Interreg Programme VI-A – Estonia-Latvia 30.06.2023 no10-3/25-1053
[email protected]
Sõbra 56
50106 Tartu
Response to Interreg Programme VI-A – Estonia-Latvia Monitoring Committee decision
about project application HydroScope
Dear Tõiv Jõul,
On behalf of the Lead Partner (Geological Survey of Estonia), we hereby submit our formal response to
the specific conditions set by the Monitoring Committee for the project HydroScope (EE-LV00250), as
outlined in Annex 1 of the selection decision.
Below, we list each condition along with our detailed reply.
1. Please explain whether and how the planned activities described under Activity 2.5 are linked to
the defined output indicators. If those activities do not contribute to and support directly the planned
jointly developed solutions, they must be removed from the application form and the budget reduced
accordingly. In the latter case, please also review the related aspects of Activity 2.4 and either provide
justification for keeping them or remove them from the application.
The activities under Activity 2.5 are directly linked to the output indicators and are necessary for
delivering the jointly developed solution, the real-time decision-making system.
Monitoring springs requires that the spring sites reflect natural groundwater conditions. If a spring is
affected by litter, bank erosion, uncontrolled water extraction, or surface runoff directly into the spring,
the monitoring data becomes unreliable since it is unclear whether detected pollution originates from
the groundwater itself or is introduced from surface sources, which may not reflect the actual condition
of the aquifer. This would compromise the accuracy of the early warning system. Cleaning, installing
protective measures, and maintaining the spring sites are essential for ensuring that the data reflects
groundwater quality, not surface-level disturbances.
Small-scale pilot measures are equally necessary for ensuring the longevity of the developed solution,
as they are a critical part of testing and demonstrating how the platform supports real-time decision-
making. When the early warning system flags an issue, municipalities can implement mitigation actions
and use the platform to evaluate whether those measures are effective. By using preliminary monitoring
results and carrying out small-scale pilot activities aimed at improving spring groundwater quality and
protecting groundwater-dependent ecosystems around spring sites during the project, municipalities
gain their first practical experience with what to do and how to do it. In the HydroScope project, it is
very important to us that the main users of the early warning platform are also equipped with the
necessary experience and knowledge to take action when pollution occurs or when ecosystem health is
at risk.
Fr. R. Kreutzwaldi 5 / 44314 Rakvere, Estonia /
[email protected] / www.egt.ee/en
Activity 2.4 and 2.5 are directly connected. The guidelines and thresholds developed under 2.4 are
applied in 2.5 as hands-on pilot actions with municipalities. Without these activities, the monitoring
system cannot function reliably or deliver accurate results. For this reason, the activities under Activity
2.5 (as well as 2.4) are fully in line with the output indicators and directly support the jointly developed
solution.
2. Please address the inconsistency between Output 1.1 and Activity 1.4 by clarifying whether a single
unified early warning platform will be developed for both countries or if a separate platform is
planned for Estonia and Latvia. Please ensure a consistent description throughout the application
form.
A single, jointly developed early warning system will be created for both countries. This system will
be deployed through two separate web platforms, one for Estonia and one for Latvia, to ensure that
municipalities and stakeholders in each country have access to locally relevant data through familiar
national portals.
This approach is technically and practically justified. Hosting the platforms within existing national
environmental GIS portals guarantees that groundwater data is easily accessible to the municipalities
and other stakeholders who will use these platforms more regularly. It also ensures that the system
remains functional and visible beyond the project lifetime without requiring the creation of an entirely
new cross-border IT infrastructure, which would be significantly more costly and less sustainable.
It is important to emphasize that while there are two separate web platforms for practical deployment,
they both visualize and operate on data generated from the same jointly developed early warning system.
The cross-border collaborative process focuses on creating a shared solution for data collection, real-
time monitoring and predictive modeling, while the user interfaces will be tailored to the needs,
languages, and technical environments of each country. In summary, the HydroScope project will
develop one unified early warning system, delivered through two separate early warning
platforms.
3. Please explain how the two planned pilot actions are jointly developed between Estonian and
Latvian partners.
The two pilot actions, (1) the deployment of real-time groundwater telemetry systems, and (2) the
implementation of digital spring monitoring with pollution mitigation measures, are the result of a joint
development process involving both Estonian and Latvian partners at every step. These actions are not
separate initiatives carried out in parallel, but rather integrated, cross-border efforts designed
collaboratively to address shared groundwater challenges and build a harmonized early warning system.
In the case of telemetry systems (developed under Activity 1.1 and implemented under Activity 2.1),
LEGMC, with its existing telemetry experience, provides practical guidance to Estonian partners on
procurement, technical options, installation, and maintenance. Input from Saaremaa and
Dienvidkurzeme municipalities is used to define specific groundwater problems (e.g. drought
sensitivity, contamination risks) and data needs. These local insights guide decisions about where and
how telemetry systems should be installed.
The scientific partners also collaborate closely. UL evaluates what types of monitoring data are needed
for machine learning models and defines data formats and resolution requirements (Activity 1.1). UT
contributes to the design and site selection process in Estonia, ensuring sensors are placed where they
can provide the most meaningful insights for tracking pollutant transport and aquifer conditions. GSE,
as lead partner, facilitates and coordinates these technical discussions, making sure that all partners’
perspectives are reflected in the decisions and that the outcome supports the development of a truly
cross-border early warning system. National monitoring authorities (EEA in Estonia and LEGMC in
2 (12)
Latvia) make sure that the pilot monitoring sites align with and add value to national monitoring
networks.
The digital spring monitoring systems and pollution mitigation measures are also jointly developed
under Activity 2.2, Activity 2.4, and Activity 2.5. First, the two municipalities identify a list of potential
spring sites. These are jointly assessed by GSE, UT, LEGMC, EEA, and UL, who contribute expertise
on hydrogeology, monitoring infrastructure, national monitoring system compatibility, and data
modelling needs. The final selection of digital spring systems takes into account ecological relevance,
data requirements, and logistical feasibility, and is agreed upon collaboratively by all involved partners.
The design of mitigation measures (such as buffer zones, erosion control features, or protective
installations) is based on jointly developed guidelines and thresholds produced by UT under Activity
2.4, with scientific coordination from GSE and input from EEA and LEGMC to ensure national
relevance. These guidelines are rooted in the ecological and hydrogeological analysis carried out jointly
earlier in the project (Activity 1.2). The final mitigation solutions are implemented in both countries
under Activity 2.5 (supported by UT with close cooperation with the municipalities), following a shared
logic to ensure comparability, replicability, and common learning outcomes. Throughout the pilot, the
municipalities receive continuous technical guidance and field-level support from all partners involved.
Cooperation takes place through joint planning sessions, site visits, and cross-border meetings, many of
which are scheduled alongside other project events to ensure broad participation. For example, Estonian
partners will visit LEGMC's existing telemetry sites in Latvia to learn from their setup (Activity 1.1),
and Latvian partners will visit Saaremaa’s spring site and monitoring wells (Activity 1.5). These sessions
result in shared technical plans, implementation schedules, and data integration strategies that support
the early warning system.
In summary, both pilot actions (telemetry systems and digital spring monitoring with mitigation) are co-
developed by all partners. Technical, scientific, and municipal partners from both countries contribute
to every relevant activity. Rather than pursuing country-specific solutions, HydroScope takes a
collaborative, cross-border approach to building an early warning system that is rooted in shared
learning, joint technical development, and aligned goals. This ensures that the outcomes are innovative,
scalable and sustainable across both national contexts.
4. Please explain and, if necessary, include corresponding information on planned system setup
activities in Latvia under Activity 1.2, to complement the Estonian example in Saaremaa.
We assume that the question refers to Activity 2.1 – the piloting of telemetry systems – rather than
Activity 1.2, which focuses on the preparatory analysis and definition of groundwater droughts and does
not involve municipality-specific technical setups.
The planned system setup in Dienvidkurzeme follows the same general logic as in Saaremaa. GSE will
procure and install approximately 7 to 10 telemetry systems in Saaremaa, with the exact number and
type determined in collaboration with the municipality and other project partners based on which
parameters are most relevant and where monitoring coverage is the most essential. Similarly, LEGMC
is expected to procure approximately 5 to 7 telemetry systems.
The difference in budget and number of systems is due to the different starting points in each country.
While Saaremaa requires the establishment of an entirely new telemetry network, in Dienvidkurzeme
the focus is on strengthening and optimizing the existing network to support the early warning system.
Depending on the results of the coverage analysis, the setup in Dienvidkurzeme may also prioritize
fewer but more advanced systems that capture key site-specific parameters relevant to local groundwater
management. This would also support the broader development of more advanced telemetry practices
in Latvia. The final setup will be determined collaboratively, based on an assessment of existing
3 (12)
infrastructure, results from the coverage analysis, and discussions with Dienvidkurzeme municipality
and project partners.
In conclusion, the telemetry setup approach is consistent for both countries. The final selection of
monitoring wells, parameters and sensor types will be based on technical assessments and close
collaboration between project partners, ensuring that the monitoring networks are fit for purpose and
fully integrated into the early warning system.
5. Please indicate the number of digital spring sites planned in Estonia and Latvia under Activity 2.2.
Under Activity 2.2, one digital spring site is planned in Estonia and one in Latvia, resulting in a
total of two. Digital spring monitoring systems are more technically complex and resource-intensive
compared to well telemetry, as they require equipment for continuous automated measurements of flow,
water quality, and sometimes additional ecological parameters. This also makes them more costly. As
this is the first time spring data will be used in an early warning system in either country, it is both
practical and methodologically sound to focus on one site per country. This approach allows the project
to properly test how the system functions, evaluate its usefulness for real-time monitoring and decision-
making and understand its role in protecting groundwater-dependent ecosystems. Limiting the pilot
actions to one spring site per country also ensures that sufficient attention can be given to understanding
the specific environmental conditions around each spring.
6. Please explain how the guidelines developed under Activity 2.4 will be practically integrated into
the platform’s operation and use.
The guidelines developed under Activity 2.4 are directly integrated into the platform’s operation and
use in two key ways.
Firstly, the thresholds and indicators developed under Tasks 1 and 2, such as baseline conditions,
pollution limits, and ecological thresholds, form the basis for how the early warning system functions.
These thresholds are essential for the system to provide meaningful alerts. Without them, the early
warning platforms could only show raw data, leaving municipalities to interpret on their own what
constitutes a risk or an unacceptable condition. Instead, the guidelines define when groundwater quality
or quantity becomes critical for either human use or ecosystem health, and they are embedded into the
system logic to automatically trigger warnings or advisories when these conditions are met or
approached.
Secondly, the mitigation and resilience measures developed under Task 3 are connected to the platform
in a practical way. When municipalities receive an alert (for example, that nitrate levels are nearing a
critical threshold or that drought conditions are emerging), the platform is complemented by the
guidelines, which help municipalities understand what the risk means and what response actions are
available. This means the platform informs about problems and directs users toward appropriate
solutions, tailored to groundwater quality management and the protection of groundwater-dependent
ecosystems.
During the project, selected measures from the guidelines will be piloted together with municipalities
based on preliminary monitoring data, as described in Activity 2.5, and further under Question 1. This
ensures that municipalities gain hands-on experience with the full decision-making process and are able
to go from interpreting platform alerts to implementing actual mitigation and prevention actions. The
developed guidelines that will be used for small-scale pilot actions during the project are thus crucial
for building the capacity of municipalities to use the early warning platforms effectively after the project
ends.
4 (12)
Guidelines developed under Activity 2.4 also align with Activity 3.1, specifically the preparation of user
guides, which will further ensure that the guidelines are presented in an accessible, user-friendly format
that complements the platform’s day-to-day use.
7. For Activity 3.1, please define what types of technical documentation and user guidelines will be
made public and which will be tailored specifically for participating municipalities. Also, please
specify the content and materials planned to be developed for capacity-building seminars.
In Activity 3.1, the HydroScope project focuses on the publication and dissemination of the jointly
developed early warning system to ensure its visibility, usability, and long-term impact. As part of this
process, several types of technical documentation and user guidelines will be created, each tailored to
different audiences and use cases.
Publicly available materials will include a general user guide to help both professionals and non-experts
understand how to interpret and use the web-based early warning platforms published on the national
GIS portals (Keskkonnaportaal in Estonia and LEGMC’s portal in Latvia). This guide will explain the
visual logic of the platform, such as the meaning of colour-coded alerts, how to toggle data layers,
navigate the timeline, and access specific spring or well data. In addition, metadata will be published
alongside the datasets, detailing when the data was last updated, which institution collected it, and under
what methodology. A simplified technical overview of the machine learning algorithms used in the
system will also be made available, focusing on transparency: it will describe what data types feed the
model and what kinds of predictive alerts (e.g. drought or pollution risk) the system is capable of
producing. These materials will be accessible directly from the platform interface and are modelled after
similar guides used in existing national mapping portals.
Municipality-specific documentation will include a more detailed set of scenario-based user guidelines
to the needs of Saaremaa and Dienvidkurzeme municipalities, but is designed to be adaptable by other
regions in the future. These materials will include instructions on what steps to take when the platform
signals a rising pollution risk or groundwater level decline. For example, if the concentration of a
chemical compound increases in a digital spring, the guide will explain how to check for possible non-
groundwater-related causes (e.g. surface contamination) and assess whether further sampling or field
inspections are required. If a drought warning is triggered, the materials will identify which areas in the
municipality are most vulnerable and recommend step-by-step response measures, such as water-saving
protocols or communication with local water users. These guidelines will cover multiple categories of
risk (e.g. groundwater quality, quantity, ecosystem thresholds) and outline actions that can be taken both
immediately and preventively. While these materials will be provided directly to municipalities, a
broader overview of this content (summarizing key findings, recommendations, and pilot outcomes)
will be included in the project’s final public report to support transparency and replication.
For capacity-building seminars, the project will produce a complete set of instructional materials to be
used during and after the events. These include slides and scenario-based exercises. The content will
explain the core functionalities of the early warning platform and provide a simplified explanation of
how the machine learning models operate. It will also guide participants through practical examples of
how to interpret system alerts and visualizations, and what actions could be taken in various real-world
situations. These seminars will help a wider group of stakeholders (beyond the two pilot municipalities)
understand how the platform can be used for operational decision-making. Case-based discussions will
show how different user groups (e.g. municipal planners, environmental inspectors, emergency
responders) can engage with the platform and how its outputs can support evidence-based responses.
8. For Activities 3.1 and 3.2, please provide a clearer structure distinguishing the various planned
materials (e.g., stakeholder-friendly guides, reports, roadmaps) and explain how they complement
one another.
5 (12)
Under Activity 3.1, the focus is on user guidance, awareness-raising, and capacity-building. The
following key materials will be produced:
1) Municipality-specific user guidelines (targeted for Saaremaa and Dienvidkurzeme):
These materials are developed specifically for the two pilot municipalities (Saaremaa and
Dienvidkurzeme) and are provided in Estonian and Latvian. They are practical, scenario-based
guides explaining what steps local authorities should take when the early warning system issues
alerts (e.g., rising pollution levels or declining groundwater levels). These guides will help
municipalities interpret alerts, assess risks, and take appropriate mitigation measures. While
they are based on content from the final report, they are presented in a highly practical and
accessible form tailored to municipal workflows.
2) Capacity-building seminar materials:
These include slides used during stakeholder training events. They explain the functioning of
the early warning platform, interpretation of alerts and visualizations, and possible actions that
different stakeholders can take. The materials are prepared in Estonian and Latvian and will be
made available to participants after the seminars. While thematically similar to the municipality-
specific guides, these materials are more general and outreach-oriented, aiming to introduce the
system to a broader stakeholder group, including sectoral agencies, NGOs, and potential future
users.
3) Stakeholder-friendly outreach materials, including a one-sheet summary:
This concise, accessible document will summarize the core achievements of the project,
including the location and purpose of the telemetry systems, the functioning and benefits of the
early warning platform, and next steps. It is designed for decision-makers and will be produced
in Estonian and Latvian. The Estonian version will focus more on the potential for future uptake
of real-time monitoring solutions, while the Latvian version will highlight how existing
telemetry data was used effectively for the first time in a real-time context. These materials are
suitable for distribution at events, government-level meetings, or follow-up communication
with relevant institutions.
Under Activity 3.2, the emphasis is on synthesising and documenting the full project process and
outcomes to support knowledge transfer and replication. This includes:
1) Final report (in English):
A comprehensive report co-authored by all partners, documenting the methodology for real-
time monitoring and predictive modeling, including lessons learned, system architecture,
integration processes, and key findings. It will cover technical, ecological, and operational
aspects, with dedicated sections explaining what worked well and what challenges were
encountered. The report is intended for research and policy communities and future cross-border
groundwater projects.
2) Replication roadmap:
This short, practice-oriented document will accompany the final report and be produced in
English, Estonian, and Latvian. It is designed for municipalities, government agencies, and
water authorities who may wish to implement similar systems. The roadmap will summarize
key steps, suggest appropriate sensor types and coverage strategies, and provide guidance on
scaling, from small pilots to national-level platforms. It will clarify which elements are context-
specific and which are broadly transferable, and may include estimated cost ranges and planning
considerations. It will be visually structured and user-friendly to support practical planning.
6 (12)
9. For Activity 3.3, please indicate the number, format, and expected audience of knowledge-sharing
sessions. Please also justify participation in the EGU General Assembly, including the need for two
representatives per country and its relevance for reaching the project objectives.
The planned knowledge-sharing sessions are larger internal project meetings, held online (in either
Teams or Zoom). Their purpose is to review project progress, discuss any issues requiring joint input,
and exchange practical knowledge among partners.
The exact number of sessions will be based on project progress and needs, but is estimated to be
approximately once per quarter, or around 12 sessions over the project period. This number is somewhat
flexible, and additional sessions may be organized when specific tasks are completed or technical
challenges arise that require joint discussion. Each session involves all key project participants, though
the number of attendees may vary depending on how partners assign project roles internally. On average,
we expect participation from at least 6 participants from Estonia (representatives from GSE, EEA, UT,
and Saaremaa) and 5 participants from Latvia (LEGMC, UL, and Dienvidkurzeme). Smaller working
group meetings will be held when necessary to resolve more specific issues, while broader knowledge-
sharing sessions focus on key project milestones and collaborative learning.
Participation in the EGU General Assembly is also an essential part of Activity 3.3. EGU is the largest
geoscience conference in Europe, bringing together leading experts in groundwater monitoring, machine
learning for drought and flood prediction, and automated environmental monitoring systems, all of
which are directly relevant to the HydroScope project. As this is the first time the project team (or anyone
in the Baltics) is applying telemetry data in the context of a groundwater early warning system, attending
EGU provides valuable opportunities to learn from global best practices and explore how similar
platforms have been developed in other regions. EGU also hosts a large exhibition of equipment
providers, including companies specializing in groundwater telemetry systems. This is particularly
important for HydroScope, as it allows the team to compare technical solutions, understand the strengths
and limitations of various systems, and make informed decisions about both current and future
monitoring setups.
Sending two participants per country is a practical necessity given the multidisciplinary nature of the
HydroScope project. For example, one representative may focus on groundwater contamination and
mitigation, while another focuses on data modeling, machine learning or technical infrastructure. The
EGU General Assembly is one of the few events that covers all these disciplines in one place. Dividing
attendance between participants with different areas of expertise ensures that the project team can
efficiently cover all critical topics, connect with relevant experts and bring back applicable knowledge
to support both scientific and practical components of the project.
10. Please explain why only five organisations are expected to continue cross-border cooperation
post-project, despite seven being represented in the project partnership.
Our aim is to maintain cross-border cooperation among all seven project partners after the project ends,
and we will be actively working toward that goal. The reason five organizations (GSE, LEGMC, EEA,
UL, UT) are listed with a higher degree of certainty is simply because these are scientific and
governmental institutions that already have a long-standing history of collaboration through previous
projects and other initiatives, like cross-border river basin management plan meetings. Among these
five organizations, the intent to continue collaboration beyond the current project has already been
discussed during previous projects, and there is a very strong foundation for continued joint activities.
With partner municipalities, the situation is somewhat different, not because of a lack of interest, but
because their participation in future cross-border collaboration typically depends on the thematic focus
of upcoming projects, their local priorities and available resources at the time. That said, we are
committed to strengthening collaboration with both Saaremaa and Dienvidkurzeme municipalities
during the HydroScope project. Discussions about potential follow-up initiatives will include all
7 (12)
partners, as our goal is to ensure that collaboration continues not only between the core scientific
partners but also with the municipal partners whenever the scope and needs align.
So, while the five aforementioned institutions have an already established pattern of cross-border
cooperation that will certainly continue, we are still fully committed to working toward extending future
collaboration to all seven partners wherever possible.
11. The budget related conditions:
In the budget of LP1, please justify the number of working hours planned for the financial manager.
If justification is insufficient, the costs must be reduced.
As the lead partner of the HydroScope project, GSE will carry full responsibility for financial
coordination across all 7 partners of the project. This includes preparing and submitting financial reports,
ensuring compliance with eligibility rules, managing partner contributions, and communicating with the
Est-Lat programme. The financial manager must also coordinate and process internal budget changes,
support partners in solving financial reporting issues, and ensure the project is fully prepared for audits.
Additionally, GSE is responsible for overseeing salary payments, maintaining documentation, and
ensuring all financial procedures align with the programme requirements. These tasks require
continuous attention throughout the project’s duration. Considering the workload, a planned allocation
of approximately 0.3 FTE for the financial manager is both reasonable and necessary to ensure accurate
and timely financial management.
In the budget of LP1, please provide a cost breakdown and justify the costs allocated for
communication and awareness materials. If justification is insufficient, the costs must be reduced.
The allocated 1 100 € (reduced cost) covers essential communication and awareness materials for
events and stakeholder engagement activities led by the Lead Partner (GSE), primarily under WP3
(Dissemination, capacity building and outreach). These materials are modest in scope but necessary to
ensure high-quality, professional communication that aligns with programme visibility rules and
supports stakeholder engagement.
The majority of project communication is digital to minimize environmental impact and cost. However,
some printed and well-designed visual materials are essential to ensure the effective uptake of the
project’s outputs, especially when communicating complex technical topics like telemetry, predictive
modeling, and groundwater protection to local decision-makers and non-technical municipal staff.
This amount represents a modest and cost-efficient communication budget, sufficient to cover the
minimum necessary materials to meet project visibility and stakeholder engagement goals. This includes
printed agendas, name tags, and workshop handouts. Additionally, this includes external graphic design
service to create clear and visually engaging instructional materials for stakeholders attending the
national capacity-building seminar. These materials will help municipalities understand how to use the
early warning platform in their workflows.
Please justify the need for participation in the EGU 2026 conference. Clarify what is included under
the membership fee and abstract submission, and how these expenses directly contribute to the
project’s objectives. If justification is insufficient, the costs must be reduced.
Participation in the EGU General Assembly is an essential part of Activity 3.3 (internal capacity
building), as it directly supports the HydroScope project’s objectives related to innovation, cross-border
learning, and long-term sustainability. EGU is the largest geoscience conference in Europe, bringing
together global experts in key fields relevant to HydroScope, including groundwater monitoring,
8 (12)
machine learning for drought and pollution forecasting, and automated environmental data systems. As
HydroScope is the first initiative in the Baltics to pilot a real-time telemetry-based groundwater early
warning system, it is crucial for the project team to learn from international best practices, explore how
similar platforms have been developed elsewhere, and apply these insights to improve project outcomes.
EGU also features a large technical exhibition with leading telemetry equipment providers. Attending
this exhibition enables project staff to assess the latest monitoring technologies, compare solutions, and
make informed decisions for the current and future development of national monitoring systems in both
Estonia and Latvia.
Due to the multidisciplinary nature of HydroScope, sending two participants per country is necessary.
For example, one participant may focus on hydrogeology and groundwater quality, while another
specializes in machine learning, data pipelines, or system integration. EGU is one of the few events that
brings together these diverse topics under one roof, ensuring that the full range of HydroScope’s
technical and scientific components is addressed.
All participants will also submit abstracts presenting HydroScope results, which directly supports the
project’s outreach and visibility goals. At EGU, presenting a poster or talk significantly increases the
chances of attracting relevant contacts, such as researchers working on similar tools, environmental
agencies, and technology providers. Being featured on the programme also makes it easier for
participants to find and connect with HydroScope representatives.
Participation in EGU requires two mandatory but small additional costs beyond the conference
registration fee:
1) An EGU membership fee (approximately €10–20 per person), which is required to register for
the event;
2) An abstract submission fee (approximately €50 per abstract), which covers processing and
ensures that the contribution is included in the official programme.
In the budgets of LP1 and PP2, please justify the quantity and cost of the digital spring monitoring
equipment, ensuring it is necessary and proportionate to the pilot activities.
Both partners (GSE in Estonia and LEGMC in Latvia) plan to procure and install one digital spring
monitoring system, with a budget allocation of 21 500 € per unit. This amount is based on existing
experience in Latvia, which indicates that the typical cost of a complete digital spring system falls within
the 20 000–21 000 € range. These systems are technically complex, as they continuously measure both
discharge (flow) and physico-chemical parameters. Unlike groundwater wells, springs offer a unique
opportunity to assess groundwater discharge under natural, undisturbed conditions, making them ideal
for evaluating ecosystem health, baseflow dynamics, and climate-related impacts.
These systems are essential for piloting real-time monitoring at spring sites, and this activity cannot be
meaningfully conducted without such equipment. The budgeted cost is appropriate and proportionate
considering the technical requirements and the market price of these systems. The total cost also includes
a small buffer of 500–1 000 € per country to cover installation materials, such as protective mounting
frames or small adaptations that may be needed at the selected spring sites. Final equipment
specifications and exact costs will be confirmed during procurement, but both countries will jointly
ensure that the selected systems remain within the allocated budget.
Provide justification for the number of hours allocated to web-based application development and
clarify whether this refers to the same platform described in other sections of the application form. If
justification is insufficient, the costs must be reduced.
9 (12)
The budgeted cost of 25 000 € per partner (EEA and LEGMC) is intended for the development and
integration of two separate web-based platforms, each developed for one country. These platforms are
not separate systems but two interfaces connected to a single, jointly developed early warning system
that includes real-time telemetry, machine learning–based predictions, and ecological insights. The
reason two platforms are needed is practical and strategic: the HydroScope system will be embedded
into existing national GIS portals (Estonian Keskkonnaportaal and the LEGMC GIS portal), which are
already known and trusted by municipalities and environmental agencies. This ensures long-term
accessibility, usability, and sustainability of the platform after the project ends, without requiring a new
standalone web solution, which would be significantly more expensive to develop and maintain.
The budget of each 25 000 € allocation includes:
1) the integration of real-time data pipelines from telemetry and digital spring systems,
2) automation of map updates and visualization of predictive results (e.g. droughts, pollution risks),
3) user interface development to national systems, workflows, and language,
4) iterative testing and refinement based on project partner feedback.
While we cannot specify the number of working hours in advance since development may be contracted
as either fixed-price or hourly service, depending on the provider, the budget reflects our partners’ expert
estimates of the minimum feasible cost to deliver these platforms. Cutting these costs would directly
compromise the functionality, usability, and long-term value of the early warning system. Therefore,
the allocated sum is entirely necessary to meet the technical and strategic goals of the project.
Please justify the planned catering costs for LP1, PP3, PP4, and PP7, ensuring they are appropriate
and clearly linked to project events or activities. If justification is insufficient, the costs must be
reduced.
1) LP1 (7 000 €): Covers two separate 2-day events in Tartu. The first event will host approx. 15
participants (budget 2 500 €), and the second event will serve 30–35 participants (budget
4 500 €). Both include coffee breaks and lunches. These estimates are based on recent
experience with similar seminars in Tartu and reflect typical costs for professional catering,
including VAT and service fees.
2) PP3 (3 500 €): Covers a 2-day event in Riga. Day 1 is a stakeholder seminar for ~25
participants, and Day 2 is an internal workshop for ~10 participants. Riga’s catering services
are typically more expensive due to higher base prices in the capital. The budget reflects local
market rates and includes coffee breaks and lunches.
3) PP4 (3 500€): Covers two days of activities in Saaremaa, including a workshop day (~25–30
participants) and a field trip to pilot sites (telemetry wells and digital springs). Catering
includes coffee breaks and lunch for both days. The budget also accounts for logistical costs in
a rural location, where fewer catering providers are available and transport costs may apply.
4) PP7 (3 500€): Covers a similar 2-day format in Dienvidkurzeme: approx. 1,5 days of
discussions and half-day field visits to potential pilot sites, with ~25 participants. Catering
covers lunches and coffee for participants and external guests involved in site selection and
platform development.
In summary, taking into account the increased catering prices in recent years, the number of participants,
the full-day nature of these events, and the partners' recent experience in organizing similar gatherings,
we consider the planned catering budgets to be appropriate, proportionate, and well-justified. They are
sufficient to cover essential hospitality needs without being excessive.
10 (12)
Please justify the costs for the high-performance computer for PP3 by specifying its use in relation
to “the study areas” and its necessity for project implementation. If justification is insufficient, the
costs must be reduced.
A high-performance computer is essential for UL's role in developing advanced machine learning
models, which require significantly more computational power than standard office computers. These
models, developed under task WP1 Activity 1.3, will integrate diverse datasets, including real-time
drought and pollution prediction based on data from both Estonian and Latvian study areas, to predict
groundwater levels and assess drought and pollution risks in both countries.
While the high-performance computer itself will be physically located at the University of Latvia in
Riga, it will process data from both pilot areas: Saaremaa (Estonia) and Dienvidkurzeme (Latvia). The
location of the hardware does not affect the relevance of the data, as its function is to deliver cross-
border predictive tools that support municipalities in both countries. UL is the only partner in the project
with the necessary expertise in machine learning, which is why this work must be carried out at their
facilities in Riga.
The current computing resources available to the UL team are inadequate for such advanced modeling
due to limitations in processing power and RAM capacity. A new high-performance computer is
therefore necessary to ensure the successful execution of these tasks.
While the primary use of this computer will be for WP1 Activity 1.3, it will also support WP1 Activity
1.2 for historical data analysis and other UL activities within the project.
Equipment and related staff costs listed by PP4 and PP7 need to be justified, ensuring they are directly
linked to pilot activities and necessary for achieving the intended outcomes. If justification is
insufficient, the costs must be reduced.
The equipment and related staff costs under PP4 and PP7 are directly linked to Activity 2.5 and are
essential for the successful implementation of the jointly developed early warning system. These costs
support the maintenance, cleaning, and small-scale mitigation measures at digital spring pilot sites,
ensuring that monitoring data remains reliable and actionable.
Spring monitoring is only effective when the spring site reflects true natural groundwater conditions.
However, many springs are impacted by surface-level disturbances such as litter, erosion, unmanaged
access, or runoff from surrounding land. Without proper site maintenance and protection, telemetry data
from digital springs can show pollution from surface inputs instead of groundwater sources. This would
undermine the reliability of the early warning platform, leading to incorrect risk assessments.
To prevent this, equipment is needed to clean and protect the digital spring site, install visitor
management infrastructure, and prevent surface contamination. The exact equipment depends on the
final site conditions, which will be determined collaboratively during the project. These are not large
infrastructure investments, but rather essential field tools and materials needed to ensure the usability of
the digital monitoring system.
The digital spring site maintenance technician positions in both municipalities are necessary to support
these efforts. These roles are temporary, project-funded staff who will:
1) perform site cleanup and maintenance, install and monitor small-scale mitigation measures,
2) ensure the monitoring equipment remains protected and functional,
3) respond to any platform alerts (e.g., pollution spikes or abnormal discharge) by checking
conditions on site,
4) collaborate with UT and UL to implement ecological or technical recommendations from
Activity 2.4.
These tasks require regular attention throughout the project to ensure pilot sites remain viable for
continuous, high-quality data collection. Moreover, the hands-on experience gained by municipal staff
11 (12)
in maintaining spring sites and implementing real-time mitigation actions is a critical part of building
long-term capacity. The HydroScope platform is designed to support informed and timely municipal
action. For that to be effective, the municipalities must also be equipped to act, and this includes the
necessary personnel and basic tools.
Please clarify whether bus rental costs are intended for project staff or external participants, and how
they support specific project activities. Please note that travel and accommodation costs for project
staff fall under the cost category "Travel and accommodation".
The bus rental cost (approx. 800 € each) covers two separate one-day field trips (one in Saaremaa and
one in Dienvidkurzeme), which take place as part of the respective 2-day pilot area events organized by
the municipalities. These field trips are a key part of the events, designed to bring participants on-site to
visit digital spring monitoring locations and groundwater telemetry wells established through the
project.
The bus will be used exclusively during the event day to transport participants from the event venue to
multiple monitoring locations and back. The trip begins and ends at the same location where the event
is held. It is not a transfer to the event location, but rather an integral part of the event itself, allowing
participants, including project partners and relevant stakeholders, to gain a shared understanding of the
selected spring sites, the progress in installing digital monitoring systems, and local hydrogeological
conditions.
This bus rental:
1) is not for project staff travel to/from the event and therefore does not fall under the "Travel
and accommodation" cost category,
2) is a logistics cost related to event implementation, comparable to venue or equipment rental.
3) cannot be replaced with individual ticket purchases, as the destination is rural, the field trip is
coordinated in a single group, and transportation to multiple remote locations is needed.
The cost (approx. 800 €) covers a 30+ seat bus, including fuel and driver, and is based on market prices
for such services in rural regions.
We trust that the explanations provided here adequately address all the stipulated conditions. We are
prepared to update the project application in the Jems system as soon as this content has been agreed
upon with the Joint Secretariat.
Please do not hesitate to contact us should you require any additional clarification or documentation.
Sincerely
(signed digitally)
Magdaleena Männik
Hydrogeologist
Geological Survey of Estonia
(signed digitally)
Sirli Sipp Kulli
Director
Geological Survey of Estonia
12 (12)