CONFIDENTIAL
RB Rail AS Your Ref: 30.10.2019 No
K.Valdemāra iela 8-7
LV-1010, Riga Our Ref: 07.11.2019 No 24.5-6/19-
0095/8261
Latvia
On Rail Baltica project implementation
Thank you for forwarding the statement reflecting concerns in relation to the Rail Baltic(a) project.
Estonia, being a party to the Rail Baltica project who has actively participated in it since
undertaking the process of Rail Baltica route planning, performing its Strategic Environmental
Assessment, and being among initiators of establishing the Joint Venture, shares with all other
involved parties the common objective of getting the new Rail Baltica rail connection designed,
constructed, tested, certified, and given into use for the benefit of our people and economies as
part of an important Economic corridor.
We appreciate you sharing this objective. Without this, RB Rail AS would not be able to perform
its tasks in cooperation with the Beneficiaries and Implementing Bodies of the project.
In the next months and years, the main focus of Rail Baltica project implementation is clearly on
getting the design activities on track and starting construction at the selected and agreed sections
and point objects, so as to achieve results of sufficient quality in time, meeting interoperability
standards as well as following the RB design guidelines, and making the best possible use of the
considerable financing that has been committed to the project from both the national budgets and
the European Union budget.
These priorities have repeatedly been discussed within the Rail Baltica International Task Force
as well as with representatives of RB Rail AS management.
Tackling the stringent deadlines we have set in the Intergovernmental Agreement on Rail Baltica
and the Implementing Decision by the European Commission is a challenge to which all three
Baltic states have committed to, the tasks to achieve those have been delegated to RBR and
national implementing bodies. Efforts have to be made to reduce the impact of the current delays
on the ultimate outcome of the project. Ways to improve project delivery must be found, we are
interested to explore those, but without significant loss of energy and time, and without risking the
loss of already committed funding.
For successfully dealing with the priorities of project implementation, all parties involved in the
project need to consolidate efforts and continue cooperation in the ways and manners that will
enable to reach the expected results avoiding further delays. Reconsidering the roles and
Suur-Ameerika 1 / 10122 Tallinn / ESTONIA
Phone: +372 625 6342 / Fax: +372 631 3660 / E-mail:
[email protected] / http://www.mkm.ee
responsibilities of the parties would in this context take the energy and effort that should rather be
dedicated to improving implementation and dealing with activities on the ground. The latter is
inevitable. We all need to deliver results.
This is necessary not only to demonstrate to local, national and international stakeholders our
capability to jointly get the Rail Baltica project implemented. It is also a necessary precondition
for successfully negotiating the next European Union’s Multiannual Financial Framework and
making the best use of the possibilities that it would foresee for completing the Rail Baltica.
The Estonian Ministry of Economy and Communications expects that we can count on all of you
contributing to good cooperation in order to jointly meet these objectives.
With best regards,