Eesti Geoloogiateenistus · 28. detsember 2023
Sisu (failidest)
Annex I to Report of Factual Findings on expenditures declared under an Interim/Final
Report
Listing of procedures performed
The ‘result’ column has three different options: ‘C’, ‘E’ and ‘N.A.’:
‘C’ stands for ‘confirmed’ and means that the auditor can confirm the ‘standard factual finding’
and, therefore, there is no exception to be reported.
‘E’ stands for ‘exception’ and means that the Auditor carried out the procedures but cannot
confirm the ‘standard factual finding’, or that the Auditor was not able to carry out a specific
procedure (e.g. because it was impossible to reconcile key information or data were
unavailable). In either case, such case must be reported and described in the Report of factual
findings with a reference to the expenditure number as indicated in the List of expenditure.
The exception may refer to any expenditure under the specific budget heading or to the
individual expenditure item. This implies that the expenditure is regarded as non-eligible.
‘N.A.’ stands for ‘not applicable’ and means that the Finding did not have to be examined by
the Auditor and the related Procedure(s) did not have to be carried out. The reasons of the
non-application of a certain Finding must be obvious i.e. 1) if no cost was declared under a
certain category then the related Finding(s) and Procedure(s) are not applicable; 2) if the
condition set to apply certain Procedure(s) are not met then the related Finding(s) and
Procedure(s) are not applicable.
Fund operated by:
1
Procedures Standard factual findings Result
(C, E,
N.A.)
General statements applicable to all project expenditures
Reference / Criteria
The issues to be verified versus all project expenditures:
Exclusion of ineligible costs
Adequate accounting system in place
Bank account
Net revenues
Irregularities
The Auditor:
1) It is ensured that ineligible
verified that no ineligible costs were declared costs are excluded according to the
under any of the BHs: EEA and Norway Grants Fund for
Regional Cooperation rules.
o Reviewed the costs in terms of
ineligibility
o In case of costs with dates of
invoicing/payments belonging to previous
reporting periods: verified if these costs were
declared only once, and only in the currently
verified report/s. 2) All costs are declared only
o Reviewed if the costs were charged in once, i.e. not already reported twice
line with the Project Partner’s accounting policy, in the project.
were correctly identified, allocated to the
proper activity, budget heading, entered in the
accounting system (traceable to underlying
documents such as purchase orders, invoices
3) The costs were charged in
and accounting),
line with the Project Partner’s
o Verified if separate accounting accounting policy and were
system/code is used for all the project costs and adequately supported.
is consistent with the presented accounting
policy,
o Verified if all project-related
expenditures are identifiable in the accounting 4) The project partner uses, for
system, the accounting purposes, a separate
accounting system and/or an
o Verified if net revenue is reported and if
adequate accounting code and all
so the net-revenue is properly calculated and
project-related expenditures are
deducted in the reporting period.
identifiable.
o Verified if net-revenue generated in the
project is properly calculated, deducted in the
Fund operated by:
2
Procedures Standard factual findings Result
(C, E,
N.A.)
reporting period and recorded in the accounting 5) The dedicated bank account (LP)
system. is used only for the project-
The following costs shall not be considered eligible: related payments
o Interest on debt, debt service charges and
late payment charges;
o Charges for financial transactions and other 6) The reported net revenue has
purely financial costs, except costs specifically been properly calculated and
required by the applicable law and costs of financial deducted from the total eligible
services imposed by the project contract; expenditure and recorded in the
o Costs related to purchase of land or real accounting system.
estate;
o Provisions for losses or potential future
liabilities; 7) There was no evidence of
o Exchange rate losses; irregularities found during the
o Recoverable VAT; project’s verification.
o Costs that are covered by other sources;
o Fines, penalties and costs of litigation,
except where litigation is an integral and necessary
component for achieving the outcomes of the
project; and
o Excessive or reckless expenditure.
Staff costs (BH1)
Reference/Criteria
The cost of staff assigned to the Project, either full- or part- time, comprising actual salaries plus
social security contributions and other statutory costs included in the remuneration, provided that
these costs are in line with each Project Partner’s usual policy on remuneration. Staff can either
be already employed by the Project Partner entity or staff specifically employed for the Project.
The Auditor: 8) There were no discrepancies
between the personnel costs as
o reviewed the contractual changes for
presented in the Report and the
staff working in the project, and the method for
costs recalculated by the
calculating staff costs,
Auditor.
o recalculated all staff costs based on
national legislation, employment contract or
equivalent and partner’s usual policy on
remuneration.
9) The claimed Staff costs are
Staff costs must be calculated individually for each adequate in quality and/or
staff member charged to the project.
quantity to the realised
In case of contractual changes for staff working in the
deliverables of the project.
project, the method for calculating staff costs may
also be adapted to the changed conditions.
Fund operated by:
3
Procedures Standard factual findings Result
(C, E,
N.A.)
The Auditor: 10) The incurred expenditures were
appropriately assigned to the
o Verified whether only permanent staff
budget heading - Staff Cost.
cost is calculated under this budget item; (any
extra services provided on short-term basis by
persons (external experts) are to be excluded
from BH1).
11) Project partner’s staff was
The Auditor:
remunerated in accordance with
o Reviewed the Project Partner’s usual the Project Partner’s usual
policies and practices regarding payroll matters policy.
(e.g. salary policy, overtime policy, variable
pay),.
o Verified whether unjustified ad-hoc
salary increases or bonuses are excluded from
the eligible expenditures.
Unjustified ad-hoc salary increases or bonuses for
project purposes are not eligible.
Further procedures if there is part time Staff
12) There were no discrepancies
employed between the part time personnel
The Auditor: costs as presented in the Report
and the costs recalculated by the
o Recalculated salaries of part time staff Auditor.
depending on the method applied by the project
partner
o Ensured that the method has been
applied in consistent manner.
Staff employed part-time in the project is dedicating
only a part of its total working time to the project,
such costs have to be calculated according to either
of the following methods:
o Part-time with a fixed percentage of time per
month dedicated to the project;
o Part-time with a flexible number of
hours/days worked per month on the project.
1) A fixed percentage of the gross employment cost,
in line with a fixed percentage of time worked on the
project, with no obligation to establish a separate
working time registration system (time-sheets);
In such case, the employment / work contract has to
specify the tasks and the percentage of the time
Fund operated by:
4
Procedures Standard factual findings Result
(C, E,
N.A.)
worked per month for the project. Alternatively, a
specific document can be issued by the project
partner for each employee setting out the percentage
of time to be worked on the project (e.g. Job
description);
Or
2) A flexible share of the gross employment cost, in
line with the number of hours/days spent on the
project, based on a time registration system (time-
sheets).
Such costs shall be calculated multiplying the
hourly/daily rate by the number of hours/days
actually worked on the project (based on time-
sheets).
The hourly/daily rate (if not specified in the
employment / work contract) to be applied for
calculation is determined by dividing the monthly
gross employment costs by the monthly working time
fixed in the employment contract (or equivalent
contract) expressed in hours/days.
Further procedures if there is Staff employed on
13) For Staff employed on contract
contract which is equivalent to employment contract which is equivalent to
in accordance with the national legislation employment contract, costs and
work conditions are not different
The Auditor: from those for personnel
o Reviewed the terms of “equivalent performing similar tasks under
contracts” of every staff employed in this way an employment contract with
(especially the cost, contract duration, work the project partner and the
description, place of work, ownership of the result of the work carried out
results and reporting obligations to the Project belongs to the project partner.
partner);
o Compared the terms of “equivalent
contracts” to those of the employed under
employment contract;
o Compared the costs of “equivalent
contracts” to those of the employed under
employment contract;
o Verified whether result of the work
carried out belongs to the project partner.
Costs for natural persons working under the contract
which are equivalent to employment contract are
eligible if:
Fund operated by:
5
Procedures Standard factual findings Result
(C, E,
N.A.)
(a) the person works under conditions similar
to those of an employee (in particular regarding the
way the work is organised and supervised, the tasks
that are performed and the premises where they
are performed);
(b) the result of the work carried out belongs to
the project partner and
(c) the costs are not different from those for
personnel performing similar tasks under an
employment contract with the project partner.
Costs arising from a contract stipulated with a natural
person that results to be not equivalent to an
employment contract according to
national/institutional rules, belong to the
‘subcontracting cost’ budget heading and have to
comply with all provisions applicable to that budget
heading, including the respect of procurement rules.
Voluntary work (BH1a)
Reference/Criteria
The voluntary work is allowed for non-governmental organisations only. Voluntary work is the
work carried out for the benefit of the project, with a specific purpose, within limited time period,
on the basis of the volunteer’s own will, and without receiving any financial compensation for it.
Voluntary work cannot be part of the paid assignments, and it cannot be assigned to any person
receiving remuneration from any of the project partners.
The Auditor examined agreements between the 14) The volunteer work was
volunteers and the project partner, signed time- appropriately calculated and
sheets and calculation method of the monetary assigned to the budget heading
value of voluntary work.
15) Volunteers did not receive
Voluntary work cannot be part of the paid remuneration from any project
assignments of the volunteers and should not be partner or any other
assigned to employees receiving remuneration from organisation within the project.
any project partner or any other organisation for the
task (or tasks) to be considered volunteering under 16) The volunteer’s contract
this project. specified a detailed role within
Voluntary work should have a specific purpose, the project and the tasks that
contribute to the content of the project and should were directly linked to project
be limited to a certain time period. The results of the only.
Fund operated by:
6
Procedures Standard factual findings Result
(C, E,
N.A.)
unpaid work should be of added value to the project 17) The work was properly
and contribute to the successful delivery of the documented by signed
project outputs. agreement between the
Voluntary work must be properly documented by volunteer and the project
signed agreement between the volunteer and the partner), signed time-sheets and
project partner (duration and conditions of unpaid calculation method of the
work shall be specified here), signed time-sheets and monetary value of voluntary
calculation method of the monetary value of work.
voluntary work.
18) Calculation of voluntary work
Calculation of voluntary work shall be objectively
was objectively valued by the
valued by the project partner and the hourly rates
shall be similar but under no circumstances higher project partner and the hourly
than the remuneration for equivalent work carried rates were not higher than the
out in the region/country. remuneration for equivalent
work carried out in the
Project beneficiaries CANNOT be volunteers.
region/country.
19) Project beneficiaries were not
engaged within the project as
volunteers.
Travel expenses and related subsistence allowances (BH2)
Reference/Criteria
Travel expenses and related subsistence allowances of staff taking part in the Project, provided
that these costs are in line with each Project Partner’s usual practices on travel. Any
accommodation allowances must not exceed the per diem rates published on the following
website http://ec.europa.eu/europeaid/funding/about-calls-tender/procedures-and-practical-
guide-prag/diems_en in force at the moment of travel. As a general principle, the most cost-
efficient means of transport shall be used.
The Auditor: 20) Costs were incurred, approved
reviewed the Project Partner’s usual practices or and reimbursed in line with
policy regarding travelling. Project Partner’s usual
In the absence of written policy, the Project Partner
practise/policy for travels and/or
provides the evidence of its practise outside the national legislation
examined project costs to enable the Auditor to
compare the travel costs charged with this practise. 21) The incurred expenditures have
been appropriately calculated
Travel expenses and related subsistence allowances
and assigned to the budget
of staff taking part in the project, must be in line with
heading - Travel expenses and
Project Partner’s usual practices on travel/national
legislation related subsistence allowances.
Fund operated by:
7
Procedures Standard factual findings Result
(C, E,
N.A.)
The Auditor verified that travel costs: 22) The supporting documents were
consistent with each other
o are justified,
regarding subject of the trip,
o correctly identified and calculated, dates, duration and reconciled
o allocated to the activity (e.g. directly with time records and
linked to the activity, related only to travels of accounting. Costs partially
the BH1 and BH1a staff) and budget heading covered by third parties have
been deducted from eligible
by reviewing relevant supporting documents expenditures.
such as minutes of meetings, workshops or
conferences, their registration in the correct 23) Travel and accommodation costs
project account, their consistency with time only relate to missions necessary
records or with the dates/duration of the for project implementation
workshop/conference/activity. carried out by the permanent
staff (BH1) and volunteers
Travel and accommodation costs must be clearly (BH1a).
linked to the project and be essential for its effective
implementation. They must be justified by activities 24) Any accommodation and daily
carried out within the project. As a general principle, allowances do not exceed the
the most cost-efficient mean of transport shall be per diem rates published by the
used (e.g. using economy class instead of business or EC.
first class unless travels are done by train. If travels
are by car, a reimbursement, based on the mileage 25) The most cost-efficient means of
calculation sheet or invoice (in case of car rental), transport was used or less-
based on national/internal rules as applicable to the efficient transport was duly
entity. justified.
Daily subsistence allowances cannot exceed the 26) Presented costs of travels relate
official EU per diem rates. For reference, use per diem
solely to travels performed by
rates published on
http://ec.europa.eu/europeaid/funding/about-calls-
the staff presented under BH1
tender/procedures-and-practical-guide- and BH1a by the Project Partner
prag/diems_en at the moment of travel. (costs of external
experts/consultants/service
Travel costs related to individuals other than staff
providers are excluded).
directly employed by Project Partners (such as
consultants, experts, external service providers),
must be included under “subcontracting costs” (BH6).
Consumables and supplies (BH3)
Reference/Criteria
The costs of consumables and supplies are eligible, provided that they are identifiable and assigned
to the Project;
Fund operated by:
8
Procedures Standard factual findings Result
(C, E,
N.A.)
The Auditor verified that: 27) Only nondurable goods were
o Purchased goods were used for the purchased under this budget
implementation of the project activities; heading.
o The costs were allocated to the proper
28) Purchased goods and supplies
activity, budget heading;
were properly tied to the
o Procurement rules were observed and
implementation of project
ensured best value for money, key elements to
activities.
appreciate the respect of this principle are the
award of the contract to the bid offering best 29) The incurred expenditures were
price-quality ratio, under conditions of appropriately assigned to the
transparency and equal treatment. budget heading - Cost of
consumables and supplies.
The Auditor also confirmed that all goods and
30) Consumables/supplies are
services were necessary for the project (it may
clearly linked to the project and
involve e.g. interviews, review of contracts and
are essential for its effective
the outputs of the services) and cannot be
implementation.
concerned indirect.
31) Procurement rules, principles
If project activities need to be supported by and guides were followed. The
additional purchases of consumables and supplies, purchases were made in
then such a purpose should be classified under accordance with the principle of
“consumables and supplies” budget heading (BH3). best value for money.
Supplies – general purpose consumable items which
commonly have a shorter life span in use than
equipment and machines;
Consumables (also known as consumable goods,
nondurable goods, or soft goods) are goods that, are
capable of being consumed, that may be destroyed,
dissipated, wasted or spent. Consumables are in
contrast to durable goods.
Further procedures if ‘consumables and supplies’ 32) The share allocated to the
used only partially by the project project is charged based on a
The Auditor: transparent method set in place
(In case of consumables and
o reviewed the method of share allocation supplies used only partially by
to the project the project).
o recalculated the actual allocation to the
project
Equipment costs (BH4)
Reference/Criteria
Fund operated by:
9
Procedures Standard factual findings Result
(C, E,
N.A.)
Cost of equipment provided that it is depreciated in accordance with generally accepted
accounting principles applicable to the Project Partner and generally accepted for items of the
same kind. Only the portion of the depreciation corresponding to the duration of the Project and
the rate of actual use for the purposes of the Project may be eligible. In case the Project Partner
determines that the equipment is an integral and necessary component for achieving the
outcomes of the Project, the entire purchase price may exceptionally be eligible;
The Lead Partner shall ensure that:
the equipment is kept in the ownership of the relevant Project Partner for a period of at
least 5 years following the completion of the Project and continues to be used for the
benefit of the Project’s overall objective for the same period;
the equipment is kept properly insured by the relevant Project Partner against losses
such as fire, theft or other normally insurable incidents both during the implementation
of the Project and for at least 5 years after the completion of the Project;
the relevant Project Partner sets aside appropriate resources for the maintenance of the
equipment for at least 5 years after the completion of the Project.
The Auditor for every asset, which costs are 33) There was a link between the
claimed in the project, verified the existence, Project Contract and the asset
audit trail in the booking records, including charged to the project.
depreciation method and procurement process.
34) Equipment has not already been
financed by other Donors and/or
The equipment must:
has not already been
o be essential for the project; depreciated.
o be not financed from any other financial 35) The incurred expenditures were
instrument (e.g. EU, national, international);
appropriately assigned to the
o not be fully depreciated; budget heading - Equipment
o not be included under any other budget costs.
line; 36) Procurement rules, principles
o not be purchased, rented or leased from and guides were followed and
another project partner; equipment has not been
o be purchased respecting the relevant purchased, rented or leased
procurement procedures. from another project partner..
The purchases were made in
As a general principle, for all project equipment
accordance with the principle of
(purchased before or during the project lifetime) only
best value for money.
depreciation costs shall be allocated to the project.
Cost of equipment shall be depreciated in accordance 37) The reported expenditures are
with generally accepted accounting principles traceable to the accounting
applicable to the project partner and generally records and the underlying
accepted for items of the same kind. The portion of
documents.
Fund operated by:
10
Procedures Standard factual findings Result
(C, E,
N.A.)
the depreciation corresponding to the duration of the 38) The depreciation method used is
project and the rate of actual use for the purposes of in line with generally accepted
the project may be eligible. accounting principles applicable
to the project partner and
generally accepted for items of
the same kind.
39) The reported expenditures
corresponded to the duration of
the project and the rate of actual
use for the purposes of the
project.
40) Equipment is available/
physically exists.
For equipment rented or leased the auditor 41) The rental/leasing costs are
verified, that rental or leasing costs are presented only for the
presented only for the respective period. respective period
The auditor verified that equipment is leased on
the operational leasing basis. 42) According to the leasing/renting
Leasing is eligible only for the respective period of the contract ownership of the
project. Ownership cannot be transferred at the end equipment is not transferred at
of the leasing period from the lessor to the lessee. the end of the leasing period to
Therefore, operational leasing is eligible, while the Project Partner.
financial leasing is not.
Project contract requirements costs (BH5)
Reference/Criteria
Costs arising directly from the requirements imposed by the Project Contract (for instance: cost of
report by an independent auditor, cost of financial guarantees etc.)
The Auditor checked whether:
43) The incurred expenditures were
o financial costs were required, appropriately assigned to the
budget heading - Costs arising
o other costs attributed to the BH5 were
directly from the requirements
required by the project contract
imposed by the Project Contract.
This budget heading covers the cost required by
project contract as indicated in project contract:
44) Financial guarantee cost
complied with the agreement
with financial institution.
Fund operated by:
11
Procedures Standard factual findings Result
(C, E,
N.A.)
o Financial costs - limited to the financial
guarantee (it is required in cases where advance
45) Procurement rules, principles
payments are foreseen), and banking costs and guides were followed. The
concerning the dedicated bank account (cf. Art. 7.1 of purchases were made in
SC and Art. 31.2 of GC) that are specifically required accordance with the principle of
by the applicable law and represent financial services best value for money.
imposed by the project contract (e.g. bank charges
for opening and administering the account,
transnational financial transaction charges)
o Audit cost (if required by the project
contract)- costs related to the verification of each
interim/final report (i.e. proof of expenditure) by
each project partner which shall take the form of a
report by an independent auditor or by a competent
and independent public officer.
o Other costs required by the project contract
- all remaining costs not covered in other budget
headings description and required by the project
contract (civil liability policy, if only for the project
purposes).
Subcontracting costs (BH6)
Reference/Criteria
Costs entailed by other contracts awarded by a Project Partner for the purposes of carrying out
the Project provided that the award complies with the Article 18 of General Conditions
(Procurement, Annex I to the Project Contract).
The Auditor verified if:
46) The subcontracting costs were
o the use of subcontractors was foreseen foreseen in the project contract
in the project contract,
o supporting documents on the selection
and award procedure were followed,
The Auditor checked whether:
o the subcontracts were not awarded to
other Project Partner in the consortium, 47) The subcontracts were not
o there were signed agreements between awarded to other Project
the Project Partner and the subcontractor, Partners of the consortium.
48) All reported expenditures are
based on the written agreements
Fund operated by:
12
Procedures Standard factual findings Result
(C, E,
N.A.)
o there was evidence that the services between the Project Partner and
were provided by subcontractor, as stipulated in the subcontractor.
the contract,
o procurement rules were applied and
49) The incurred expenditures have
ensured best value for money (key elements to
been appropriately assigned to
appreciate the respect of this principle are the
the budget heading - External
award of the contract to the bid offering best
expertise and services costs.
price-quality ratio, under conditions of
transparency and equal treatment). 50) External expertise and services
Subcontracting costs shall be paid based on contracts are clearly linked to the project
or other written agreements of equivalent probative and are essential for its effective
value and against invoices or requests for implementation.
reimbursement to external service providers.
Subcontracting costs shall be connected to certain
51) The share allocated to the project
project tasks or activities that cannot be carried out
is plausible, i.e. calculated
by the project partners themselves (mainly to bring in
according to a fair, equitable and
more expertise or capacity) and are therefore
outsourced to external service providers.
verifiable method. (In case of
experts or services that are NOT
The awarding procedure should comply with exclusively used for the project).
procurement rules and avoid any conflict of interest.
Project partners shall always follow the strictest
procurement rules applicable to them.
‘Subcontracting cost’ budget heading covers (and is
limited to) the price paid for subcontracts and related
taxes. Such price may include travel costs of external
52) Procurement rules, principles
service providers and experts. Their participation in
project meetings and events needs to be justified and and guides were followed. The
contributing to the project content and activities. purchases were made in
The activities to be implemented and the estimated accordance with the principle of
cost for each subcontract must be set out in the best value for money.
Project Description.
Characteristics of subcontracting:
Based on business conditions (this means that
the subcontractor charges a price, which usually
includes a profit);
Subcontractor is not hierarchically subordinate
to the project partner;
The project partner remains responsible for all its
rights and obligations under the Project Contract,
including the tasks carried out by a subcontractor;
Fund operated by:
13
Procedures Standard factual findings Result
(C, E,
N.A.)
Subcontractor has no rights or obligations
53) The provision of services to the
towards the Fund Operator or the other project
partners (it has no contractual relation with them). target group was reasonable,
justified and reflect the
Project Partners are not allowed to contract each expected contribution to the
other to carry out project activities.
implementation of specific
project activities and to the
overall success of the project.
Further procedure if cost related to provision of
services to the target group are reported
54) The provision of services to the
target group is properly
The auditor verified if the amount of support is documented, all necessary
reasonable, justified and reflects the expected agreements/contracts are duly
contribution to the implementation of specific signed with the beneficiaries of
project activities and to the overall success of the such support, timesheets and
project other proofs are provided.
The auditor checked if provision of services is
based on formal agreements between the
project partner and the end beneficiary and is
properly documented.
Here the costs for the provision of services to the
target group are covered. Such services might take
form of a subsistence allowances, scholarships,
internships or other forms as specified in the project
description.
All the forms of such services should be within the
context of a specific project idea and within the scope
of planned activities (e.g. clearly defined training /
education scheme), with the aim to create the
measurable outputs in line with the outcomes of the
project.
Indirect Cost (BH7)
Reference/Criteria
A flat rate of 15% of the total eligible staff costs of the Project is eligible under the Budget Heading
7- Indirect Cost.
The indirect costs represent the general administrative costs which cannot be attributed to the
direct eligible expenditure of the Project.
Indirect costs do not need to be supported by the proof of expenditure.
Fund operated by:
14
Procedures Standard factual findings Result
(C, E,
N.A.)
The auditor verified, if no indirect costs were
55) No indirect costs were presented
presented for reimbursement under any direct
for reimbursement under any
Budget Heading (BH1-BH6).
direct Budget Headings ( BH1-
A flat rate of 15% of the total eligible staff costs BH6).
(including voluntary work) of the project is eligible
under indirect costs, representing the general
administrative costs which can be regarded as
chargeable to the project.
Indirect costs shall normally include all administrative
expenditure of the project which cannot be directly
attributed to the project. For example:
o Office rent;
o Insurance and taxes related to the buildings
where the staff is located and to the equipment of
the office (e.g. fire, theft insurances);
o Utilities (e.g. electricity, heating, water);
o General professional services provided
inside the Project Partner organisation;
o Maintenance, cleaning and repairs;
o Security;
o IT systems (operating /administrative IT
services of general nature, linked to the
implementation of the project);
o Communication (e.g. telephone, fax,
internet, postal services, business cards);
No proofs of expenditure are to be verified under this
BH.
Fund operated by:
15
Annex II to Report of Factual Findings on expenditures declared under an Interim/Final
Report
List of expenditures
{EGREG table format}
Fund operated by:
16
REPORT OF FACTUAL FINDINGS ON EXPENDITURES DECLARED
UNDER AN INTERIM/FINAL REPORT
<<The Report should be printed on auditor’s letterhead>>
<<Fill in the fields in color with relevant data. Fields in brackets highlighted in grey should be removed
from the final Report if not applicable. In case when you are required to choose one from proposed
Options, remove other from the Report>>
To
[Name of contact person(s)],
[Position]
[The project partner name ]
[Address]
[dd-mm-yyyy]
Dear [Name of contact person(s)],
As agreed under the terms of reference dated [dd-mm-yyyy]
with: [insert name of the Project Partner],
we
[name of the auditor] (‘the Auditor’),
established at
[full address/city/state/province/country],
represented by
[name and function of an authorised representative],
have carried out the procedures agreed with you regarding the expenditures declared in the
Interim/Final Report(s) covering period [dd-mm-yyyy] to [dd-mm-yyyy]
submitted by the [Project Partner]
concerning the Project Contract [insert Project Contract reference: number, title],
and hereby provide our Report of Factual Findings (‘the Report’) using the compulsory report format
agreed with you.
Our engagement was carried out in accordance with the Terms of Reference (‘the ToR’) appended to
this Report. The Report includes the agreed-upon procedures (‘the Procedures’) carried out and the
standard factual findings examined.
STANDARDS AND ETHICS
Our engagement was undertaken in accordance with:
the Terms of Reference appended to this Report and:
Fund operated by:
2
the International Standard on Related Services (‘ISRS’) 4400 (Revised) Engagements to perform
Agreed upon Procedures regarding Financial Information as promulgated by the IFAC;
the IFAC Code of Ethics for Professional Accountants (developed and issued by IFAC's
International Ethics Standards Board for Accountants, which establishes fundamental ethical
principles for Auditors with regard to integrity, objectivity, independence, professional
competence and due care, confidentiality, professional behaviour and technical standards.
Although ISRS 4400 (Revised) provides that independence is not a requirement for agreed-
upon procedures engagements, the FO requires that the Auditor is independent from the
Project Partners and complies with the independence requirements of the IFAC Code of Ethics
for Professional Accountants.
PROCEDURES PERFORMED
As requested, we have only performed the procedures listed in the model Report for this engagement
and we have reported our factual findings on those procedures in the Annex I to the Report ("Listing
of procedures performed").
These procedures have been determined solely by the FO and the procedures were performed solely
to assist the FO in evaluating whether the expenditure claimed by the Project Partner in the
accompanying Interim/Final Financial Part of the Report(s) is eligible in accordance with the terms and
conditions of the Project Contract.
Because the procedures performed by us did not constitute either an audit or a review carried out in
accordance with International Standards on Auditing or International Standards on Review
Engagements, we do not express any assurance on the accompanying Financial Report.
Had we performed additional procedures or had we performed an audit or review of the financial
statements of the Project Partner in accordance with International Standards on Auditing, other
matters might have come to our attention that would have been reported to you.
SOURCES OF INFORMATION
The Report sets out information provided to us by you in response to specific questions or as obtained
and extracted from Project Partner’s accounts and records.
FACTUAL FINDINGS
On the basis of the results of procedures, we found:
Total eligible project costs which are the subject of this expenditure verification amount to
EUR <xxxxxx> [Fill in the total incurred eligible project costs (direct+indirect) of the Project
Partner, applicable to the interim/final report(s) subject to verification within this Report. The
value of total incurred project costs per partner is visible in financial part of interim/final report,
section 2. Overview tables.]
[Choose the appropriate option (other to be removed from the Report)]
[Option A] The expenditures indicated in Annex II to the Report (‘the List of expenditures’) met the
following criteria:
Fund operated by:
3
they were incurred between the first and final dates of eligibility of the Project, unless
otherwise specified in the Special Conditions;
they were related to the subject of the Project as described in Annex II and they were indicated
in the budget of the Project;
they were proportionate and necessary for the implementation of the Project;
they were used for the sole purpose of achieving the objective(s) of the Project and its
expected outcome(s), in a manner consistent with the principles of economy, efficiency and
effectiveness;
they were identifiable and verifiable, in particular through being recorded in the accounting
records of the Project Partners and determined according to the applicable accounting
standards and generally accepted accounting principles; and
they complied with the requirements of applicable tax and social legislation,
they were supported by receipted invoices, or alternatively by accounting documents of
equivalent probative value,
they were paid and the subject matter delivered (in case of goods) or performed (in case of
services and works). Depreciation of equipment have been incurred when it was recorded on
the accounts of the Project Partner.
[Option B] The expenditures indicated in Annex 2 to the Report (‘the List of expenditures’) met the
following criteria, with the execeptions listed below:
they were incurred between the first and final dates of eligibility of the Project, unless
otherwise specified in the Special Conditions;
they were related to the subject of the Project as described in Annex II and they were indicated
in the budget of the Project;
they were proportionate and necessary for the implementation of the Project;
they were used for the sole purpose of achieving the objective(s) of the Project and its
expected outcome(s), in a manner consistent with the principles of economy, efficiency and
effectiveness;
they were identifiable and verifiable, in particular through being recorded in the accounting
records of the Project Partners and determined according to the applicable accounting
standards and generally accepted accounting principles; and
they complied with the requirements of applicable tax and social legislation,
they were supported by receipted invoices, or alternatively by accounting documents of
equivalent probative value,
they were paid and the subject matter delivered (in case of goods) or performed (in case of
services and works). Depreciation of equipment have been incurred when it was recorded on
the accounts of the Project Partner.
With the following exceptions:
[Describe here any case of ‘exception’. List any non-eligible project costs and add any information on
the cause and possible consequences of each exception, if known Include the corresponding amount.]
[Example:
Fund operated by:
4
[The Project Partner was unable to substantiate the Expenditure presented in annex 2 under position
[no XXX] with document number [document own number] in the amount of [amount of ineligible cost]
reported under budget heading no […] because [description]
Finding number [number of Standard factual findings] was not fulfilled because [description of the
differences].
Total non-eligible direct project costs amount to EUR [amount] [fill in the total amount of costs found
to be non-eligible]
FURTHER REMARKS
In addition to reporting on the results of the specific procedures carried out, the Auditor would like to
make the following general remarks:
[Example (to be removed from the Report):
1. Regarding Finding number 7, 9) we regard that there is a link between work and content of the
project the conditions for additional remuneration because …
2. In order to be able to confirm the Finding number 15 we carried out the following additional
procedures: ….]
USE OF THIS REPORT
This report is prepared solely for confidential use and for the purpose of submission to the FO. This
report may not be relied upon for any other purpose, nor may it be distributed to any other parties.
The FO may disclose this Report to others who have regulatory rights of access to it, in particular the
FMO, the EFTA Board of Auditors, as well as the Auditor General of Norway.
This Report relates only to the Interim/Final Report(s) specified above and does not extend to any of
your financial statements.
There was no conflict of interests1 in establishing this Report.
Yours sincerely
(…)
Auditors’ signature [person or firm or both, as appropriate and in accordance with company policy]
Name of Auditor signing [person or firm or both, as appropriate.Registration Number if applicable of
the Auditor]
1 A conflict of interest arises when the Auditor's objectivity to issue the Report is compromised in fact or in appearance when the
Auditor for instance:
- was involved in the preparation of the Interim/Final Report;
- stands to benefit directly should the expenditures be accepted;
- has a close relationship with any person representing the Project Partner;
- is a director, trustee or partner of the Project Partner or Lead Partner; or
- is in any other situation that compromises his or her independence or to issue the Report impartially.
Fund operated by:
5
Auditors’ address [office having responsibility for the engagement]
Date of signature <dd-mm-yyyy> [date when the final report is signed]
Fund operated by:
6
TERMS OF REFERENCE FOR REPORT OF FACTUAL FINDINGS
ON EXPENDITURES DECLARED UNDER AN INTERIM/FINAL
REPORT
This document sets out the Terms of Reference (‘ToR’) under which
Eesti Geoloogiateenistus (‘the Project Partner’) registry code 77000387, with registered address at
F.R. Kreutzwaldi tn 5, Rakvere, represented by the Director Sirli Sipp Kulli
agrees to engage
Audit & Consult OÜ (‘the Auditor’) registry code 11505111, with registered address at Telliskivi 60/1,
Tallinn, represented by the member of the Management Board Kairi Luigelaht-Teder
to produce an independent Report of Factual Findings (‘the Report’) concerning the eligible
expenditures declared within Final Report covering period from 01.07.2023 to 31.12.2023 by the
Eesti Geoloogiateenistus for the EEA and Norway Grants Fund for Regional Cooperation under the
Project Contract no 2018-1-0137 EU WATERRES “EU-intergrated management system of cross-
border groundwater resources and anthropogenic hazards” 01.09.2020-31.12.2023 (‘the Project
Contract’).
General information
The Project Contract has been concluded under the EEA and Norway Grants Fund for Regional
Cooperation between the Lead Partner representing the Project Consortium and the Fund Operator
(‘FO’).
Where in these ToR, the FO is mentioned, this refers to ECORYS Poland, which has signed the Project
Contract with the Lead Partner, and JCP Italy. The EEA and Norway Grants is not a party to this
agreement.
The Report is composed of the following:
• The ToR to be signed by the Project Partner and the Auditor,
• The Report to be issued on the Auditor’s letterhead, dated, stamped and signed by the
Auditor which includes the agreed-upon procedures (‘the Procedures’) to be performed by
the Auditor, and the standard factual findings (‘the Findings’) to be confirmed by the Auditor.
Subject of the engagement
The subject of this engagement is the Final Report related to the Project Contract for the period
covering 01.07.2023 to 31.12.2023.
Responsibilities of the Parties to the Engagement
The Project Partner accepts that the ability of the Auditor to perform the procedures required by this
engagement effectively depends upon the Project Partner, providing full and free access to project
staff, its accounting and bookkeeping system, underlying accounts and records, as well as any
relevant information.
The Project Partner:
• must draw up the financial part of the Final Report for the expenditures incurred under the
Project Contract in compliance with the obligations under the Project Contract. The financial
part of the report must be drawn up according to the Project Partner’s accounting and book-
keeping system and the underlying accounts and records,
• must provide the financial part of the Final Report to the Auditor including all supporting
documents in originals,
Fund operated by:
• is responsible and liable for the accuracy of the financial part of the Final Report,
• is responsible for the completeness and accuracy of the information provided to enable the
Auditor to carry out the Procedures,
• accepts that the Auditor cannot carry out the Procedures unless it is given full access to the
project partner’s staff and accounting as well as any other relevant information, records and
documentation.
The Auditor is responsible for performing the agreed-upon procedures as specified in these ToR.
"Auditor" refers to:
• the audit firm1 or the person, contracted for performing this engagement and for submitting
a report of factual findings to the Project Partner and meeting at least one of the following
conditions
- is a member of a national accounting or auditing body or institution which in turn is a
member of the International Federation of Accountants (‘IFAC’);
- is a member of a national accounting or auditing body or institution. Although this
organisation is not member of the IFAC, the Auditor holds valid internationally
recognised certification, and commits him/herself to undertake this engagement in
accordance with the IFAC standards and ethics;
- is registered as a statutory auditor in the public register of a public oversight body in an
EU member state in accordance with the principles of public oversight set out in
Directive 2006/43/EC of the European Parliament and of the Council (this applies to
auditors and audit firms based in an EU member state);
- is registered as a statutory auditor in the public register of a public oversight body in a
third country and this register is subject to principles of public oversight as set out in the
legislation of the country concerned (this applies to auditors and audit firms based in a
third country).
• a competent and independent public officer recognised by the relevant national
authorities as having a budget and financial control capacity over the entity incurring the
costs and who has not been involved in the preparation of the financial statements,
certifying that expenditure declared in an Interim/Final Report has been incurred in
accordance with the provisions of the Project Contract, national law and relevant
national accounting principles.
Standards and Ethics
The Auditor shall undertake this engagement in accordance with:
• the International Standard on Related Services (‘ISRS’) 4400 (Revised) Engagements to
perform Agreed upon Procedures regarding Financial Information as promulgated by the
IFAC (Estonia);
• the IFAC Code of Ethics for Professional Accountants (developed and issued by IFAC's
International Ethics Standards Board for Accountants) (Estonia), which establishes
fundamental ethical principles for Auditors with regard to integrity, objectivity,
independence, professional competence and due care, confidentiality, professional
behaviour and technical standards. Although ISRS 4400 (Revised) provides that
1 The Leader of the engagement team, signing the Report must meet at least one of the above conditions.
Fund operated by:
independence is not a requirement for agreed-upon procedures engagements, the FO
requires that the Auditor is independent from the Project Partners and complies with the
independence requirements of the IFAC Code of Ethics for Professional Accountants.
Procedures, Evidence and Documentation
The scope of verification covers 100% of expenditures declared under a Final Report covering period
from 01.07.2023 to 31.12.2023.
The Auditor should plan the work so that the procedures can be effectively performed.
The Auditor performs the procedures listed in Annex 1 to the Report ("Listing of specific procedures
to be performed"). The Auditor is not liable for the appropriateness of these procedures for the
purpose of the engagement.
The evidence to be used for performing the procedures is all the information — financial and not
financial related but relevant to the project implementation — which makes it possible to examine
the expenditure claimed by the Project Partner in the Final Report. The Auditor uses the evidence
obtained from these procedures as the basis for the report of factual findings. The Auditor
documents matters which are important in providing evidence to support the Report, and evidence
that the work was carried out in accordance with ISRS 4400 (Revised) and these ToR.
The report on this expenditure verification should describe the purpose, the agreed-upon procedures
and the factual findings of the engagement in sufficient detail to enable the Project Partner and the
FO to understand the nature and extent of the procedures performed by the Auditor and the factual
findings reported by the Auditor.
As this engagement is not an assurance engagement the Auditor does not provide an audit opinion
and expresses no assurance. The FO assesses for itself the factual findings reported by the Auditor
and draws its own conclusions from these factual findings.
Reporting
The Report must be written in English. The use of the model Report integral to this ToR is
compulsory.
The FO, the Financial Mechanism Office (‘FMO’), the EFTA Board of Auditors, as well as the Auditor
General of Norway have the right to audit any work that is carried out under the action and for which
costs are declared from Norway Grants Fund for Regional Cooperation budget. This includes work
related to this engagement. Within the period up to 5 years starting from the date of the Final
Payment, The Auditor must provide all necessary explanations and access to all working papers (e.g.
recalculation of hourly rates, verification of the time declared for the action) related to this
assignment if the FO, the FMO, the EFTA Board of Auditors, as well as the Auditor General of Norway
request them.
If the Auditor believes, based on the collected evidence that there is high probability of the fraud in
the examined project, he/she must report this in writing directly to the FO.
Timing
The Report should be provided by 30.03.2024.
Fee
Fund operated by:
The fee for this engagement shall be 875 EUR plus value added tax. The amount payable for the
engagement shall be paid by the Project Partner within 7 calendar days after the date of submitting
the invoice by the Auditor. The fee for the engagement shall be deemed as covering all the expenses
incurred by the Auditor.
According to the estimation of the Auditor, the engagement is expected to take 20 hours.
Other Terms
Parties’ Liability
The Project Partner shall be liable for the violation of obligations provided for in the ToR, unless it is
caused by unforeseeable circumstances or circumstances independent of the activities of the Parties
(Force majeure).
The Auditor shall be liable for the Project Partner for direct proprietary damage wrongfully caused by
the professional activities of the certified auditor. The maximum liability limit is a tenfold Contract
fee. The maximum limit is not applied upon damage caused by gross negligence or deliberate
violation. The Auditor shall not bear any liability if it is not culpable of causing the damage, among
other things, if the damage arises from misleading information presented during the audit by the
Project Partner either orally or in writing or by the Project Partner’s failure to present information.
Confidentiality
Documentation prepared by the Auditor in connection with the engagement and/or documents
prepared by the Project Partner and submitted to the Auditor as well as other materials and/or
information presented to the Auditor during the engagement is deemed as being working papers
(incl. electronic working papers) that belong to the Auditor. Working papers are confidential and the
Auditor shall store them in accordance with the requirements established by the legislation of the
Republic of Estonia and internal principles and regulations established in the Auditor. The working
papers may be disclosed in the cases prescribed by legislation.
The Project Partner may not disclose the documents of the Auditor prepared during the engagement
and/or submit them to third parties without the prior written consent of the Auditor, except in cases
prescribed by the legislation of the Republic of Estonia.
The confidentiality requirement is not applied to information that is publicly available or to the
mutual relations between the Auditor and the Project Partner the existence of which may be
disclosed by the Auditor to clients, potential clients and other third parties.
The Auditor is required to keep the confidentiality of information and documents obtained during
the performance of the professional activities. The obligation to keep the professional secret
specified in the foregoing sentence is not limited in time and is also effective after the Auditor
terminates its professional activities.
There is no obligation to keep confidentiality, if the Auditor has the Project Partner’s written permit
to disclose the circumstances or if the Auditor is required to disclose the information and documents
due to legislation.
The Auditor shall retain all the copyrights and other intellectual property rights to anything created,
developed or designed prior to or during the audit, including, but not limited to the systems,
methods, software, know-how and working documentation. The Auditor shall retain all the
copyrights and other intellectual property rights to the reports, written advice and other materials
submitted by the Auditor to the Project Partner.
Fund operated by:
The Auditor is only required to use the information obtained by it within the framework of this ToR
for the purpose of performing the engagement and may not disclose it to other parties.
Money laundering and terrorist financing prevention
The Auditor is required to establish the identity of the Project Partner and the existence of passive
legal capacity, establish and verify the identity and right of representation of the members of the
management board of the Project Partner and identify the beneficial owner.
At the request of the Auditor, the Project Partner is required to submit the necessary document and
provide information relevant for application of diligence measures arising from the Money
Laundering and Terrorist Financing Prevention Act, incl. information about the transactions
concluded and funds used by the Project Partner that must be in compliance with the nature and
scope of the Project Partner’s economic activities as well as information about the change in
beneficial owners.
Expiry and termination of the ToR
The Parties may only cancel the ToR with good reason. The Project Partner may initiate the
cancellation of the agreement when Project Partner becomes aware of the information about the
Auditor that could damage the reputation of the Project Partner.
The Parties must immediately notify the Auditors Activities Oversight Board of the cancellation of the
ToR through the information system of the Auditors Activities register, providing their explanations
regarding the reasons for cancellation of the ToR.
Cancelling the ToR, the Project Partner is immediately required to pay the Auditor for all the work
agreed in the Contract performed prior to the cancellation. The foregoing sentence shall not be
applied, if the cancellation of the Contract is caused due to the suspension or expiry of the activity
licence of the Auditor.
The ToR shall expire after the conforming performance of the Auditor.
Settlement of disputes
The Parties shall perform and interpret the ToR in accordance with the legislation effective in the
Republic of Estonia. The disagreements, disputes and claims arising from the ToR that the Parties fail
to solve by way of an agreement are settled in Harju County Court.
For the Project Partner: For the Auditor:
/signed digitally/ /signed digitally/
Sirli Sipp Kulli Kairi Luigelaht-Teder
Director Member of management board
Appendix: (model) Report of factual findings on expenditures declared under an Interim/Final
Report.
Fund operated by: