Audit report form v.5
AUDIT OF OPERATION REPORT
Central Baltic INTERREG V A Cross-border Co-operation Programme 2014 – 2020
AUDIT NUMBER: CB-24/2021
Date of final audit report 15/06/2021
Contradictory procedure 07/06/2021
Accounting period 01/07/2020 – 30/06/2021
Progress report No. 4.1 and 212 614.14 EUR, audited 100 %
Audit scope
Progress report No. 5.1 and 60 009.30 EUR, audited 100 %
Elis Kõrvek, Audit Leader, Lead Auditor of II Audit Unit, Financial Control
Department of Ministry of Finance of Estonia Suur-Ameerika 1, 10129 Tallinn,
Estonia
Marten Janno, Audit team member, Auditor of II Audit Unit, Financial Control
Auditor(s) Department of Ministry of Finance of Estonia Suur-Ameerika 1, 10129 Tallinn,
Estonia
Kadi Peets, Audit Supervisor, Head of the II Audit Unit, Financial Control
Department of Ministry of Finance of Estonia Suur-Ameerika 1, 10129 Tallinn,
Estonia
Tallinn City Government
Tallinn Urban Environment and Public Works Department
Audited organisation
Mündi 2, 15197 Tallinn
& contact information
Janne Teder
[email protected], +372 640 4307
Place of the audit Tallinn Urban Environment and Public Works Department
Persons present during the audit Janne Teder
Date of on-the-spot checks 03.05.2021
Achieving healthier water quality in urban small rivers of the
Baltic Sea catchment by restoration of water bodies and
Full project name
preventing of nutrients and hazardous substances inflow from
watersheds
Project Number & Acronym CB716 – HEAWATER
Priority Axis 2. Sustainable use of common resources
SO 2.4 Reduced nutrients, hazardous substances and toxins’ inflows into the
Specific Objective
Baltic Sea
Reporting Period 01/09/2019 – 31/08/2020
Name of the Lead Partner Tallinn City Government
Project duration
01/03/2018 - 28/02/2021
(start and end dates)
Based on the audit work performed we have obtained reasonable assurance that the
AUDIT expenditure declared under the audited operation CB716 – HEAWATER within
CONCLUSION priority axis 2 in the reference year 01/07/2020 – 30/06/2021 is, in most material
aspects, legal and regular.
Page 1
Audit report form v.5
However, the auditor made one major finding with a financial impact in regard to
carrying out public procurements. The summarized list of findings identified during
the audit is presented in the following table and report.
Number
Total Financial Total Financial
of Nature of the finding(s)
Impact Impact ERDF
findings
1 €56.17 €47.41 The lead partner has not carried out the procurement with a
within the audit within the audit reference no 188772 in compliance with the Public Procurement
scope scope Act (Major finding, with financial impact)
Page 2
Audit report form v.5
PART 1 – AUDIT SCOPE
According to Article 127 of Regulation (EU) No 1303/2013 the audit authority is responsible to carry out
audits of operations on the basis of supporting documents constituting the audit trail and verify the legality
and regularity of expenditure declared to the Commission, including the following aspects:
a) that the operation was selected in accordance with the selection criteria for the Operational
Programme, was not physically completed or fully implemented before the beneficiary submitted
the application for funding under the Operational Programme, has been implemented in accordance
with the approval decision and fulfilled any conditions applicable at the time of the audit concerning
its functionality, use, and objectives to be attained;
b) that the expenditure declared to the Commission corresponds to the accounting records and that
the required supporting documentation demonstrates an adequate audit trail;
c) that for expenditure declared to the Commission determined in accordance with Articles 67(1)(b)
and (c) and 109 of Regulation (EU) No 1303/2013 and Article 14(1) of Regulation (EU) No 1304/2013,
outputs and results underpinning payments to the beneficiary have been delivered, participant data
or other records related to outputs and results are consistent with the information submitted to the
Commission and that the required supporting documentation demonstrates an adequate audit trail.
PART 1.1 – LIMITATION OF SCOPE
The conclusions of the audit are based on the analysis of the procedure in place, information and documents
gathered and interviews conducted in the audited bodies as well as the tests performed in the course of the
audit following the checklist for the audit areas.
PART 1.2 – AUDIT METHODOLOGY
The audit is carried out in compliance with internationally accepted auditing standards and the audit
strategy, which is approved by the audit authority and group of auditors representing each Central Baltic
INTERREG VA Programme Member State.
The audit process comprises of three stages:
a) Preparation and planning of the audit
In this stage legal regulations and other documentation, including from the management verification
ex Regulation (EU) No 1299/2013, Article 23(4), needed for familiarising with the selected
operations were collected and analysed. Also, interviews or checklists which were needed for the
planning of the audit, familiarising with the functioning of the system, project files structure, the
objectives and the status of implementation of the operations, the risk encountered during the
implementation as well as those inherent to the type of operations.
b) Fieldwork
At this stage a whole range of interviews with responsible staff were conducted, documents were
gathered and testing was performed. In order to attain the audit objectives during the audit we
tested all applicable audit areas. We performed the audit using the checklists for the several audit
areas which enabled us to verify the requirements laid down in European and national legislation.
The assurance about the achievement of the project’s objectives was attained via documentation
uploaded to the programme’s information system (eMS), e-mail conversation with the project
partner and photos of the project outputs.
Page 3
Audit report form v.5
c) Reporting
This stage encompassed activities related to the preparation of the Draft Report and the
contradictory procedure where auditee has been granted 10 working days to reflect on the audit
report, the inclusion of their replies and comments and the submission of the Final Report.
Provide the actual schedule of the contradictory procedure as following
Preliminary report: 24.05.2021
Final report: 15.06.2021
PART 2 – FINANCIAL DATA OF OPERATION
Financial data of audited partner must be listed
PART 4.1 – BUDGET (EUR)
Audited Partners Granted in % Payments % Payments %
approved budget total for the included in the included in
partner payment claim the payment
4.1 claim 5.1
ERDF €230,094.18 84.4% €179,446.33 84.4% €50,647.85 84.4%
Public funding €42,529.26 15.6% €33,167.81 15.6% €7,827.30 15.6%
(total)
Private funding € 0.00 € 0.00 € 0.00
Income € 0.00 € 0.00 € 0.00
TOTAL PARTNER €272,623.44 100% €212,614.14 100% € 60,009.30 100%
BUDGET
Audited expenditure (according to the Sample, report 4.1)1
Total amount audited Ineligible detected in
Budget Line (combining milestones) audit scope
1. Staff costs €51,553.31 € 0.00
2. Office and administration €7,732.99 € 0.00
3. Travel and accommodation €848.72 €56.17
4. External expertise and services € 0.00 € 0.00
5. Equipment € 0.00 € 0.00
6. Infrastructure and works €152,479.12 € 0.00
Total amount audited €212,614.14 € 0.00
Audited expenditure (according to the Sample, report 5.1)2
Total amount audited Ineligible
Budget Line (combining milestones)
1. Staff costs €52,182.00 € 0.00
2. Office and administration €7,827.30 € 0.00
3. Travel and accommodation € 0.00 € 0.00
4. External expertise and services €0.00 € 0.00
5. Equipment €0.00 € 0.00
6. Infrastructure and works € 0.00 € 0.00
Total amount audited €60,009.30 € 0.00
1
Costs outside the sample were not audited
2
Costs outside the sample were not audited
Page 4
Audit report form v.5
PART 3 – FINDINGS AND RECOMMENDATIONS
PART 3.1 GENERAL
During the audit we identify and document audit findings. We categorise these findings by reference to the
level of importance. The categories which we use to classify our findings are as follows:
Findings which have a financial impact above EUR 250 (ERDF) or any other high-
Major
risk deficiencies.
Findings for which action should be taken to ensure full compliance but have a
Minor limited financial impact (below EUR 250 (ERDF)), no financial consequences or
no high-risk character.
All audit findings are reported in the final audit report, even if the Member States participating in the
Programme may decide that neither the lead beneficiary nor the Programme's MA is obliged to recover an
amount unduly paid which does not exceed EUR 250, per operation and accounting year, not including
interest, in contribution from the Funds and the EMFF, as all the irregular amounts detected are to be taken
into account for the calculation of the annual Total Error Rate of the Programme.
PART 3.2 FINDINGS AND RECOMMENDATIONS PER BUDGET LINE
In this paragraph the findings and recommendations per audit area are included.
E. Procurement procedures
Audit Finding No. 1 - Tallinn City Government has not carried out the procurement with a reference
no 188772 in compliance with the Public Procurement Act. Ineligible costs € 56.17 within the audit
scope.
According to the Central Baltic Programme manual point 3.7 public procurements shall be done according
to national rules or following EU rules, depending on the thresholds.
The lead partner Tallinn City Government has carried out an open procurement with a reference no
188772 “Travel agency services (Reisikorraldusteenused)” electronically in the e-procurement register
(published on 30.06.2017). Service contracts were awarded on 06.11.2017 to tenderers CWT Estonia AS,
AS Wris and AS Baltic Tours with a total contract estimated amount 1 000 000.00 EUR according to the
contract award notice published in TED (2017/S 223-464297).
Auditors have identified a noncompliance with the Estonian Public Procurement Act:
1. § 3 subsection 3: all persons whose place of residence or seat is in Estonia, in another Member State
of the European Union, in another contracting party to the EEA Agreement or in a state that has joined
the Government Procurement Agreement (GPA) of the WTO, must be treated equally and without
discrimination by the contracting authority and the contracting authority must make certain that all
restrictions and criteria established for the persons are proportional, relevant and justified in relation
to the purpose of the public procurement;
Page 5
Audit report form v.5
2. § 39 subsection 1: the contracting authority will verify whether the financial and economic standing
and the technical and professional ability of a tenderer or candidate comply with the award criteria
specified in the contract notice.
The award criteria must be sufficient for proving the tenderer’s or candidate’s ability to duly perform the
public contract and relevant and proportional to the nature, quantity and purpose of the supplies, services
or public works that constitute the object of the public contract.
As a result of the audit procedures, the auditors identified the following risks:
1. The procurement contract notice contains restrictive selection criteria: III.2.3) technical and
professional ability of a tenderer: Tenderer must be a member of the International Air Transport
Association for at least 3 years from the date the contract notice has been published in the state
procurement register. Tenderer must submit a copy of IATA certificate.
The contracting authority must make certain that the selection criteria established in the contract notice
are proportional, relevant, non-discriminatory and reasoned in relation to the purpose of the public
procurement, must not distort the competition by excluding companies, who have been operating in the
market less than 3 years and can prove their ability to fulfill the contact according to the requirements.
Thus, the requirement to be a member of the International Air Transport Association for at least 3 years is
not proportional, distorts the competition and does not show the ability of the tenderer to fulfill the
contract.
2. Significant modification of contract ‒ contract duration has been extended and initial value of the
contract exceeded by 57%.
Service contracts were awarded on 06.11.2017 to CWT Estonia AS, AS Wris and AS Baltic Tours for € 1
million as stated in the contract award notice following an open procedure. According to the contract point
10.1, contracts with CWT Estonia AS, AS Wris and AS Baltic Tours entered into force 01.01.2018 and were
valid 24 months. On 12th of December 2019 amendments to the initial contracts with AS Baltic Tours and
CWT Estonia AS, on 10th of December 2019 with AS Wris were concluded to extend the contract duration
until 14th of February 2020 in accordance with Public Procurement Act §123 (1) 1). According to the
Procurement Register the final value of the contracts is € 1 761 792.02 (excl. VAT).
A modification of a contract during its term shall be considered to be substantial, where it renders the
contract materially different in character from the one initially concluded. (Article 72(4) of Directive
2014/24/EU)
Auditors are in the opinion that the contract modifications do not comply with the requirements in §123
(1) 1) of the Public Procurement Act . Auditors find that modifications leading to an increase of the contract
price of 57% are substantial, caused by insufficient planning by the contracting authority and could have
been avoided by timely preparation of a new tender.
CONCLUSION AND RECOMMENDATIONS:
In auditors opinion the abovementioned requirements are restrictive, thus not ensuring equal access for
tenderers and have the effect of creating unjustified obstacles to the opening up of public procurement to
competition. Contracting authority made a significant modification to contracts with CWT Estonia AS, AS
Page 6
Audit report form v.5
Wris and AS Baltic Tours, contract duration has been extended and initial value of the contracts exceeded
by 57%.
The above findings will result in a financial correction of 25% of the certified expenditure due to a
substantial contract modification according to point 23 (2) of the Guidance on financial corrections
(C(2019) 3452 final dated 14/05/2019).
1) Recommendation to the auditee:
It is recommended to the beneficiary to make a refund in amount of the ERDF co-financing € 47.41 (84.4%)
and to deduct the ineligible co-financing € 8.76 (15.6%) from the project’s overall eligible expenditure.
2) Recommendation to the First Level Control
It is recommended to pay attention to the travel and accommodation costs related to procurement with
a reference no 188772 in this project and in other projects where Tallinn City Government is one of the
partners. Those costs may be affected by the same error. If similar cases are found, the costs should be
deducted where possible and the Managing Authority should be notified.
3) Recommendation to the Managing Authority
It is recommended to begin a procedure to recover the ineligible amounts. Concerning the amount in audit
scope, the auditor recommends to reclaim the ineligible ERDF funding of € 47.41 and deduct the ineligible
co-financing of € 8.76 from the partner’s budget.
The Managing Authority should identify all projects containing ineligible costs resulting from the
procurement with a reference no 188772 and apply financial correction of 25% to the certified
expenditure.
Auditee response:
HEAWATER travel procurement was made independently from the Tallinn City Government open
procurement with reference no 188772 “Travel agency services (Reisikorraldusteenused)”. HEAWTATER
travel offers were based on Tallinn City Procurement Rules, valid from 10.10.2017 until 31.12.2020
(Tallinna linna hankekord). For travels to 2nd Partners Meeting to Söderhamn (3.-4.10.18) and 3rd
Partners Meeting to Turku 27.-28.03.19 a bid-at-three procedure was applied (proof documents added to
the e-mail).
Concerning the 4th meeting in Helsinki 2.-3.10.2019 only one offer was asked for traver service: firstly,
Tallinn City Procurement Rules allow it: § 5 (5) “Riigihanke eest vastutav isik edastab kirjaliku kutse e-
posti teel võimaluse korral vähemalt kolmele pakkujale, kontrollides enne nende vastavust õigusaktides
sätestatud erinõuetele, kui seda eeldab ostumenetluse esemest lähtuv tegevus; and secondly, the
programme rules require that a bid-at-three procedure must be applied in case of tenders of 5 000€
and above.
It was decided to ask for only one offer as:
1. the total travel cost was under 999,99 €;
2. travelling cost to Helsinki with the Ferry was open to see everyone when
visiting https://www.tallink.ee/vali-reis (the dates and time were fixed for the project).
3. accommodations was organized by project partner SYKE as their institute had a contract with the
GLO Hostel, which provided us much lower accommodation cost in the seminar place (proof added
to the e-mail). Accommodation was not included in the tender, it included only ferry and insurance
cost.
Page 7
Audit report form v.5
The auditee does not agree with the conclusions in the draft audit report and and confirms that the
project was implemented following all the requirements laid down in European and national legislation
and project manuals.
First Level Control response:
FLC will make a corrections and deducts 25% from costs of the travel and accommodation costs related
to procurement with reference no 188772 in this and in other projects where Tallinn City Government is
one of the partners.
In the future, FLC will pay more attention to the travel and accommodation costs related to procurement
and also will look into framework contracts more detail and analyse the extent of the value.
Based on the travel services reflected in Project reports, FLC does not usually have by the assertion time
of submitted costs enough information to assess the purchase of travel services used at the entire
procurement Tallinn City Government. Therefore, it is often not possible for FLC to check the
fulfillment/exceeding of the public procurement framework contract.
Managing Authority response:
The MA will only provide general comments in this case. According to the MA understanding, the
procurement has been correctly carried out at the time of the check. If later developments change this,
and an audit recommendation is made, the MA will take this for information and make any necessary
corrective steps.
Final conclusion by the auditors:
Auditors thank the auditee for the additional information provided via email on 02.06.2021 regarding
travel costs in audited progress reports no 4.1 and 5.1. The auditors would like to point out that the travel
offers were asked from the same companies CWT Estonia AS, AS Wris and AS Baltic Tours with whom the
beneficiary has concluded the framework contracts with procurement reference no 188772 “Travel
agency services (Reisikorraldusteenused)”. The procurement procedure for travel agency services was
conducted by Tallinn City Office and as referred in the tender documents, the resulting contract is
mandatory and binding to all departments. Auditee’s response as project HEAWATER travel procurement
has been made independently from the Tallinn City Government open procurement with reference no
188772 “Travel agency services (Reisikorraldusteenused)” would in auditors’ opinion refer to a non-
compliance with the public procurement rules. Therefore, corrections should be applied.
As the finding may impact other projects where Tallinn City Government is one of the partners, the FLC
should pay attention to the travel and accommodation costs of Tallinn City Government. The costs should
be deducted where possible and the Managing Authority should be notified.
PART 4 - FOLLOW-UP
This audit report is compiled for use of the Audit Authority of the Central Baltic INTERREG VA 2014-2020
Programme and will be used to draw conclusions about the functioning of the Management and Control
Systems of the above-mentioned Programme. Information in the report will be disclosed to relevant parties
involved of management of the EU funds, including Commission services.
Parties responsible of audit finding follow-up:
1. Findings with Financial impact – The Audit Authority (AA) will inform the Managing Authority (MA)
to take necessary actions to correct shortcomings in the system;
Page 8
Audit report form v.5
a. Deductions will be made by the MA;
b. Confirmation of deductions will be made by the AA;
c. If needed follow-up audit will be done by Group of Auditor (GoA) members.
2. Findings without the Financial impact
a. The MA will be informed and evaluation will be done if further actions are needed;
b. Confirmation of actions will be followed-up by the AA and if needed by the GoA members.
Upon request from the MA the Auditee is responsible to implement the recommendations and deliver the
proof to the MA.
Audit Manager: Elis Kõrvek
Signed electronically
Audit Supervisor: Kadi Peets
Signed electronically
Page 9
Hr Mihhail Kõlvart
Tallinna Linnavalitsus Meie 16.06.2021 nr 10-5/4619-1
[email protected]
Auditi lõpparuande edastamine
Austatud härra Kõlvart
Edastame Teile Kesk-Läänemere INTERREG V-A programmi projekti nr CB716
„HEAWATER“ projektiauditi lõpparuande nr CB-24/2021.
Täname Teid meeldiva koostöö ja osutatud abi eest.
Lugupidamisega
(allkirjastatud digitaalselt)
Kaur Siruli
Finantskontrolli osakonna juhataja
Lisa: Auditi lõpparuanne (9 lehel)
Sama:
Pr Imbi Uusjärv, Riigi Tugiteenuste Keskus (
[email protected])
Pr Merike Niitepõld, Managing Authority / The Regional Council of Southwest Finland
(
[email protected])
Teadmiseks:
Pr Mairi Uusen, Riigi Tugiteenuste Keskus (
[email protected])
Hr Urmo Merila, Riigi Tugiteenuste Keskus (
[email protected])
Elis Kõrvek 611 3197
[email protected]
Suur-Ameerika 1 / 10122 Tallinn / 611 3558 /
[email protected] / www.rahandusministeerium.ee
registrikood 70000272