Ref. Ares(2019)7215287 - 22/11/2019
Third countries capacity calculation
Legal requirements
The Guideline on Capacity Allocation and Congestion Management (Commission Regulation
(EU) 1222/2015) (CACM) sets out the methods for calculating how much capacity can
market participants use on cross-border lines without endangering system security.
In line with CACM, capacity calculation methods need to be agreed within the Capacity
Calculation Region. This applies also to calculation methods with third countries, as they have
an impact on internal capacities. Ideally, all the TSOs of the Baltic Capacity Calculation
Region (LV, LT, EE, FI, SE, PL) would need to agree (either explicitly or tacitly) on a
common capacity calculation methodology with third countries, and submit the same version
to their NRAs for approval. However, as in practice, Sweden, Poland and Finland are not
affected, only the agreement between the three Baltic States could be sufficient. In case the
TSOs do not agree on a proposal to the NRAs, it is for the Commission to facilitate the
adoption of a methodology (Art. 9(4) CACM). This mainly mandatory methodologies
pursuant to CACM and the respective deadlines defined therein. If the TSOs submit the
request to their respective NRAs and the NRAs do not agree, then ACER takes a decision in
this respect.
Any breach of the provisions regarding capacity calculation methods, such as any unilateral
action not involving all the three Baltic States, entails a breach of the CACM Regulation that
is of direct application. This could lead to legal challenges by any of the parties that have not
been involved in the procedure, by market participants in the Baltic States and by the
Commission (infringement).
Technical solution
Following the discussions regarding the new capacity calculation methodology with third
countries, it was agreed that the way forward will be a common solution agreed by three
Baltic States to be achieved by March/April 2020. Given that the physical realities of
electricity flows in the BRELL Ring, only a technical solution taking into account all
infrastructure in the Baltic States can be considered.
Commercial solution
On top of the technical solution, the three Baltic States agreed to also consider a commercial
layer that would address also political concerns leading to an acceptable solution for the
methodology.
The guiding principles of the commercial layer are as follows:
Trade volumes with Kaliningrad will not be constrained and Kaliningrad’s energy
security will be safeguarded;
Guarantees of origin for electricity can be requested from the Russian traders;
No additional risks for energy security in the Baltic States.
Way forward
The Baltic States at Senior Official level will negotiate and agree on a commercial solution
that takes into account the three principles mentioned above. They will be advised by their
TSOs and NRAs and DG ENER will facilitate discussions and a compromise. In their
proposals and considerations, the Baltic States can take into account the value of current and
historical imports from third countries in terms of capacity utilization and volume. Historical
values of imports from Belarus could be considered for exclusion.
We would like to invite that the Baltic States already exchange any proposals and data
available in due time before the next senior officials’ meeting on 28 November.
Saatja: CACI Simone(ENER) <
[email protected]>
Saadetud: 22.11.2019 11:56
Adressaat: EGLITIS Eriks (Ministry of economics of the republic of
latvia) <
[email protected]>; PURLYS Egidijus (MINISTRY OF ENERGY OF
THE REPUBLIC OF LITHUANIA) <
[email protected]>; PURLYS Egidijus
(MINISTRY OF ENERGY OF THE REPUBLIC OF LITHUANIA) <
[email protected]>; MKM
info <
[email protected]>
Koopia: ILJINA Inga (Permanent Representation of Latvia = Représentation
permanente de la Lettonie) <
[email protected]>; NAVICKAITE Jolanta
(Permanent Representation of Lithuania to the EU)
<
[email protected]>; Reesi-Reena Runnel <Reesi-
[email protected]>; kristiina tammeraid <
[email protected]>;
VAINUTE Sandra (MINISTRY OF ENERGY OF THE REPUBLIC OF LITHUANIA)
<
[email protected]>
Teema: Ares(2019)7215287 - BEMIP synchro SO invitation
Manused: Way forward on the methodlogy for capacity calculation with
third countries for ARES.pdf; Invitation BEMIP HLG synchronisation
SO_28_11_2019(2).pdf
Dear all,
Please see attached, as discussed, the invitation for the BEMIP
Synchronisation Senior Officials’ meeting to take place on 28 November at
15:00 in Brussels. Please also see attached a one-pager description of
the
principles agreed upon so far.
Best regards,
Klaus-Dieter Borchardt
Deputy Director-General
European Commission
Directorate General for Energy
24, Rue (Jean-André) De Mot
Ref. Ares(2019)7215287 - 22/11/2019
EUROPEAN COMMISSION
DIRECTORATE-GENERAL FOR ENERGY
The Deputy Director-General
Brussels,
ENER/KDB/AIC/sc(2019)s7988951
Mr Egidijus Purlys
Vice-minister for energy, Lithuania
Mr Timo Tatar
Deputy Secretary General for energy
Federal Ministry for Economic Affairs and
Communications, Estonia
Mr Ēriks Eglitis
Secretary of State
Ministry of economics, Latvia
Dear Sirs,
I would like to invite you to a meeting of the High-Level Group of the Baltic Energy Market
Interconnection Plan (BEMIP HLG) on the synchronisation project (at senior officials’ level)
taking place on 28 November 2019 between 15.00 and 16.30 in Berlaymont, Rue de la Loi
200, 1049 Bruxelles, room Robert Schuman.
The aim of the meeting is to follow-up on our discussions of 30 October 2019 on
coordinating the way forward regarding relations with third countries before 2025 in the
presence of representatives from the transmission system operators and national regulatory
authorities. Please see attached to this invitation a short non-paper outlining the principles of
the compromise solution as agreed so far.
I would appreciate if you could confirm your participation to the meeting. For your access to
the Berlaymont building, please register your presence as well as the participation of all
accompanying persons (including a representative of the transmission system operator and of
the national regulatory authority) at the following link:
https://ec.europa.eu/eusurvey/runner/BEMIP_HLG_Synchro_officials_28Nov19
Yours sincerely,
Klaus-Dieter BORCHARDT
Commission européenne/Europese Commissie, 1049 Bruxelles/Brussel, BELGIQUE/BELGIË - Tel. +32 22991111
Office: DM24 04/083 - Tel. direct line +32 229-94011