Application Form Part A
EUROPEAN COMMISSION CONNECTING EUROPE FACILITY
ENERGY SECTOR
A1
Proposal TENtec nr. DRAFT (26431304)
Call: CEF-Energy-2015-2
General information on the project of common interest
Commission Delegated Regulation 1391/2013 Project No. 8.1.2.2
Title of the PCI Paldiski LNG
Energy sector Gas
Priority corridor Baltic Energy Market Interconnection Plan in gas
PCI description New onshore LNG terminal near Paldiski (including a
reloading facility for bunkering or small scale distribution)
with an annual send-out capacity of 2.5 BCM/year. The
LNG storage capacity is of about 180.000 – 320.000 CM
LNG and the maximum ship size of 165.000 CM LNG (or
any standard LNG tanker capable to pass through the
Danish Straits).
Location of the Project of Common Interest
Member State(s) EE
Region(s) EE00 Eesti
3rd country
(1) NUTS 2 nomenclature will be used for the regions.
Proposal type
Please select the proposal type:
Work
Study
GENERAL INFORMATION ON THE PROPOSED ACTION
Name of the Action Building and commissioning of Paldiski LNG terminal
Start date of the Action 01/07/2015 End date of the Action 01/01/2020
Summary of the Action (up to 2000 characters). Please describe the main scope, goals and objectives of the action,
the main needs addressed by the action and the technical data of the action to be funded.
Page 1
The PCI (Paldiski LNG 8.1.2.2.) consists of one action: the building and commissioning of Paldiski LNG terminal. The
aim of the Action is to build and commission the East Baltic Sea regional LNG import and regasification terminal. The
project location is on the south coast of the Gulf of Finland, in Estonia. The port location on the north-eastern side of
the Pakri peninsula has been chosen for its favourable ice conditions, easy navigational path, low impact on the
environment and a large available safety radius. Since the project is planned on the BalticConnector (PCI 8.1.1.)
land-fall, connectivity to grid is relatively inexpensive.
Balti Gaas OÜ intends to build a Baltic regional terminal with 160 000 m3 storage tank capacity to be commissioned
in the beginning of 2019 in order to provide a supply option for the Baltic States. The terminal would be large enough
to assist with supply to the Finnish market through BalticConnector. It is designed to service both gas grid customers
and off-grid customers, since pursuant to market analysis it is clear that the off-grid market will prove instrumental in
this region. In connection to that, truck and LNGC loading facilities are developed to support off-grid markets as well
as feeder terminals along the coast of the Baltic Sea. The terminal design flow for re-gasification is planned at around
4 MCM/day. The project is developed with the possibility of further enlargement subject to market conditions.
The main needs addressed are ending the energy isolation of gas for Baltic States and together with Baltic
Connector also for Finland, helping to implement a unified regional gas-market and ensuring security of supply by
providing an alternative supply route for gas and allowing the storage of emergency reserves for interested Member
States and TSO’s.
Page 2
Application Form Part A
EUROPEAN COMMISSION CONNECTING EUROPE FACILITY
ENERGY SECTOR
A2.1
Proposal TENtec nr. DRAFT (26431304) Applicant nr. 1
APPLICANT
Applicant's legal name Balti Gaas OÜ
Administrative Data
Legal address
Street name Roseni Number 13
Town / city Tallinn
Postal code 10111
Country Republic of Estonia
Legal Status Of The Applicant
Applicant's legal status Private undertaking/body in the EU
According to article 43 (1) of the Commission Delegated Regulation (EU) No 1268/2012 (on the rules of application of
Regulation (EU, Euratom) No 966/2012 of the European Parliament and of the Council on the financial rules
applicable to the general budget of the Union), international organisations are: (a) international public sector
organisations set up by intergovernmental agreements, and specialised agencies set up by such organisations; (b) the
International Committee of the Red Cross (ICRC);(c) the International Federation of National Red Cross and Red
Crescent Societies; (d) other non-profit organisations assimilated to international organisations by a Commission
decision.
Does the applicant have the legal personality in accordance with the applicable national legislation?
YES
NO
If NO, then applicants must provide the statutes of the applicant (or the relevant abstract) as a supporting document to
the application form to demonstrate that the representative of the applicant has the capacity to undertake legal
obligations on its behalf.
Page 3
Application Form Part A
EUROPEAN COMMISSION CONNECTING EUROPE FACILITY
ENERGY SECTOR
A2.2
Proposal TENtec nr. DRAFT (26431304) Applicant nr. 1
APPLICANT
Applicant's legal name Balti Gaas OÜ
Contact Points
Person in charge (the person who will be contacted by the Commission in the first instance)
Family name Piikmann First name(s) Karmo
Function Analyst
Is the address different from the legal address (of section A2.1)? NO
Street name Roseni Number 13
Town / city Tallinn
Postal code 10111
Country Republic of Estonia
Phone +372 55 631 545
Fax -
Email
[email protected]
Representative authorized to sign this application
Family name Hääl First name(s) Marti
Function Member of the board
Is the address different from the legal address (of section A2.1)? NO
Street name Roseni Number 13
Town / city Tallinn
Postal code 10111
Country Republic of Estonia
Phone +372 661 7731
Fax -
Email
[email protected]
Date
Stamp + signature
Page 4
Application Form Part A
EUROPEAN COMMISSION CONNECTING EUROPE FACILITY
ENERGY SECTOR
A2.3
Proposal TENtec nr. DRAFT (26431304) Applicant nr. 1
APPLICANT
Applicant's legal name Balti Gaas OÜ
IF THE APPLICANT IS A THIRD COUNTRY, AN INTERNATIONAL ORGANISATION, A JOINT UNDERTAKING OR
A PUBLIC OR PRIVATE UNDERTAKING/BODY ESTABLISHED IN THE EU, OR AN ENTITY ESTABLISHED IN A
THIRD COUNTRY, THE MINISTRY OF THE EU MEMBER STATE CONCERNED BY THE PCI, PLEASE FILL IN
THE SECTION BELOW ON THE MINISTRY OF THE EU MEMBER STATE APPROVING THIS PROPOSAL
Ministry's legal name Ministry of Economic Affairs and Communication
Administrative data
Legal address
Street name Harju Number 11
Town / city Tallinn
Postal code 15072
Country Republic of Estonia
Representative authorized to sign this proposal
Family name First name(s)
Function
Is the address different from the legal address? YES/NO NO
Street name Harju Number 11
Town / city Tallinn
Postal code 15072
Country Republic of Estonia
Phone
Fax
Email
Date
Stamp(*) + signature
(*) Stamp of the competent Ministry.
Page 5
Application Form Part A
EUROPEAN COMMISSION CONNECTING EUROPE FACILITY
ENERGY SECTOR
A2.4
Proposal TENtec nr. DRAFT (26431304) Applicant nr. 1
APPLICANT
Applicant's legal name Balti Gaas OÜ
If the applicant wishes to designate any affiliated entities to be involved in the implementation of the proposed Action,
the following information should be completed:
Page 6
Application Form Part A
EUROPEAN COMMISSION CONNECTING EUROPE FACILITY
ENERGY SECTOR
A3.1
Proposal TENtec nr. 26431304
INFORMATION ABOUT THE ACTION REQUESTING GRANTS UNDER CEF-ENERGY
LOCATION OF THE PROPOSED ACTION
Member States(s) Estonia
Region(s)
Third Country(ies)
(1) NUTS 2 nomenclature will be used for the regions.
ACTIVITIES OF THE PROPOSED ACTION
Activity Activity name Activity description Start date End date Milestone(s)
number
1 Applying for a The project needs a public grant, to be 01/07/2015 14/10/2015 1
public grant financially viable and for that an application in
the Connecting Europe Facility, 2015 second
call for proposals in the energy sector will be
submitted.
2 The signing of As the project needs financing also by 01/10/2015 31/01/2016 1
the loan commercial lenders, then it is crucial to sign a
agreement loan agreement with commercial bank(s) for
the terminal project as well as an agreement
for bridge financing for the public grant.
3 The The objective of this activity is to find the most 03/12/2015 18/03/2016 2
procurement suitable EPC partners, which conform to the
for EPCs set parameters in the compiled EPC tendering
packages. The construction and due to that
also EPC will be divided into three parts: Tank
and process part, Jetty and offshore part and
Non-process part.
4 Construction of In the construction phase, the developer will 12/04/2016 13/06/2019 3
the terminal actively communicate with the EPC partners
together with and monitor their progress. The successful
monitoring cooperation and precise monitoring will be of
key importance for the project to be
commissioned as scheduled.
5 Construction of As the off-shore part has a shorter schedule 13/06/2016 12/12/2018 3
the off-shore for construction and a separate permitting
part and jetty timeline, it is scheduled to start later. The
expected construction time is two years and it
should finish the same time as the on-shore
part.
6 The start of the The different parts of the terminal are given 13/03/2019 30/06/2019 3, 4
commissioning over to the commissioning partner from the
constructing partners and the testing of the
terminal begins. Also, the teaching of the staff
of the terminal operator will begin.
Page 7
7 Ordering of the For the successful commissioning, all of the 02/01/2019 31/12/2019 4
first LNG infrastructure must be tested and the staff well
shipment trained. For the purpose of commissioning, it
is really important to receive the first shipment
of LNG and to test the different functions
needed, for the terminal to operate normally.
8 Finalising the Concurrently to the ordering of the first LNG 01/07/2019 31/12/2019 4
commissioning shipment, all of the needed procedures will be
implemented in the terminal and all of the
required permits will be applied for. The staff
of the terminal operator is well trained and
ready for everyday operations.
MILESTONES OF THE PROPOSED ACTION
Milestone Milestone name Milestone description Expected Means of verification
number date
1 Final Investment Decision The next critical milestone 11/02/2016 The public grant financing is
in the development of secured, the final commitment of
Paldiski LNG terminal is commercial banks is received and
the securing of financing the equity investments are
and the Final Investment guaranteed
Decision (FID). As the
project is not
commercially viable
without a public grant, the
most important part for
FID is the awarding of
public grant. The public
grant is also the key
ingredient in securing the
other sources of
financing. Both the
commercial lenders as
well as the main
shareholder of Balti Gaas
OÜ as the equity capital
provider, have set the
public funding in the
extent to secure
commercial viability as
one of their preconditions
for financing the project.
The milestone will be
achieved after the public
grant is awarded to the
project and also the
commercial lender(s) and
equity investor(s) have
submitted their
commitment for providing
the capital needed for
FID.
2 Procurement of EPC This is the first step after 18/03/2016 Signed EPC contracts
FID, where the EPC
tenders will be carried
through. The EPC will be
divided into three different
EPC tenders:
•Tank and Process Part
•Jetty and Offshore Part
•Non- Process Part
All procurement of EPC
tenders will be carried out
simultaneously. The
milestone will be reached,
if all of the EPC contracts
are signed and time
schedules are in place.
Page 8
3 Completion of The construction phase is 13/06/2019 All of the structures have been
construction divided into three constructed and available for testing
simultaneously running and commissioning
areas:
•Construction of the tank
and process part;
•Construction of Jetty and
Offshore part
•Construction of non-
process part
The construction phase
can be considered
completed in case all of
the object are finished
and available for testing.
4 Commissioning The last milestone is the 31/12/2019 The terminal has received the first
full commissioning of the shipment of LNG, all of the functions
terminal. For achieving and equipment has been tested and
this milestone, the the personnel has been trained
construction phase must
be finished, all of the
relevant coaching for the
different staff involved
should be carried out and
a testing should be
conducted, where the full
cycle of LNG handling
should be involved.
Page 9
Application Form Part A
EUROPEAN COMMISSION CONNECTING EUROPE FACILITY
ENERGY SECTOR
A4.1
Proposal TENtec nr. DRAFT (26431304)
Financial information on the project of common interest
SOURCES OF FINANCING Financial Contribution (in euros)
Applicant 60648000
EIB loan 0
Other loans 136374000
State budget(s) 0
Regional/local budgets(s) 0
Other EU funds (e.g. ESIF, EEPR, TEN-E, CEF, EIPA, 0
IPA, etc.)
Contribution from CBCA (*) 0
Other sources 0
CEF-E financing requested 146969000
Total 343991000
(*) Please indicate the contribution from CBCA to be received by the respective applicant(s).
For multi-beneficiary actions, please split the sources of financing by applicant.
All amounts must be in euros.
Exchange rate used for preparing the applications
Please list all the Actions related to the Project of Common Interest co-financed by the EU (e.g. under CEF, ESIF,
TEN-E, EEPR, EIPA, IPA, etc.), including the "Amount granted (in euros)" and "Grant Agreement Number" or
"Decision Number" where available:
Action Name Amount granted (in euros) Grant Agreement/Decision Number
Building and commissioning of 0 DecisionNr
Paldiski LNG terminal
Page 10
Application Form Part A
EUROPEAN COMMISSION CONNECTING EUROPE FACILITY
ENERGY SECTOR
A4.2
Proposal TENtec nr. DRAFT (26431304)
Financial information on the action requesting grants under CEF
SOURCES OF FINANCING Financial Contribution (in euros)(*)
Applicant 58446000
EIB loan 0
Other loans 136374000
State budget(s) 0
Regional/local budgets(s) 0
Other EU funds (e.g. ESIF, EEPR, TEN-E, CEF, EIPA, 0
IPA, etc.)
Contribution from CBCA (**) 0
Other sources 0
CEF-E financing requested 146969000
Total 341789000
(*) Contribution to eligible costs only.
(**) Please indicate only contribution from CBCA expected from entities other than the applicant(s).
For multi-beneficiary actions, please split the sources of financing by applicant.
All amounts must be in euros.
Indicative breakdown of estimated eligible costs of the proposed action by activity
Activities 2015 2016 2017 2018 2019 2020 Total eligible
costs
1.Direct costs
1 Applying for 0 50000 0 0 0 0 50000
a public grant
2 The signing 0 2000000 0 0 0 0 2000000
of the loan
agreement
0 5744000 0 0 0 0 5744000
3 The
procurement
for EPCs
0 93827000 103365000 100315000 0 0 297507000
4
Construction
of the
terminal
together with
monitoring
0 0 21994000 10997000 0 0 32991000
5
Construction
of the off-
shore part
and jetty
6 The start of 0 0 0 1997000 0 0 1997000
the
commissionin
g
Page 11
7 Ordering of 0 0 0 1000000 0 0 1000000
the first LNG
shipment
8 Finalising 0 0 0 500000 0 0 500000
the
commissionin
g
Total eligible 0 101621000 125359000 114809000 0 0 341789000
costs
Page 12
Hr Kristen Michal EV majandusminister Tallinn 1 7 .09 .2015 Hr minister, lubage pöörduda seoses Paldiski LNG terminali projektiga. 14.10.2013 kinnitas Euroopa Komisjon üleeuroopalise tähtsusega energiataristu ühishuviprojektide nimekirja, kus määratleti kla strina : Kiili-Paldiski (50km, DN700, 55bar), Paldiski- Inkoo (80km, DN500, 80bar) ja Inkoo-Siuntio (20km, DN500, 80bar) gaasitoru koos vastavate kompressorjaamadega merealuse osa mõlemas otsas („Balticconnector“) ning üks järgmistest LNG regionaalse terminali projektidest, kas Finngulf LNG ( Gasum projekt Inkoos ), Paldiski LNG (Alexela projekt Paldiskis), Tallinn LNG ( Vopaki projekt Muugal) või Latvian LNG ( Latvjas Gaze projekt Riias). Paldiski LNG terminali projekt on läbinud üldplaneeringu, keskkonnamõjude hindamise ja detailplaneeringu etapid koos selle edukalt lõppenud kohtuliku kontrolliga . K ehtestatud planeeringute kohaselt on võimalik terminal soovitud asukohta rajada. Rahvusvahelise konkursi võitnud T ractebel Engineering GDF SUEZ -iga koostöös on lõp p enud eel proje kteerimine ( FEED ) ja ettevalmistused rahvusvahelise ehituskonkursi (EPC) läbiviimiseks. Ehitusloa ja vee erikasutusloa menetlused on lõppjärgus ja ootavad lõplikku investeerimisotsust. Ei ole kahtlust, et eelviidatud kla stris on Paldiski LNG projekt kõige küpsem ja edu konkureerivate projektide ees on ajaliselt mõõdetav aastates. Samas lõpliku investeerimisotsuse üheks olulisimaks eelduseks nii arendajale kui ka finantseerimisest huvitatud pankadele on lõplik selgus, kas ja mis ulatuses riigiabi (siseriiklikud meetmed regioonis, CEF või mingi muu programm) Läänemere / Soome lahe regioonis LNG imporditerminalile osaks saab . Ei koorma käesolevat avaldust argumentatsiooniga , milliseid vaba turu moonutusi ja selle tagajärjel otsese i d kahju si d riigiabi otsustamine peale Paldiski LNG terminali valmimist tekitab. Vajadusel oleme meelsasti valmis seda selgitama. Tulenevalt eeltoodust oleme seisukohal, et lähtudes vabaturu põhimõtetest tuleks selline küsimus lahendada „las parim projekt võidab“ põhimõttel. 2014 suvel, kui avati CEF TEN-E programmi rahastustaotluste esimene voor, jätsime me Paldiski osas uuringute kaasrahastuseks taotluse esitamata, kuivõrd uuringud olid meil juba lõppfaasis ja Eesti-Soome vahel olid käimas kompromissiläbirääkimised. Teine rahastusvoor lõpeb 14.10.2015 ja me soovime Paldiski LNG terminali projekti ehitustööde kaasrahastamiseks selles voorus taotluse esitada. Vastavalt EL määruse 347/2013 sätetele, peavad liikmesriigid kooskõlastama nende territooriumile planeeritavate energiataristu ühishuviprojektid. Seetõttu palume kooskõlastada vastavalt EK vormile Paldiski LNG terminali taotlus (manuses) arvestades selle rahastusvooru sulgumise tähtajaga. Lugupidamisega digitaalallkirjastatud Marti Hääl, juhatuse liige Alexela Group OÜ Balti Gaas OÜ