Transportand an annex the following transport system in the Tallinn capital
Transportand Economic Affairs
83 based and sustainable Milestone Mobility Q2 2026 documentary evidence: region (including common ticketing
Mobility and
transport and energy Development Plan a) certificate of completion and pricing systems).
Development Plan Communications
infrastructure 2021-2035 signed by the contractor and
2021-2035
the competent authority
completed
demonstrating which sections
of the electrified railway lines
from Tallinn to Tartu have
been built or extended in line
42
Non-Repayable Support
Qualitative Quantitative indicators Date for Responsibility for Further
Seq. Related measure (reform Milestone /
Name indicators (for targets) completion reporting and specification (if Verification mechanism Milestone and target description
№ or investment) Target
(for milestones) implementation necessary)
Unit Baseline Goal Quarter Year
with the requirements of the
milestone;
b) a copy of the description of
the new common ticketing and
pricing system for public
transport in the Tallinn capital
region (e.g. user guide,
passenger information), which
has been distributed on paper
or made available online to
users of the Tallinn transport
system;
c) copies of any arrangements
(e.g. contracts, MoU) among
the parties involved, i.e. public
transport authorities and
service providers, on the
sharing of costs and revenues
etc.
Summary document duly A contract shall be awarded for the
lustifying how the milestone construction of an electrified railway
(including all the constitutive track on the sections of Turba-Ellamaa
elements) was satisfactorily and Ellamaa-Risti over their total
fulfilled. length.
This document shall include as
Award of a railway an annex the following
construction documentary evidence:
Ministry of
contract for the a) award decision for the
5.2 Construction of a Economic Affairs
construction of a contract for the construction of
84 section of the westbound Milestone Contract signed Q2 2022 and
railway on the an electrified railway track on
Tallinn-Rohuküla railway Communications
sections of Turba- the section of Turba-Ellamaa
Ellamaa and over its total length;
Ellamaa-Risti b) award decision for the
contract for the construction of
an electrified railway track on
the section of Ellamaa-Risti
over its total length;
c) signed contract for a);
d) signed contract for b).
5.2 Construction of a Completion of new Km of Summary document duly Completion of an electrified railway
Ministry of
85 section of the westbound Target railway (ready for railway 0 15 Q4 2024 ustifying how the target track, ready for passenger traffic,
Economic Affairs
Tallinn-Rohuküla railway traffic) track (including all the constitutive between Turba and Risti on Tallinn-
43
Non-Repayable Support
Qualitative Quantitative indicators Date for Responsibility for Further
Seq. Related measure (reform Milestone /
Name indicators (for targets) completion reporting and specification (if Verification mechanism Milestone and target description
№ or investment) Target
(for milestones) implementation necessary)
Unit Baseline Goal Quarter Year
and elements) was satisfactorily Rohuküla line, connecting the West-
Communications fulfilled. Estonian railways to Tallinn's Old Port
This document shall include as and Tallinn Airport.
an annex certificates of
completion signed by the
contractors) and the
competent authority
demonstrating that the
electrified railway tracks have
been completed, are
operational and are in line with
the requirements of the target.
Summary document duly The architectural and engineering
justifying how the milestone design of the Rail Baltic Ülemiste
(including all the constitutive multimodal terminal shall be
elements) was satisfactorily completed and accepted by the
fulfilled. contracting authority Rail Baltic
This document shall include as Estonia OÜ and the works contract
5.3 Award of the
an annex the following shall be signed with the constructor for
Construction contract for the Ministry of
documentary evidence: the terminal building.
of the Rail construction of the Economic Affairs
a) certificates of acceptance of
66 Baltic Milestone Rail Baltic Contract signed Q1 2022 and
the architectural and
multimodal multimodal Communications
engineering design by the
joint terminal terminal building in
contracting authority Rail Baltic
in Tallinn Tallinn Estonia OÜ;
b) the contract signed by the
constructor for the construction
of the Rail Baltic Ülemiste
multimodal joint terminal
building.
Summary document duly The Consumer Protection and
justifying how the milestone Technical Surveillance Authority shall
(including all the constitutive issue a permit for use of the tunnel,
5.3
elements) was satisfactorily connecting St Petersburg road with
Construction Ministry of
fulfilled. Tallinn Airport below the Ülemiste
of the Rail Light traffic tunnel Economic Affairs
Completion of the This document shall include as terminal.
87 Baltic Milestone under the terminal Q4 2024 and
terminal passage an annex the permit for use of
multimodal authorised Communications
the tunnel connecting St
joint terminal
Petersburg road with Tallinn
in Tallinn
Airport below the Ülemiste
terminal, issued by the
Consumer Protection and
44
Non-Repayable Support
Qualitative Quantitative indicators Date for Responsibility for Further
Seq. Related measure (reform Milestone /
Name indicators (for targets) completion reporting and specification (if Verification mechanism Milestone and target description
№ or investment) Target
(for milestones) implementation necessary)
Unit Baseline Goal Quarter Year
Technical Surveillance
Authority.
Summary document duly Construction works for the Rail Baltic
justifying how the milestone Ülemiste multimodal terminal shall be
(including all the constitutive completed and all necessary
elements) was satisfactorily authorisations for use shall have been
fulfilled. obtained.
5.3 This document shall include as
Construction Ministry of an annex the following
of the Rail Economic Affairs documentary evidence:
Completion of the Construction works
88 Baltic Milestone Q1 2026 and a) certificates of completion
new railway station completed
multimodal Communications signed by the contractor and
joint terminal the competent authority
in Tallinn demonstrating that the project
has been completed;
b) authorisation for use of the
Rail Baltic Ülemiste multimodal
oint terminal issued by the
competent authority.
Summary document duly Tallinn Urban Planning and Utilities
ustifying how the milestone Board shall adopt the design of the
(including ail the constitutive tramway construction project.
elements) was satisfactorily
fulfilled.
Ministry of
Completion of the This document shall include as
Economic Affairs
5.4 Construction of the tramway Approval of the an annex the certificate of
89 Milestone Q4 2021 and
Tallinn Old Port tram line construction project design adoption of the project design
Communications
project design for the construction of the
Tallinn Old Port tramline
between Gonsiori street and
Põhja Puiestee, issued by the
Tallinn Urban Planning and
Utilities Board.
Summary document duly Works contract concluded between
Ministry of
justifying how the milestone Tallinn Urban Planning and Utilities
Contract signed for Economic Affairs
5.4 Construction of the Award of works (including all the constitutive Soard and the contractor for the
90 Milestone the construction of Q2 2022 and
Tallinn Old Port tram line contract elements) was satisfactorily construction of the tramway line
the tramway line Communications
fulfilled. between Gonsiori street and Põhja
Puiestee
45
Non-Repayable Support
Qualitative Quantitative indicators Date for Responsibility for Further
Seq. Related measure (reform Milestone
Name indicators (for targets) completion reporting and specification (if Verification mechanism Milestone and target description
№ or investment) Target
(for milestones) implementation necessary)
Unit Baseline Goal Quarter Year
This document shall include as
an annex the signed contract
for the construction of the
tramway line between Gonsiori
street and Põhja Puiestee.
Summary document duly The tramway section of 2500 meters
justifying how the target in length shall be completed and put
(including all the constitutive into service in accordance with the
elements) was satisfactorily letter authorisation issued by the City
fulfilled. of Tallinn
Ministry of
This document shall include as
Meters of Economic Affairs
5.4 Construction of the New tramway line an annex the certificates of
91 Target tramway 0 2500 Q2 2024 and
Tallinn Old Port tram line in operation completion signed by the
line Communications
contractor and the competent
authority demonstrating that
the project has been
completed, is operational and
is in line with the requirements
of the target.
Summary document duly An open call for investment by
ustifying how the milestone municipalities in bike- and walkways
(including all the constitutive shall be published.
elements) was satisfactorily
fulfilled.
This document shall include as
an annex the following
documentary evidence:
a) copy and link to the
Regulation of Minister of Public
Publication of the
5.5 Municipalities’ Administration on terms and
Call for proposals notice for call for
92 investments in bike- and Milestone Q4 2022 Ministry of Finance conditions for measure
for grants proposals for
walkways ’Municipalities' investments in
grants
bike-and/or walkways" as
published in the Official
Journal (www.riigiteataja.ee)
b) link to website of the state
Shared Service Centre (Riigi
Tugiteenuste Keskus) to the
information of the open call;
c) copy of public press release
with notice for call for proposal
for grants.
46
Non-Repayable Support
Qualitative Quantitative indicators Date for Responsibility for Further
Seq. Related measure (reform Milestone ƒ
Name indicators (for targets) completion reporting and specification (if Verification mechanism Milestone and target description
№ or investment) Target
(for milestones) implementation necessary)
Unit Baseline Goal Quarter Year
Summary document duly At least 24 kilometres of bike and
ustifying how the target walkways shall be built as a result of
(including all the constitutive the support scheme. These shall
elements) was satisfactorily generally be new ways. In justified
Bike- and
5.5 Municipalities' Km of bike- fulfilled, including extracts from cases, the reconstruction of existing
walkways
93 investments in bike- and Target and 0 24 Q4 2025 Ministry of Finance the electronic register bike- and walkways shall be allowed,
infrastructure
walkways walkways “e-toetus'· of the certificates of such as if the width of the existing
completed
completion (or equivalent walkway does not meet the standards,
evidence) of the bike- and/or making it impossible for walkers and
walkways. cyclists to move simultaneously in a
safe and non-Interference manner.
Copy of the publication in the Entry into force of the Regulation
Official Journal of the which shall:
legislation on the Hospital ■lay down the list of regional, central,
network development plan and local and rehabilitation hospitals in
Entry into force of reference to the relevant order to ensure equal access to health
6.1 A comprehensive the Government provisions indicating the entry care services;
Entry into force of Ministry of Social
94 change in the organisation Milestone Regulation on the Q4 2024 into force, accompanied by a • the requirements, objectives and
the Regulation Affairs
of health care in Estonia Hospital network summary document duly steps to be taken for consolidating the
development plan ustifying how the milestone hospital network;
(including all the constitutive ■the necessary investments for the
elements) was satisfactorily construction, renovation and re
fulfilled. profiling of the hospitals included in
frie list of hospitals.
Summary document duly The Strategic Framework for
ustifying how the milestone addressing health workforce shortages
(including all the constitutive shall outline:
Approval of the elements) was satisfactorily ■ measures on the organisation of
Approval of the Strategic fulfilled. health care services in the different
Strategic Framework for This document shall include as health sectors, in particular specialised
6.1 A comprehensive
Framework for addressing health Ministry of Social an annex the copy of the care,
95 change in the organisation Milestone Q4 2022
addressing health workforce Affairs adopted Strategic Framework ■ allocation of physical and human
of health care in Estonia
workforce shortages by the for addressing health resources to ensure the provision of
shortages Minister of Health workforce shortages and a link health care throughout the territory,
and Labour to the website where the ■ financing, governance and
Strategic Framework can be information exchange mechanisms
accessed. that ensure performance throughout
the country.
47
Non-Repayable Support
Qualitative Quantitative indicators Date for Responsibility for Further
Seq. Related measure (reform Milestone /
Name indicators (for targets) completion reporting and specification (if Verification mechanism Milestone and target description
N’ or investment) Target
(for milestones) implementation necessary)
Unit Baseline Goal Quarter Year
Copy of the publication in the Entry into force of the Decree of the
Official Journal of the decree Minister of Health and Labour and
Entry into force of
of the Minister of Health and Health on the Service Organisation
the Decree of the
Labour on the Health Services Act which shall improve the
Minister of Health
Entry into force of Organisation Act amending the reimbursement system for doctors,
and Labour and
the Decree of the reimbursement system for nurses and pharmacists to incentivise
Health on the
6.1 A comprehensive Minister of Health doctors, nurses and the health workforce to work in remote
Service Ministry of Social
96 change in the organisation Milestone and Labour and Q1 2023 pharmacists and reference to areas.
Organisation Act Affairs
of health care in Estonia Health on the ihe relevant provisions
amending the
Service indicating the entry into force,
reimbursement
Organisation Act accompanied by a summary
system for doctors,
document duly justifying how
nurses and
the milestone (including all the
pharmacists
constitutive elements) was
satisfactorily fulfilled.
Summary document duly The admission of persons to nursing
justifying how the target training has been increased by 5%
Percentage (including all the constitutive compared to 2020.
increase in elements) was satisfactorily
6.1 A comprehensive the number fulfilled.
Admission to Ministry of Social
97 change in the organisation Target of persons 0 5 Q4 2023 This document shall include as
nursing training Affairs
of health care in Estonia admitted to an annex the (anonymised)
nursing annual admission rolls of
training nursing training providers for
the years 2020,2021,2022
and 2023.
Copy of the publication in the Entry into force of the Ministerial
Entry into force of Official Journal of the Regulation amending the agreement
the Ministerial Ministerial Regulation on between the Ministry of Social Affairs
Regulation Entry into force of amending the agreement and the University of Tartu which shall
amending the the Ministerial between the Ministry of Social lay down the requirements for the
agreement Regulation and Affairs and the University of gradual increase of admission in
6.1 A comprehensive
between the agreement Ministry of Social Tartu and reference to the certain professions with shortages, in
98 change in the organisation Milestone Q2 2026
Ministry of Social between the Affairs relevant provisions indicating particular general practitioners,
of health care in Estonia
Affairs and the Ministry of Social the entry into force, psychiatrists, internal diseases.
University of Tartu Affairs and the accompanied by a summary
on the shortage of University of Tartu document duly justifying how
doctors in certain the milestone (including all the
specialisations constitutive elements) was
satisfactorily fulfilled.
48
Non-Repayable Support
Qualitative Quantitative indicators Date for Responsibility for Further
Seq. Related measure (reform Milestone /
Name indicators (for targets) completion reporting and specification (if Verification mechanism Milestone and target description
№ or investment) Target
(for milestones) implementation necessary)
Unit Baseline Goal Quarter Year
Summary document duly The contracting authority, which is the
ustifying how the milestone owner of the hospital, shall sign the
(including all the constitutive contract for the design of the Northern
Signature of the
Ministry of Social elements) was satisfactorily Estonia Medical Campus. The contract
6.2 Establishment of the design contract of
Signature of the Affairs and the fulfilled. shall include the obtaining of the
99 Northern Estonia Medical Milestone the Northern Q4 2021
design contract government of This document shall include as necessary permits for the construction
Campus Estonia Medical
Tallinn city an annex a copy of the signed
Campus
contract for the design of the
Northern Estonia Medical
Campus.
Summary document duly The contracting authority, which is the
ustifying how the milestone owner of the hospital, shall sign
(including all the constitutive contracts for:
elements) was satisfactorily • the excavation works and the
Signature of the fulfilled. connections with water supply,
contracts for the This document shall include as wastewater collection infrastructure
excavation and for an annex a copy of the signed and electricity; and
the water supply Ministry of Social contracts for the excavation - the reinforced concrete structures.
6.2 Establishment of the
and electricity, and Signature of Affairs and the works and the connections
100 Northern Estonia Medical Milestone Q4 2023
for the reinforced contracts government of with water supply, wastewater
Campus
concrete structures Tallinn city collection infrastructure and
of the Northern electricity and the reinforced
Estonia Medical concrete structures including
Campus any annexes containing the
technical specifications of the
projects proving that it is in line
with the requirements of the
milestone.
Summary document duly The contracting authority, which is the
¡ustifying how the milestone owner of the hospital, shall sign a
(including all the constitutive contract for the construction of the
elements) was satisfactorily Northern Estonia Medical Campus,
Signature of the fulfilled. including the installation of the
Ministry of Social
6.2 Establishment of the contract for the This document shall include as technical building systems in particular
Signature of the Affairs and the
101 Northern Estonia Medical Milestone construction of the Q1 2024 an annex a copy of the signed the technical equipment for heating,
contract government of
Campus Northern Estonia contract for the construction of cooling, ventilation, hot water, lighting
Tallinn city
Medical Campus the Northern Estonia Medical and electricity production,
Campus works including any measurement, monitoring and control
annexes containing the systems and interior works.
technical specifications of the
projects proving that it is in line
49
Non-Repayable Support
Qualitative Quantitative indicators Date for Responsibility for Further
Seq. Related measure (reform Milestone /
Name indicators (for targets) completion reporting and specification (if Verification mechanism Milestone and target description
№ or investment) Target
(for milestones) implementation necessary)
Unit Baseline Goal Quarter Year
'with the requirements of the
milestone.
Summary document duly 10% of the construction contract
justifying how the milestone mentioned in milestone 101 has been
(including all the constitutive fulfilled when the builder has
elements) was satisfactorily confirmed the completion of 10% of
fulfilled. the construction work as defined in the
This document shall include as contract, the contracting authority has
Percentage an annex progress reports accepted the work and possible
of volume Ministry of Social signed by the contractor and deficiencies have been identified
6.2 Establishment of the 10% of the volume
of the Affairs and the the competent authority together with a deadline to resolve
102 Northern Estonia Medical Target of the construction 0 10 Q4 2024
constructie government of demonstrating that 10% of the them.
Campus contract is fulfilled
n contract Tallinn city construction works as defined
fulfilled in the contract have been
completed, possible
deficiencies have been
identified and a timeline to
resolve them has been agreed.
Based on the approved reports
the builder issues invoices.
Summary document duly 50% of the construction contract
ustifying how the milestone mentioned in milestone 101 has been
(including all the constitutive fulfilled when the builder has
elements) was satisfactorily confirmed the completion of 50% of
fulfilled. the construction work as defined in the
This document shall include as contract, the contracting authority has
Percentage an annex progress reports on accepted the work and possible
of volume Ministry of Social covered works signed by the deficiencies have been identified
6.2 Establishment of the 50% of the volume
of the Affairs and the contractor and the competent together with a deadline to resolve
103 Northern Estonia Medical Target of the construction 10 50 Q4 2025
constructio government of authority demonstrating that them.
Campus contract is fulfilled
n contract Tallinn city 50% of the construction works
fulfilled as defined in the contract have
been completed, possible
deficiencies have been
identified and a timeline to
resolve them has been agreed.
Based on the approved reports
the builder issues invoices.
50
Non-Repayable Support
Qualitative Quantitative indicators Date for Responsibility for Further
Seq. Related measure (reform Milestone /
Name indicators (for targets) completion reporting and specification (if Verification mechanism Milestone and target description
№ or investment) Target
(for milestones) implementation necessary)
Unit Baseline Goal Quarter Year
Summary document duly The contracting authority, which is the
justifying how the milestone owner of the hospital, shall sign a
(including all the constitutive contract for supplying the hospital with
elements) was satisfactorily all the equipment necessary to make
fulfilled. the hospital fully operational (such as
Signature of the This document shall include as hospitals beds, medical equipment)
contract for an annex a copy of the signed after the construction work has been
Ministry of Social
6.2 Establishment of the equipping the contract for supplying the completed.
Signature of the Affairs and the
104 Northern Estonia Medical Milestone Northern Estonia Q2 2025 Northern Estonia Medical
contract government of
Campus Medical Campus to Campus with all the equipment
Tallinn city
make it fully necessary to make the hospital
operational fully operational, including any
annexes containing the
technical specifications of the
projects proving that it is in line
with the requirements of the
milestone.
Summary document duly The contracting authority, which is the
justifying how the milestone owner of the hospital, shall receive a
(including all the constitutive certificate from the contractor attesting
elements) was satisfactorily the completion of the construction
fulfilled. works. The contracting authority shall
This document shall include as demonstrate that it has initiated the
an annex the following procedure for issuing a certificate that
documentary evidence: the building has been completed and
a) certificates of completion complies with the relevant regulations.
Certificate attesting Ministry of Social
6.2 Establishment of the signed by the contractor and
Completion of the the completion of Affairs and the
105 Northern Estonia Medical Milestone Q2 2026 the competent authority
construction works the construction government of
Campus demonstrating the completion
works Tallinn city
of the construction works as
defined in the milestone;
b) proof that the contracting
authority has initiated the
procedure for issuing a
certificate (building use permit)
that the building has been
completed and complies with
the relevant regulations.
51
Non-Repayable Support
Qualitative Quantitative indicators Date for Responsibility for Further
Seq. Related measure (reform Milestone /
Name indicators (for targets) completion reporting and specification (if Verification mechanism Milestone and target description
№ or investment) Target
(for milestones) implementation necessary)
Unit Baseline Goal Quarter Year
Copy of the publication in the Entry into force of legislative
Official Journal of the Decree amendments which shall improve the
Entry into force of
of the Government on access to specialised care by
the Decree of the
amending the list of health extending the use of e-consultation in
Government,
care services of the Estonian primary care allowing patients to be
which amends the Entry into force of
Health Insurance Fund and advised by a specialist without having
list of health care legislative
6.3 Strengthening primary Ministry of Social reference to the relevant to consult them face-to-face.
106 Milestone services of the amendments to the Q3 2020
health care Affairs provisions indicating the entry
Estonian Health Decree of the
into force, accompanied by a
Insurance Fund on Government
summary document duly
access to
justifying how the milestone
specialised
(including all the constitutive
medical care
elements) was satisfactorily
fulfilled.
Copy of the publication in the Legislative amendments shall enter
Entry into force of
Official Journal of the Decree into force providing for the financing of
amendments to the
of the Government amending fixed costs and services for general
Decree of the
the list of health care services practitioners in order to increase the
Government which
Entry into force of of the Estonian Health allocation of resources to primary
amends the list of
the legislative Insurance Fund and reference medical practice outside metropolitan
6.3 Strengthening primary health care Ministry of Social
107 Milestone amendments to the Q1 2021 to the relevant provisions areas, especially in remote areas, and
health care services of the Affairs
Decree of the indicating the entry into force, to increase patients’ access to
Estonian Health
Government accompanied by a summary diagnostic and screening services.
Insurance Fund on
document duly justifying how
costs and services
the milestone (including all the
of general
constitutive elements) was
practitioners
satisfactorily fulfilled.
Copy of the publication in the Entry into force of the amendments to
Official Journal of the Health Services Organisation Act
legislation on amendments to which shall amend the management of
the Health Services Ihe list of patients, ensure continuity of
Organisation Act and primary care and extend the rights of
Entry into force of Provision in the
reference to the relevant nurses to prescribe medicines to
6.3 Strengthening primary amendments to the law indicating the Ministry of Social
108 Milestone Q1 2023 provisions indicating the entry patients.
health care Health Services entry into force of Affairs
into force, accompanied by a
Organisation Act the law
summary document duly
justifying how the milestone
(including all the constitutive
elements) was satisfactorily
fulfilled.
52
Non-Repayable Support
Qualitative Quantitative indicators Date for Responsibility for Further
Seq. Related measure (reform Milestone /
Name indicators (for targets) completion reporting and specification (if Verification mechanism Milestone and target description
№ or investment) Target
(for milestones) implementation necessary)
Unit Baseline Goal Quarter Year
Summary document duly Approval of the proposal on the
Approval of the ustifying how the milestone Governance Framework and
proposal on the (including all the constitutive implementation roadmap which shall
eHealth elements) was satisfactorily update the governance framework for
Approval of the
Governance fulfilled. eHealth and the coordination of the
eHealth
Framework and This document shall include as development of eHealth services.
6.4 Renewal of the Governance Ministry of Social
109 Milestone implementation Q2 2023 an annex the copy of the
eHealth Governance Framework and its Affairs
roadmap by the adopted eHealth Governance
implementation
Steering Framework and its
roadmap
Committee of the implementation roadmap and a
“Eesti tervise IKT ink to the website where the
¡ühtimise raamistik" Framework and the roadmap
can be accessed.
Summary document duly Contracts signed by the Estonian
ustifying how the milestone Police and Border Guard Board on the
¡including all the constitutive purchase of medical emergency
elements) was satisfactorily helicopters and on building the
fulfilled. airbases and landing sites for the
This document shall include as helicopter service of an ambulance.
an annex the following For the purchase of the special
documentary evidence: purpose helicopters, the best
a) signed contract for the technology that allows compliance
Award of contracts purchase of multifunctional with the ‘Do no significant harm'
6.5 Capacity building for Award of the public
for multifunctional Police and Border medical helicopters; Technical Guidance (2021 /С58/01 )
110 multipurpose medical Milestone procurement Q4 2023
medical helicopter Guard Board a) signed contracts for the shall be sought.
helicopters contracts
capabilities construction of airbases and
landing sites for multi-purpose
medical helicopters;
c) extract of the official
documents containing the
selection criteria that ensure
compliance with the 'Do no
significant harm' Technical
Guidance (2021/C58/01), as
specified in the CID Annex.
Summary document duly Delivery of two helicopters accepted
ustifying how the target by the Estonian Police and Border
6.5 Capacity building for (including all the constitutive Guard Board
Reception of Number of Police and Border
111 multipurpose medical Target 0 2 Q1 2025 elements) was satisfactorily
helicopters helicopters Guard Board
helicopters fulfilled.
This document shall include as
an annex the certificates of
53
Non-Repayable Support
Qualitative Quantitative indicators Date for Responsibility for Further
Seq. Related measure (reform Milestone /
Name indicators (for targets) completion reporting and specification (if Verification mechanism Milestone and target description
№ or investment) Target
(for milestones) implementation necessary)
Unit Baseline Goal Quarter Year
delivery signed by the
contractor and the competent
authority demonstrating that
the helicopters have been
received, are operational and
are in line with the
requirements of the target.
Summary document duly Two helicopter airbases/landing sites
ustifying how the milestone shall be constructed/expanded and
(including all the constitutive shall be ready for use, as evidenced
elements) was satisfactorily by formal acceptance of contract
fulfilled. This document shall fulfilment by the Estonian Police and
include as an annex the Border Guard Board.
6.5 Capacity building for Completion of Number of
Police and Border certificates of completion
112 multipurpose medical Target airbases built or helicopters 0 2 Q2 2026
Guard Board signed by the contractor and
helicopters expanded bases
the competent authority
demonstrating that the
airbases have been
completed, are operational and
are in line with the
requirements of the target.
Link to the website where the Entry into force of the Decree of the
legislation of strengthening the Minister of Health and Labour which
‘My First Job" scheme can be shall define the characteristics of the
Entry into force of
accessed and reference to the scheme and the conditions for its
6.6 Providing labour the Decree of the Entry into force of
relevant provisions indicating implementation, including financing
market measures to Minister of Health the Decree of the Ministry of Social
113 Milestone Q1 2022 the entry into force, and target group. The aim of the
reduce youth and Labour to Minister of Health Affairs
accompanied by a summary scheme shall be to enable young
unemployment strengthen the “My and Labour
document duly justifying how people without work experience or
First Job" scheme
the milestone (including all the with little work experience to gain work
constitutive elements) was experience and to improve their skills
satisfactorily fulfilled. to participate in the labour market.
Summary document duly The Government shall adopt an
justifying how the milestone amended Youth Guarantee Action
(including all the constitutive Plan to support youth employment.
Adoption of the
6.6 Providing labour elements) was satisfactorily This action plan shall
reinforced Youth
market measures to Youth Guarantee Ministry of Social fulfilled. ■ include measures to improve the
114 Milestone Guarantee Action Q2 2022
reduce youth Action Plan Affairs This document shall indude as skills of young people,
Plan by the
unemployment an annex the copy of the ■ define actions to prevent and
Government
adopted Youth Guarantee address youth unemployment,
Action Plan and a link to the including outreach and preventton of
NEET-situation
54
Non-Repayable Support
Qualitative Quantitative indicators Date for Responsibility for Further
Seq. Related measure (reform Milestone /
Name indicators (for targets) completion reporting and specification (if Verification mechanism Milestone and target description
№ or investment) Target
(for milestones) implementation necessary)
Unit Baseline Goal Quarter Year
website where the acton plan ■define key parties and their roles of
can be accessed. preventing and dealing with youth
unemployment
Summary document duly At least 3 178 young people aged 16-
justifying how the target 29 have participated in the “My First
(including all the constitutive Job" scheme (cumulative number of
elements) was satisfactorily entrants).
fulfilled.
This document shall include as
an annex the following
documentary evidence:
a) an extract of the register
containing the identification
Number of young number of the individual
6.6 Providing labour
people contracts signed between the
market measures to Number of Unemployment
115 Target participating in the 0 3178 Q4 2025 Unemployment Insurance
reduce youth participants Insurance Fund
“My First Job" Fund and the employer
unemployment
scheme proving alignment with the
description of the target in the
CID annex;
b) an extract of the register
containing the individual
training reimbursement
decisions by the
Unemployment Insurance
Fund;
c) summary of the training,
including its content.
Alongside the Copy of the publication in the Entry into force of the amendments to
NAIRU/NAWRU, Official Journal of the the Act which shall lay down a
other reference legislation on the amendments permanent mechanism to activate the
Entry into force of
unemployment to the Unemployment Services extension of the duration of
the amendments to
rates (such as and Benefits Act and the unemployment insurance benefits by
6.7 Extending the duration the Unemployment Entry into force of
Ministry of Social multi-year moving Unemployment Insurance Act 60 days, notably when the registered
116 of unemployment Milestone Services and the legislative Q2 2023
Affairs averages) may and reference to the relevant unemployment rate exceeds the non
insurance benefits Benefits Act and amendments
also be used as provisions indicating the entry accelerating inflation/wage rate of
the Unemployment
benchmarks for into force, accompanied by a unemployment by a significant margin.
Insurance Act
activating the summary document duly The mechanism of prolongation and
extension, based justifying how the milestone the margin, which shall not be higher
on the result of (including all the constitutive
55
Non-Repayable Support
Qualitative Quantitative indicators Date for Responsibility for Further
Seq. Related measure (reform Milestone /
Name indicators (for targets) completion reporting and specification (if Verification mechanism Milestone and target description
№ or investment) Target
(for milestones) implementation necessary)
Unit Baseline Goal Quarter Year
the consultation elements) was satisfactorily than 2%, shall be agreed upon in
with social fulfilled. dialogue with the social partners.
partners as
reported under
interim step 116.1
in Annex II.
Copy of the publication in the Entry into force of legislative
Official Journal of the amendments to the Social Welfare Act
legislation on the amendments which shall lay down the concept of
to the Social Welfare Act and long-term care and require local
reference to the relevant authorities to take into account the
Entry into force of Entry into force of
Ministry of Social provisions indicating the entry principle that a person must be able to
117 6.8 Long-term care Milestone amendments to the legislative Q2 2022
Affairs into force, accompanied by a live as long as possible in his or her
Social Welfare Act amendments
summary document duly home, in his or her usual environment,
ustifying how the milestone with sufficient quality services
(including all the constitutive available.
elements) was satisfactorily
fulfilled.
Summary document duly The Ministry of Social Affairs shall
ustifying how the milestone adopt an Action Plan that provides for
(including all the constitutive the establishment of an integrated
elements) was satisfactorily care model throughout Estonia and
Action Plan on an fulfilled. the roles and responsibilities of the
Adoption of the Ministry of Social
118 6.8 Long-term care Milestone integrated care Q4 2022 This document shall include as actors involved in the future financing
Action Plan Affairs
model an annex the copy of the model of the system.
adopted Action Plan on an
integrated care model and a
link to the website where the
action plan can be accessed.
56
Non-Repayable Support
Qualitative Quantitative indicators Date for Responsibility for Further
Seq. Related measure {reform Milestone/
Name indicators (for targets) completion reporting and specification (if Verification mechanism Milestone and target description
№ or investment) Target
(for milestones) implementation necessary)
Unit Baseline Goal Quarter Year
Copy of the publication in the The Decree of the Minister of Social
Official Journal of the Decree Protection shall define the design and
of the Minister of Social characteristics of services by local
Protection on the design, authorities to people with lower care
characteristics and conditions needs, as well as the conditions of
for the local authorities on how their implementation. In particular, it
Entry into force of Entry into force of to provide independent living shall include Investments and
the decree of the the decree of the Ministry of Social for elderly in supported living development of services by local
119 6.8 Long-term care Milestone Q4 2024
Minister of Social Minister of Social Affairs service and reference to the authorities to provide for independent
Protection Protection relevant provisions indicating iving for older people with lower care
the entry into force, needs and people with disabilities to
accompanied by a summary support independent living.
document duly justifying how
the milestone (including all the
constitutive elements) was
satisfactorily fulfilled.
Copy of the publication in the Entry into force of legislative
Official Journal of the Social amendments which shall provide for
Welfare Act on amendments of the modernisation and integration of
the support system for children services for children with higher care
with higher care needs and needs. In particular,
Entry into force of
reference to the relevant ■ services in the health, education,
the legislative
Entry into force of provisions indicating the entry social protection and employment
amendments of the Ministry of Social
120 6.8 Long-term care Milestone the legislative Q1 2025 into force, accompanied by a areas shall be integrated in order to
support system for Affairs
amendments summary document duly provide comprehensive support for
children with high
justifying how the milestone families under care burden, and
care needs
(including all the constitutive ■ the current support system shall be
elements) was satisfactorily simplified and the assessment of care
fulfilled. needs consolidated so that parents
have a secure point of contact for
nitial advice and support
Summary document duly The Plan shall outline the measures to
justifying how the milestone reduce the gender pay gap.
(including all the constitutive
Adoption of the
elements) was satisfactorily
Welfare Adoption of the
6.9 Reducing gender pay Ministry of Social fulfilled.
121 Milestone Development Plan Welfare Q1 2024
gap Affairs This document shall include as
2023-2030 by the Development Plan
an annex the copy of the
government
adopted Welfare Development
Plan 2023-2030 and a link to
the website where the
57
Non-Repayable Support
Qualitative Quantitative indicators Date for Responsibility for Further
Seq. Related measure (reform Milestone /
Name indicators (for targets) completion reporting and specification (if Verification mechanism Milestone and target description
№ or investment) Target
(for milestones) implementation necessary)
Unit Baseline Goal Quarter Year
Development Plan can be
accessed.
Summary document duly A prototype of a gender pay gap tool
ustifying how the milestone for employers shall be developed with
(including all the constitutive the aim of providing them with data
elements) was satisfactorily and information concerning the gender
fulfilled. pay gap and its possible reasons in
Developing a
This document shall include a their organisations and thereby
6.9 Reducing gender pay Digital gender pay prototype of a Ministry of Social
122 Milestone Q4 2022 confinnation by the Ministry of supporting making informed decisions
gap gap tool gender pay gap Affairs
Social Affairs that the and taking effective action in orderte
tool
prototype of a digital gender implement the principle of equal pay
pay gap tool has been and to reduce the gender pay gap.
developed and is in line with
the requirements of the
milestone.
Summary document duly The digital gender pay gap tool shall
justifying how the milestone be available to employers with the aim
(including all the constitutive of providing them with data and
elements) was satisfactorily nformation concerning the gender pay
fulfilled. gap and its possible reasons in their
Roll-out of a digital This document shall include a organisations and thereby supporting
6.9 Reducing gender pay Digital gender pay Ministry of Social
123 Milestone gender pay gap Q1 2024 confirmation by the Ministry of making informed decisions and taking
gap gap tool Affairs
tool Sodai Affairs that the digital effective action in orderte implement
gender pay gap tool is the principle of equal pay and to
operational and has been reduce the gender pay gap.
made available to employers
and is in line with the
requirements of the milestone.
Copy of the publication in the Entry into force of the regulation
Entry into force of Official Journal of the establishing the legal framework for
the Government regulation establishing the the implementation and monitoring of
Regulation on the legal framework for the the recovery and resilience plan of
legal framework for Entry into force of implementation and monitoring Estonia before the first payment
124 Milestone the implementation government Q4 2021 of the RRP and reference to request is made. The regulation shall
and monitoring of regulation the relevant provisions at least define the authorities involved
the recovery and indicating the entry into force, in the implementation of the recovery
resilience plan of accompanied by a summary and resilience plan of Estonia and
Estonia. document duly justifying how their tasks including the tasks of the
the milestone (including all the Ministry of Finance, the sectoral
58
Non-Repayabfe Support
Qualitative Quantitative indicators Date for Responsibility for Further
Seq. Related measure (reform Milestone /
Name indicators (for targets) completion reporting and specification (if Verification mechanism Milestone and target description
№ or investment) Target
(for milestones) implementation necessary)
Unit Baseline Goal Quarter Year
constitutive elements) was ministries and the State Shared
satisfactorily fulfilled. Service Center.
59
Annex II
Arrangements and Timetable for Monitoring
# Related measure M/T Name Qualitative indicators Quantitative indicators Date for completion
(reform or investment) (for milestones) (for targets)
Unit Baseline Goal Q Year
1 1.1. Digital transformation in Μ Call for proposals with award criteria and Publication of the notice of the call for Q2 2022
enterprises award conditions proposals
2 1.1. Digital transformation in T Award of grants Number of enterprises being 0 110 Q4 2023
enterprises awarded a grant
3.1 1.1. Interim step Award of grants Number of enterprises being 0 180 Q4 2024
awarded a grant
3 1.1. Digital transformation in T Award of grants Number of enterprises being 110 230 Q4 2025
enterprises awarded a grant
4 1.2. Development of e-construction Μ Adoption of international standards and best Adoption of international standards and Q4 2024
practices for the use of digital technologies in best practices
construction
5 1.2. Development of e-construction Μ Availability of public services on the e- Entry into service of interfaces between the Q4 2025
construction platform e-construction platform and the related
public services
6.1 1.2 Interim step Launch of development and prototyping Number of projects launched 0 40 Q4 2023
projects
6 1.2. Development of e-construction T Completion of development and prototyping Number of projects completed 0 120 Q4 2025
projects
7 1.3. Development of digital waybills T eFTI (electronic Freight Transport Information) Number of projects launched 0 5 Q2 2023
services platforms development
8 1.3. Development of digital waybills T eCMR (electronic Consignment Note) interface Number of projects launched 0 270 Q4 2024
services developments
60
# Related measure M/T Name Qualitative indicators Quantitative indicators Date for completion
(reform or investment) (for milestones) (for targets)
Unit Baseline Goal Q Year
9 1.3. Development of digital waybills T Total number of projects completed Number of projects completed 0 275 Q4 2025
services
10 1.3. Development of digital waybills Μ Ex-post evaluation of the development and Adoption of ex-post evaluation report by Q2 2026
services deployment of the digital waybills the Ministry of Economic Affairs and
Communications
11 1.4. Skills reform for the digital Μ Entry into force of secondary legislation setting Entry into force of secondary legislation Q2 2022
transformation of businesses out the terms of support for the development of
digital skills
12 1.4. Skills reform for the digital T Enrolment in training activities Number of participants 0 500 Q4 2023
transformation of businesses
13.1 1.4. Interim step Completion of training activities Number of participants who 0 1000 Q2 2025
shall have completed their
training.
13 1.4. Skills reform for the digital T Completion of training activities Number of participants 0 2000 Q2 2026
transformation of businesses
14 1.4. Skills reform for the digital T Number of new upskilling and retraining Number of curricula registered 0 5 Q4 2023
transformation of businesses modules in Estonia’s Education
Information System (EHIS).
15 1.4. Skills reform for the digital T Review of qualification standards for ICT Number of qualification 0 5 Q4 2024
transformation of businesses specialists. standards analysed and
adapted as and if needed
16 1.5.1. Supporting the Μ Preparation of the development of strategies Completion of preparatory tasks Q2 2022
competitiveness of enterprises in
foreign markets - Country and
regional strategies
17.1 1.5.1 Interim step Launch of procurement Publication of the call fortenders, including Q3 2023
a specification of the value added
expected from each study and of how the
pro-active smart advice referred to in
Target 18 will be achieved.
61
# Related measure M/T Name Qualitative indicators Quantitative indicators Date for completion
(reform or investment) (for milestones) (for targets)
Unit Baseline Goal Q Year
17 1.5.1. Supporting the Μ Procurement of studies Signature of contracts Q2 2024
competitiveness of enterprises in
foreign markets - Country and
regional strategies
18 1.5.1. Supporting the T Number of country and regional export Number of strategies 0 13 Q2 2026
competitiveness of enterprises in strategies published
foreign markets - Country and
regional strategies
19 1.5.2. Supporting the Μ Preparatory analysis to define the content and Delivery of a preparatory analysis Q2 2022
competitiveness of enterprises in the locations of business centres
foreign markets - Innovative
business centres in key export
markets
20.1 1.5.2. Interim step Number of business centres opened Number of business centres 0 4 Q3 2025
which shall have opened
20 1.5.2. Supporting the T Number of business centres opened Number of business centres 0 7 Q2 2026
competitiveness of enterprises in
foreign markets - Innovative
business centres in key export
markets
21 1.5.3. Supporting the Μ Setting-up of impact groups and selection of Decisions on the composition of the impact Q2 2022
competitiveness of enterprises in destinations for global digital missions groups and the destinations of the global
foreign markets - Global e-export digital missions
impact groups and virtual stages
22.1 1.5.3. Interim step Number of expert contracts signed for the Number of contracts signed 0 7 Q2 2024
impact groups/global missions
22 1.5.3. Supporting the T Number of missions carried out by the global Total of number of missions 0 29 Q2 2026
competitiveness of enterprises in impact groups and number of major events in and events carried out
foreign markets - Global e-export which Estonia was represented through ‘virtual
impact groups and virtual stages stages’
62
# Related measure M/T Name Qualitative indicators Quantitative indicators Date for completion
(reform or investment) (for milestones) (for targets)
Unit Baseline Goal Q Year
23 2.1. Green transition of enterprises Μ Creation of a Green Transition Task Force to Set up of a task force and working groups Q4 2021
implement and monitor the green transition
23.1 2.1. Ex-post monitoring Activity report Submission of an activity report on the Q2 2023
outputs and results of the Task Force
23.2 2.1. Ex-post monitoring Activity report Submission of an activity report on the Q2 2025
outputs and results of the Task Force
24 2.1. Green transition of enterprises Μ Adoption of the Circular Economy Action Plan Circular Economy Action Plan adopted Q4 2022
by the Green Transition Task Force
24.1 2.1. Ex-post monitoring Implementation report Submission of a report on the Q2 2025
implementation of the Circular Economy
Action Plan
25 2.2. Green skills to support the Μ Entry into force of secondary legislation setting Entry into force of secondary legislation Q2 2022
green transition of enterprises out the terms of support for the development of
green skills
26 2.2. Green skills to support the T Number of upskilling and retraining modules Number of modules 0 5 Q4 2023
green transition of enterprises
27.1 2.2. Interim step People taking part in upskilling and retraining Number of participants 0 1400 Q2 2025
programmes
27 2.2. Green skills to support the T People taking part in upskilling and retraining Number of participants 0 2830 Q2 2026
green transition of enterprises programmes
28 2.3. Green technology development Μ Establishment of a working group to plan and Recruitment of a project manager and set Q4 2021
programmes set up the development programme up of a working group
28.1 2.3. Ex-post monitoring Number of stock-taking meetings undertaken Number of stock-taking 0 3 Q4 2022
by the working group, with appropriate activity meetings
reports, which shall notably justify the actions
selected to be supported
63
# Related measure M/T Name Qualitative indicators Quantitative indicators Date for completion
(reform or investment) (for milestones) (for targets)
Unit Baseline Goal Q Year
29 2.3. Green technology development Μ Set up of the Green Technologies Contracts signed for all development Q2 2024
programmes Development Programme clusters and support measures designed
and opened
30.1 2.3. Interim step Number of clusters supported through the Number of clusters 0 3 Q4 2024
Green Technology Development Programme
30 2.3. Green technology development T Number of clusters supported through the Number of clusters 0 5 Q2 2026
programmes Green Technology Development Programme
31.1 2.3. Interim step Number of start-ups supported through the Number of start-ups 0 4 Q4 2024
Green Technology Development Programme
31 2.3. Green technology development T Number of start-ups supported through the Number of start-ups 0 10 Q2 2026
programmes Green Technology Development Programme
and which have received private investment
32 2.4. Modernisation of the business Μ Entry into force of the ministerial decree setting Entry into force of the ministerial decree Q2 2022
models in manufacturing companies out the terms and conditions of grant eligibility
33.1 2.4. Interim step Number of projects supported Number of projects 0 20 Q2 2023
33 2.4. Modernisation of the business T Number of projects supported Number of projects 0 70 Q4 2025
models in manufacturing companies
34 2.5. Deployment of resource- Μ Publication of call for proposals for grants Publication of the notice for calls for Q2 2022
efficient green technologies proposals for grants
35 2.5. Deployment of resource T Number of contracts awarded following the call Contracts awarded 0 25 Q4 2023
efficient green technologies for proposals
36 2.5. Deployment of resource- T Number of projects completed Number of projects 0 25 Q2 2026
efficient green technologies
37 2.6. Green Fund Μ Signature of contractual agreement between Signature of contractual agreement Q4 2021
the Ministry of Economic Affairs and
Communications and SmartCap
64
# Related measure M/T Name Qualitative indicators Quantitative indicators Date for completion
(reform or investment) (for milestones) (for targets)
Unit Baseline Goal Q Year
38 2.6. Green Fund Μ Adoption of the investment policy document by Investment policy document adopted by Q4 2021
SmartCap SmartCap
39.1 2.6. Interim step Establishment of clear climate selection criteria Selection criteria that ensure that selected Q4 2022
for the Green Fund projects either lower GHG emissions,
improve adaptation to climate change or
aim to promote other environmental
objectives provided in Article 9 of the
Taxonomy Regulation
39.2 2.6. Interim step Volume of investments in venture capital funds Volume of invested capital (in 0 30000000 Q4 2023
or equity investments in enterprises EUR)
39 2.6. Green Fund T Volume of investments in venture capital funds Volume of invested capital (in 0 60000000 Q4 2024
or equity investments in enterprises EUR)
40 2.6. Green Fund T Volume of investments in venture capital funds Volume of invested capital (in 60000000 100000000 Q2 2026
or equity investments in enterprises EUR)
41 2.7. Creating opportunities for the Μ Entry into force of the ministerial decree setting Entry into force of the ministerial decree Q4 2022
uptake of renewables-based green out the terms and conditions for granting
hydrogen technologies support
42 2.7. Creating opportunities for the Μ Technologies and equipment to create Procurement, installation and start of Q1 2025
uptake of renewables-based green complete green hydrogen value chains operation of technologies and equipment
hydrogen technologies
43 2.7. Creating opportunities for the T Grants allocated to renewables-based green EUR 0 49490000 Q2 2026
uptake of renewables-based green hydrogen technologies representing at least
hydrogen technologies EUR 49.49 million
44 3.1. Creation and development of a Μ Setting up a data management team in the Establishment of the necessary Q4 2021
centre of excellence for data Statistical Office, the Ministry of Economic organisational structure for coordinating
governance and open data Affairs and Communications and the State data management
Information System Authority
45 3.1. Creation and development of a T Completion of data quality improvement Number of projects 0 430 Q2 2025
centre of excellence for data projects
governance and open data
65
# Related measure M/T Name Qualitative indicators Quantitative indicators Date for completion
(reform or investment) (for milestones) (for targets)
Unit Baseline Goal Q Year
46 3.1. Creation and development of a T Publication of datasets on the national open Number of published datasets 707 2600 Q4 2025
centre of excellence for data data portal
governance and open data
47 3.2. Development of event services T Launch of personal life event services and/or Number of services which are 0 2 Q4 2022
and proactive digital public services pro-active services operational
for individuals
48 3.2. Development of event services T Launch of personal event services and pro Number of services which are 2 10 Q4 2025
and proactive digital public services active services operational
for individuals
49 3.3. Development of event services T Deployment of IT developments contributing to Number of projects that have 0 1 Q4 2022
and digital gateway for the implementation of the business event successfully deployed new
entrepreneurs services and gateway developments online
50.1 3.3. Interim step Deployment of IT developments contributing to Number of projects that have 1 5 Q2 2024
the implementation of the business event successfully deployed new
services and gateway developments online
50 3.3. Development of event services T Deployment of IT developments contributing to Number of projects that have 1 10 Q4 2025
and digital gateway for the implementation of the business event successfully deployed new
entrepreneurs services and gateway developments online
51 3.4. #Biirokratt programme (national T Access to digital public services through the Number of public digital 0 1 Q2 2022
virtual assistant platform and virtual assistant platform services accessible through
ecosystem) the virtual assistant
52 3.4. #Bürokratt programme (national T Introduction of the Bürokraft virtual assistant in Number of service 0 18 Q4 2025
virtual assistant platform and digital public services environments environments
ecosystem)
53 3.4. #Bürokratt programme (national T Access to digital public services through the Number of public digital 1 20 Q4 2025
virtual assistant platform and virtual assistant platform services accessible through
ecosystem) the virtual assistant
54 3.5. Reconfiguration of basic digital Μ Development of centrally delivered/shared IT Opening of shared server hosting and Q3 2022
services and safe transition to cloud base services computer workstation services to public
infrastructure authorities
66
# Related measure M/T Name Qualitative indicators Quantitative indicators Date for completion
(reform or investment) (for milestones) (for targets)
Unit Baseline Goal Q Year
55 3.5. Reconfiguration of basic digital T Deployment of national private cloud Number of information 0 10 Q4 2023
services and safe transition to cloud infrastructure by public authorities systems migrated to the
infrastructure national private cloud
56 3.5. Reconfiguration of basic digital Μ Extension of the cloud infrastructure to the Completion of the extension of the national Q4 2023
services and safe transition to cloud data embassy private cloud to the infrastructure of
infrastructure Estonia's data embassy
57 3.5. Reconfiguration of basic digital T Migration of critical systems to the national Number of critical systems 0 10 Q4 2024
services and safe transition to cloud cloud infrastructure of the data embassy
infrastructure
58 3.5. Reconfiguration of basic digital T Central security testing of public authorities’ Number of tests performed 0 16 Q4 2024
services and safe transition to cloud information systems
infrastructure
59.1 3.6. Interim step Drafts of the amendment of the Money Submission to the Commission of draft Q3 2024
Laundering and Terrorist Financing Prevention laws with an explanatory document
Act and of other legislative, administrative and
contractual changes needed for the Centre for
Strategic Analysis
59 3.6. Establishing the strategic Μ Entry into force of the amendment of the Provision in the law indicating the date of Q4 2024
analysis of money laundering and Money Laundering and Terrorist Financing entry into force of amended act and entry
terrorist financing in Estonia Prevention Act and of other legislative, into force of other legislative,
administrative and contractual changes administrative and contractual acts
needed for the Centre for Strategic Analysis
60.1 3.7 Interim step Progress report Submission to the Commission of a Q2 2025
progress report concerning the
development of the new ICT system for the
Centre for Strategic Analysis
60 3.7. Information system for real-time Μ Development of the new real-time ICT analysis Delivery of the new ICT system to the Q2 2026
strategic analysis of money system for the Centre for Strategic Analysis, Financial Intelligence Unit
laundering and terrorist financing and delivery to the Financial Intelligence Unit
61 3.8. Construction of very high T Rollout of very high capacity broadband Number of sites 0 4000 Q4 2023
capacity broadband networks network to new sites
67
# Related measure M/T Name Qualitative indicators Quantitative indicators Date for completion
(reform or investment) (for milestones) (for targets)
Unit Baseline Goal Q Year
62.1 3.8. Interim step Rollout of very high capacity broadband Number of sites 4000 6000 Q4 2024
network to new sites
62 3.8. Construction of very high T Rollout of very high capacity broadband Number of sites 4000 8097 Q4 2025
capacity broadband networks network to new sites
63 4.1. Energy efficiency promotion Μ Conclusion of the cooperation agreement Conclusion of the cooperation agreement Q4 2022
stipulating conditions for cooperation between between SA KredEx/ Enterpise Estonia
SA Kredex/Enterprise Estonia and county and county development centers
development centers
64 4.1. Energy efficiency promotion Μ Digital tools to facilitate access to information Operational user-friendly renovation Q4 2024
on renovation including visualising the results website and pricing models
of the renovation and estimating the cost of
renovation have become operational
65 4.2. Support for the renovation of Μ Publication of calls for applications for Publication of calls for housing renovation Q2 2022
apartment buildings residential apartment buildings renovation grants
grants
66.1 4.2 Interim step Grants awarded for renovation of apartment Number of dwellings for which 0 2600 Q4 2022
buildings a final grant decision has been
awarded
66 4.2. Support for the renovation of T Dwellings with improved energy performance Number of dwellings 0 2600 Q4 2024
apartment buildings
67 4.2. Support for the renovation of T Estimated annual reduction of greenhouse gas N/A Ions of CO2eq/year 0 2200 Q2 2026
apartment buildings emissions
68 4.3. Support for the renovation of Μ Published calls for renovation grant Publication of calls Q2 2022
small residential buildings
69.1 4.3. Interim step Grants awarded for renovation of small Number of dwellings for which 0 80 Q4 2022
residential buildings a final grant decision has been
awarded
69 4.3. Support for the renovation of T Dwellings with improved energy performance Number of dwellings 0 80 Q4 2024
small residential buildings
68
# Related measure M/T Name Qualitative indicators Quantitative indicators Date for completion
(reform or investment) (for milestones) (for targets)
Unit Baseline Goal Q Year
70 4.4. Boosting the green transition in Μ Government decision on investments needed Adoption of the decision of the Q2 2021
the energy economy to alleviate the defence related height Government
restrictions on wind parks
70.1 4.4. Ex-post monitoring Investments carried out, height restrictions on Submission to the Commission of Q1 2026
wind parks alleviated in accordance with the information on alleviation of defence
government decisions related height restrictions on wind parks
71 4.4. Boosting the green transition in Μ Adoption of the decision of the Government on Adoption of the decision of the Q4 2021
the energy economy the initiation of the preparation process of the Government
National Development Plan of the Energy
Sector, the designation of those responsible
and deadlines
72.1 4.4. Interim step Results of the assessment Submission to the Commission of the Q2 2023
results of the assessment describing the
current situation and identifying the
changes needed (in the legislation and/or
preparation of relevant guidance materials)
to alleviate the barriers for the installation
of renewable energy generating
installations and energy storage facilities
72 4.4. Boosting the green transition in Μ Entry into force of the relevant primary and/or Provision in the law indicating the entry Q4 2024
the energy economy secondary legislation and publication of into force of the relevant primary and/or
guidance material to alleviate the barriers for entry into force of secondary legislation
the installation of renewable energy generating and publication of guidance material
installations and energy storage facilities
73.1 4.4. Interim step Draft Development Plan of the Energy Sector Submission to the Commission of the draft Q4 2024
Development Plan of the Energy Sector
73 4.4. Boosting the green transition in Μ Adoption of the National Development Plan of Document adopted by the Government Q4 2025
the energy economy the Energy Sector by the Government
73.1 4.4. Ex-post monitoring Progress report Submission to the Commission of a Q4 2026
progress report describing the current
situation on the implementation of the
69
# Related measure M/T Name Qualitative indicators Quantitative indicators Date for completion
(reform or investment) (for milestones) (for targets)
Unit Baseline Goal Q Year
National Development Plan of the Energy
Sector
74 4.5. Programme to strengthen the Μ Signature of network investment co-financing Signature of a contract with the Q1 2022
electricity grid to increase contract with transmission system operator transmission system operator
renewable energy production
capacity and adapt to climate
change (such as protection against
storms)
74.1 4.5. Interim step Progress report Submission to the Commission of a Q1 2025
progress report describing the works
carried out by the transmission system
operator
75 4.5. Programme to strengthen the T Additional renewable energy connection Additional connection capacity 0 310 Q2 2026
electricity grid to increase capacity created via investments into the (MW)
renewable energy production transmission network
capacity and adapt to climate
change (such as protection against
storms)
76 4.6. Programme to boost energy Μ Publication of a call for proposals for projects Call for proposals published Q4 2022
production in industrial areas boosting energy production in industrial sites
76.1 4.6.Interim step Completion of selection of projects Submission to the Commission of the list Q2 2024
and description of projects (inclunding MW
to be added to the grid)
77 4.6. Programme to boost energy T Additional connection capacity for renewable Connection capacity created 0 28 Q2 2026
production in industrial areas electricity production in or near industrial sites (MW)
connected to the grid
78 4.7. Pilot Energy Storage Μ Publication of a call for proposals for a pilot Call for proposals published Q4 2022
Programme energy storage programme
78.1 4.7. Interim step Completion of selection of projects Submission to the Commission of the list Q2 2024
and description of projects (solutions)
selected for a grant
70
# Related measure M/T Name Qualitative indicators Quantitative indicators Date for completion
(reform or investment) (for milestones) (for targets)
Unit Baseline Goal Q Year
79 4.7. Pilot Energy Storage T Additional heat storage capacity resulting from Capacity installed (m3) 0 35000 Q2 2026
Programme investment support
80 4.7. Pilot Energy Storage T Additional electricity storage capacity resulting Capacity installed (MW) 0 4 Q2 2026
Programme from investment support
81 5.1. Deploy safe, green, Μ Adoption of the Transport and Mobility Adoption of the Transport and Mobility Q1 2022
competitive, needs-based and Development Plan 2021-2035 by the Development Plan 2021-2035
sustainable transport and energy Government
infrastructure
82 5.1. Deploy safe, green, Μ Adoption of the Implementation Plan for green Adoption of the Implementation Plan Q4 2022
competitive, needs-based and sustainable public transport development of
sustainable transport and energy the Transport and Mobility Development Plan
infrastructure 2021-2035
83.1 5.1 Interim step Annual report on progress with the Progress report submitted to the Q2 2023
implementation plan for green sustainable Commission
public transport development
83.2 5.1 Interim step Annual report on progress with the Progress report submitted to the Q2 2024
implementation plan for green sustainable Commission
public transport development
83.3 5.1 Interim step Annual report on progress with the Progress report submitted to the Q2 2025
implementation plan for green sustainable Commission
public transport development
83 5.1. Deploy safe, green, Μ Implementation of Transport and Mobility Implementation of several key measures of Q2 2026
competitive, needs-based and Development Plan 2021-2035 the Transport and Mobility Development
sustainable transport and energy Plan 2021-2035 completed
infrastructure
84 5.2. Construction of a section of the Μ Award of a railway construction contract for the Contract signed Q2 2022
westbound Tallinn-Rohukűla railway construction of a railway on the sections of
Turba-Ellamaa and Ellamaa-Risti
85 5.2. Construction of a section of the T Completion of new railway (ready for traffic) Km of railway track 0 15 Q4 2024
westbound Tallinn-Rohukűla railway
71
# Related measure M/T Name Qualitative indicators Quantitative indicators Date for completion
(reform or investment) (for milestones) (for targets)
Unit Baseline Goal Q Year
86 5.3. Construction of the Rail Baltic Μ Award of the contract for the construction of Contract signed Q1 2022
multimodal joint terminal in Tallinn the Rail Baltic multimodal terminal building in
Tallinn
87.1 5.3 Interim step Completion of first phase of works for the Completion of excavation, consolidation, Q2 2023
tunnel piping
87 5.3. Construction of the Rail Baltic Μ Completion of the terminal passage Light traffic tunnel under the terminal Q4 2024
multimodal joint terminal in Tallinn authorised
88.1 5.3 Interim step Completion of first phase of works for the Completion of heavy works, excavation, Q4 2024
terminal building concrete and steel works of the north and
south sections of structures of the terminal
building
Completion of relocation of existing
1520mm railway and tunnel sections below
it
88 5.3. Construction of the Rail Baltic Μ Completion of the new railway station Construction works completed Q1 2026
multimodal joint terminal in Tallinn
89 5.4. Construction of the Tallinn Old Μ Completion of the tramway construction project Approval of the project design Q4 2021
Port tram tine design
90 5.4. Construction of the Tallinn Old Μ Award of works contract Contract signed for the construction of the Q3 2022
Port tram line tramway line
91.1 5.4 Interim step Completion of excavation, utilities diversion Completion of heavy works e.g. Meters of tramway line 2500 Q4 2023
excavation, consolidation, piping and other
key structural elements of the tramline
foundation
91 5.4. Construction of the Tallinn Old T New tramway line in operation Metres of tramway line 0 2500 Q2 2024
Port tram line
92 5.5. Municipalities' investments in Μ Call for proposals for grants Publication of the notice for call for Q4 2022
bike- and walkways proposals for grants
72
# Related measure M/T Name Qualitative indicators Quantitative indicators Date for completion
(reform or investment) (for milestones) (for targets)
Unit Baseline Goal Q Year
93.1 5.5 Interim step Decisions on financing applications for bike- Decisions on financing applications Q4 2023
and/or walkways infrastructure adopted
93 5.5. Municipalities' investments in T Bike- and walkways infrastructure completed Km of bike- and walkways 0 24 Q4 2025
bike- and walkways
94 6.1. A comprehensive change in the Μ Entry into force of the Government Regulation Entry into force of the Regulation Q4 2024
organisation of health care in on the Hospital network development plan
Estonia
95 6.1. A comprehensive change in the Μ Approval of the Strategic Framework for Approval of the Strategic Framework for Q4 2022
organisation of health care in addressing health workforce shortages addressing health workforce shortages by
Estonia the Minister of Health and Labour
95.1 6.1 Ex-post monitoring Progress report Submission of a progress report to the Q2 2025
Commission on the implementation of the
actions included in the Strategic
Framework addressing health workforce
shortages
96 6.1. A comprehensive change in the Μ Entry into force of the Decree of the Minister of Entry into force of the Decree of the Q1 2023
organisation of health care in Health and Labour and Health on the Service Minister of Health and Labour and Health
Estonia Organisation Act amending the reimbursement on the Service Organisation Act
system for doctors, nurses and pharmacists
97 6.1. A comprehensive change in the T Admission to nursing training Percentage increase in the 0 5 Q4 2023
organisation of health care in number of persons admitted to
Estonia nursing training
98.1 6.1. Interim step Progress report Submission of a progress report to the Q4 2023
European Commission on the negotiations
between the Ministry of Social Affairs and
the University of Tartu on the shortage of
doctors in certain specialisations
98 6.1. A comprehensive change in the Μ Entry into force of the Ministerial Regulation Entry into force of the Ministerial Q2 2026
organisation of health care in amending the agreement between the Ministry Regulation and agreement between the
Estonia of Social Affairs and the University of Tartu on Ministry of Social Affairs and the University
of Tartu
73
# Related measure M/T Name Qualitative indicators Quantitative indicators Date for completion
(reform or investment) (for milestones) (for targets)
Unit Baseline Goal Q Year
the shortage of doctors in certain
specialisations
99 6.2. Establishment of the Northern Μ Signature of the design contract of the Signature of the design contract Q4 2021
Estonia Medical Campus Northern Estonia Medical Campus
100.1 6.2 Interim step Progress report Submission of a progress report to the Q2 2023
European Commission on the state of play
of the desgin contract of the Northern
Estonia Medical campus including on the
projected timeline for the finalisation of the
design contract.
100 6.2. Establishment of the Northern Μ Signature of the contracts for the excavation Signature of contracts Q4 2023
Estonia Medical Campus and for the water supply and electricity, and for
the reinforced concrete structures of the
Northern Estonia Medical Campus
100.2 6.2 Interim step Progress report Submission of a progress report to the Q3 2024
European Commission on the state of play
of the contracts signed for the excavation
and for the water supply and electricity,
and for the reinforced concrete structures
of the Northern Estonia Medical Campus
and the expected timeline to finalise the
different contracts.
100.3 6.2 Interim step Certificates of completion Certifcates of completion for the desgin Q2 2026
contract of the Northern Estonia Medical
campus and for the contracts signed for
the excavation and for the water supply
and electricity, and for the reinforced
concrete structures of the Northern Estonia
Medical Campus.
101 6.2. Establishment of the Northern Μ Signature of the contract for the construction of Signature of the contract Q1 2024
Estonia Medical Campus the Northern Estonia Medical Campus
74
# Related measure M/T Name Qualitative indicators Quantitative indicators Date for completion
(reform or investment) (for milestones) (for targets)
Unit Baseline Goal Q Year
102 6.2. Establishment of the Northern T 10% of the volume of the construction contract Progress in construction (%) 0 10 Q4 2024
Estonia Medical Campus is fulfilled
103 6.2. Establishment of the Northern T 50% of the volume of the construction contract Progress in construction (%) 10 50 Q4 2025
Estonia Medical Campus is fulfilled
104 6.2. Establishment of the Northern Μ Signature of the contract for equipping the Signature of the contract Q2 2025
Estonia Medical Campus Northern Estonia Medical Campus to make it
fully operational
105 6.2. Establishment of the Northern Μ Completion of the construction works Certificate attesting the completion of the Q2 2026
Estonia Medical Campus construction works
105.1 6.2 Ex-post monitoring Certificate on initiating the procedure of Certificate on initiating the procedure that Q4 2026
compliance and progress report the building complies with the relevant
regulations and a progress report on
equipping and operationalising the
Northern Estonia Medical campus
106 6.3. Strengthening primary health Μ Entry into force of the Decree of the Entry into force of legislative amendments Q3 2020
care Government, which amends the list oí health
care services of the Estonian Health Insurance
Fund on access to specialised medical care
107 6.3. Strengthening primary health Μ Entry into force of amendments to the Decree Entry into force of the legislative Q1 2021
care of the Government which amends the list of amendments to the Decree of the
health care services of the Estonian Health Government
Insurance Fund on costs and services of
general practitioners
108 6.3. Strengthening primary health Μ Entry into force of amendments to the Health Provision in the law indicating the entry Q1 2023
care Services Organisation Act into force of the law
109 6.4. Renewal of the eHealth Μ Approval of the eHealth Governance Approval of the proposal on the eHealth Q2 2023
Governance Framework and its implementation roadmap Governance Framework and
implementation roadmap by the Steering
Committee of the “Eesti tervise IKT
juhtimise raamistik"
75
# Related measure M/T Name Qualitative indicators Quantitative indicators Date for completion
(reform or investment) (for milestones) (for targets)
Unit Baseline Goal Q Year
110.1 6.5. Interim step Draft tender specification for the Submission to the Commission of the draft Q2 2023
multifunctional medical helicopter capabilities tender specification
110 6.5. Capacity building for Μ Award of contracts for multifunctional medical Award of the public procurement contracts Q4 2023
multipurpose medical helicopters helicopter capabilities
111 6.5. Capacity building for T Reception of helicopters Number of helicopters 0 2 Q1 2025
multipurpose medical helicopters
112 6.5. Capacity building for T Completion of airbases built or expanded Number of helicopters bases 0 2 Q2 2026
multipurpose medical helicopters
113 6.6. Providing labour market Μ Entry into force of the Decree of the Minister of Entry into force of the Decree of the Q1 2022
measures to reduce youth Health and Labour to strengthen the “My First Minister of Health and Labour
unemployment Job" scheme
114 6.6. Providing labour market Μ Youth Guarantee Action Plan Adoption of the reinforced Youth Q2 2022
measures to reduce youth Guarantee Action Plan by the Government
unemployment
115.1 6.6. Interim step Number of young people participating in the Number of participants 0 1800 Q4 2023
“My First Job" scheme
115 6.6. Providing labour market T Number of young people participating in the Number of participants 0 3178 Q4 2025
measures to reduce youth “My First Job” scheme
unemployment
116.1 6.7 Interim step Report on the results of consultation with social Submission to the Commission of a report Q2 2022
partners on the consultation of social partners on
the mechanism of prolongation and the
margin to be used.
116.2 6.7 Interim step Draft amendments to the Unemployment Submission to the Commission of the draft Q4 2022
Services and Benefits Act and the amendments
Unemployment Insurance Act
116 6.7. Extending the duration of Μ Entry into force of the amendments to the Entry into force of the legislative Q2 2023
unemployment insurance benefits Unemployment Services and Benefits Act and amendments
the Unemployment Insurance Act
76
# Related measure M/T Name Qualitative indicators Quantitative indicators Date for completion
(reform or investment) (for milestones) (for targets)
Unit Baseline Goal Q Year
117 6.8. Long-term care Μ Entry into force of amendments to the Social Entry into force of legislative amendments Q2 2022
Welfare Act
118 6.8. Long-term care Μ Action Plan on an integrated care model Adoption of the Action Plan Q4 2022
118.1 6.8. Ex-post monitoring Progress report Submission to the Commission of a Q4 2025
progress report on the implementation of
the actions included in the Action Plan on
an integrated care model.
119 6.8. Long-term care Μ Entry into force of the decree of the Minister of Entry into force of the decree of the Q4 2024
Social Protection Minister of Social Protection
120 6.8. Long-term care Μ Entry into force of the legislative amendments Entry into force of the legislative Q1 2025
of the support system for children with high amendments
care needs
121 6.9. Reducing gender pay gap Μ Adoption of the Welfare Development Plan Adoption of the Welfare Development Plan Q1 2024
2023-2030 by the government
121.1 6.9 Ex-post monitoring Progress report Submission of a progress report on the Q1 2026
implementation of the actions on gender
pay gap included in the Welfare
development plan 2023-2030
122 6.9. Reducing gender pay gap Μ Digital gender pay gap tool Developing a prototype of a gender pay Q4 2022
gap tool
123.1 6.9. Interim step Μ Progress report Submission to the Commission of a Q2 2023
progress report on the state of play of
rolling out a gender pay gap tool.
123 6.9. Reducing gender pay gap Μ Digital gender pay gap tool Roll-out of a digital gender pay gap tool Q1 2024
123.2 6.9 Ex-post monitoring Progress report Submission to the Commission of a Q2 2026
progress report on employers’ experience
of using of the gender pay gap tool and
how it helped them to take effective action
77
# Related measure M/T Name Qualitative indicators Quantitative indicators Date for completion
(reform or investment) (for milestones) (for targets)
Unit Baseline Goal Q Year
in order to implement the principle of equal
pay and to reduce the gender pay gap
124 Monitoring and implementation of Μ Entry into force of the Government Regulation Entry into force of government regulation Q4 2021
the plan on the legal framework for the implementation
and monitoring of the recovery and resilience
plan of Estonia.
78