Budget 2025
Adopted
**v
OBS 2024.13-fin
Meeting: Financial Committee
Date: 18 November 2024
BUDGET 2025
Table of contents
1. Remarks on the Observatory’s budget for 2025............................................................. 1
1.1. General remarks .............................................................................................................................................................................................1
1.2. Budget framework and composition ......................................................................................................................................................1
1.2.1. The total budget ......................................................................................................................................................................1
1.2.2. The activity budget .................................................................................................................................................................2
1.2.3. The EPRA special budget ......................................................................................................................................................3
2. Comments on the income and expenditure budgets ..................................................... 4
2.1. Income4
2.1.1. Credit balance ...........................................................................................................................................................................4
2.1.2. Fund for the extension of the Observatory’s premises ..............................................................................................5
2.1.3. Income from products and services ..................................................................................................................................5
2.1.4. Bank interest .............................................................................................................................................................................8
2.1.5. Members’ compulsory contributions ................................................................................................................................8
2.2. Expenditure................................................................................................................................................................................................... 10
2.2.1. General remarks on the managerial projects ............................................................................................................. 11
2.2.2. The programme of activities ............................................................................................................................................ 12
2.2.3. The support units ................................................................................................................................................................. 14
2.2.4. The European Platform of Regulatory Authorities ................................................................................................... 17
2.3. Implementation of the budget .............................................................................................................................................................. 17
2.3.1. Contribution Agreements .................................................................................................................................................. 17
2.3.2. The EPRA budget .................................................................................................................................................................. 17
2.3.3. Role of the reserve ............................................................................................................................................................... 17
2.3.4. Transfers within the budget ............................................................................................................................................. 18
3. Summary tables ............................................................................................................... 19
3.1. The total budget ......................................................................................................................................................................................... 19
3.2. Activity budget............................................................................................................................................................................................. 21
3.3. Special budget ............................................................................................................................................................................................. 28
3.4. Staffing table ................................................................................................................................................................................................ 30
3.4.1. Posts and positions .............................................................................................................................................................. 30
3.4.2. Assignments ........................................................................................................................................................................... 30
BUDGET 2025
Figures
Figure 1 – Total Budget structure (income) 2016-2025 .......................................................................................................................................... 2
Figure 2 – 2024 activity budget ........................................................................................................................................................................................ 3
Figure 3 – Income from products and services ........................................................................................................................................................... 6
Figure 4 – Sales of publications and online services, 2023 ................................................................................................................................... 7
Figure 5 – Weight of the co-financed projects in the activity budget, 2016-2025....................................................................................... 8
Figure 6 – Changes in members’ compulsory contributions over ten years .................................................................................................... 9
Figure 7 – Proportion of members’ compulsory contributions in the activity budget ................................................................................. 9
Figure 8 – Total income budget, 2023-2025 ............................................................................................................................................................. 10
Figure 9 – Composition of the expenses budget, 2021-2025 activity budget ............................................................................................. 16
Tables
Table 1. Total budget: Receipts ....................................................................................................................................................................... 19
Table 2. Total budget: Expenses...................................................................................................................................................................... 19
Table 3. Total budget: Expenses, breakdown by budget head ............................................................................................................ 20
Table 4. Activity budget: Receipts ................................................................................................................................................................... 21
Table 5. Activity budget: Receipts, breakdown of products and services ....................................................................................... 21
Table 6. Activity budget: Receipts, breakdown of co-financed projects .......................................................................................... 22
Table 7. Activity budget: Breakdown of members’ contributions ....................................................................................................... 23
Table 8. Activity budget: Expenses ................................................................................................................................................................. 24
Table 9. Activity budget: Expenses, breakdown by cost accounting section (1) .......................................................................... 25
Table 10. Activity budget: Expenses, breakdown of the reserve ........................................................................................................... 27
Table 11. Special budget: Receipts ................................................................................................................................................................... 28
Table 12. Special budget: Expenses.................................................................................................................................................................. 29
Table 13. Staffing table.......................................................................................................................................................................................... 31
BUDGET 2025
1. Remarks on the Observatory’s budget
for 2025
1.1. General remarks
The 2025 budget is intended to support the implementation of the Action Plan as part of
the Mid-term Strategy (MtS) 2024-2028.
The 2022 to 2024 financial years were characterised both by the late completion of the
restructuring of the Secretariat undertaken as part of the previous MtS and by staff
changes that resulted in vacancies with an impact on the Observatory team’s workload.
These unforeseen circumstances, combined with very high income from financial
investments in 2024 due to persistently high interest rates together with dynamic cash
management, resulted in exceptional credit balances. The Observatory was able to take
advantage of this situation to allocate to the Fund for co-financed projects the amount
necessary for the negotiation of the fourth Contribution Agreement, which is due to start
in 2025.
With the team back to full strength in early 2025, and with a modest increase in
resources, the Observatory will be able to make steady progress towards the main
objectives of the MtS, which are to consolidate a unique institution of renown and ensure
that it is of ever greater use to the European audiovisual sector, especially its political and
economic decision-makers.
1.2. Budget framework and composition
1.2.1. The total budget
The budget is made up of an activity budget and a special budget. The former comprises
the “ordinary” budget (i.e., the Observatory's own resources) and the budget for the third
Contribution Agreement, a project co-financed by the European Commission. While the
Observatory's own resources finance its core activities, the co-financed projects both
cover recurrent services to the European Commission and the exploration of new areas by
the Observatory. The third Contribution Agreement with the European Commission, which
came into force on 1 January 2024, runs until 31 December 2025.
The activities concerning the hosting of the European Platform of Regulatory Authorities
(EPRA) are covered by a special budget.
OBS 2024.13-fin EN Budget 2025 - Adopted 2772-6597-9147 v.1
Page 1
BUDGET 2025
Income budget Ordinary Activity Special
budget budget budget
Credit balance
Dedicated fund
Income from products and services
Co-financed projects
Budget of the European Platform of Regulatory
Authorities (EPRA)
Members’ compulsory contributions
Total budget
Figure 1 – Total Budget structure (income) 2016-2025
100% Credit balance
90% Extension of premises
80% Financial reserve (investments)
70% Core products and services
60% PAGoDA/Contribution Agreements
50% TV Market in Europe
40% EPRA
30% Bank interest
20% Voluntary contributions
10% Past contribution (Russian
Federation)
0% Compulsory contributions
2016 2017 2018 2019 2020 2021 2022 2023 2024 2025
1.2.2. The activity budget
The following figure shows the breakdown of the funding for the Observatory’s
programme of activities. In the interests of budgetary transparency, the budget for the
Contribution Agreement is presented separately in the summary tables section.
OBS 2024.13-fin EN Budget 2025 - Adopted 2772-6597-9147 v.1
Page 2
BUDGET 2025
Figure 2 – 2024 activity budget
European
Commission
cofinancing
Contribution 95%
"Ordinary budget" Agreement
86,8% 13,2%
Observatory
cofinancing
5%
1.2.3. The EPRA special budget
The Observatory has hosted the Secretariat of the European Platform of Regulatory
Authorities since 2006. This is based on a Memorandum of Understanding automatically
renewed every year and under which the Observatory provides the structure and services
necessary for EPRA to operate. This Memorandum of Understanding was amended in 2019
to take account of EPRA’s development and has been tacitly renewed since then.
OBS 2024.13-fin EN Budget 2025 - Adopted 2772-6597-9147 v.1
Page 3
BUDGET 2025
2. Comments on the income and
expenditure budgets 1
2.1. Income
The total budget is slightly higher (+0.4%) than the final budget for the 2024 financial
year as a result of contrasting trends in the various income items: there is a sharp fall in
the volume of the third Contribution Agreement with the European Commission (CA3) and
income from bank interest but this is offset by the contribution of the credit balance from
the last closed financial year, members’ compulsory contributions and, more significantly,
the new inclusion in the budget of the fund for the project to extend the Observatory's
premises (cf. paras. 2.1.2 and 2.2.3.3).
The activity budget rises by 0.2% and the ordinary budget by 6.1%. If the budget for the
project to extend the premises is excluded, due to the rise in the credit balance, the
increase in the ordinary budget is limited to 1.9%. In a situation of persistent inflation, the
policy of insourcing IT development and maintenance and the use of machine translation
will contribute to generating the savings needed to balance the budget.
The EPRA budget increases by 3.7%.
The risks inherent in the implementation of the programme of activities and the budget
are described in the MtS 2.
2.1.1. Credit balance
The credit balance of the last closed financial year is an integral part of the budget.
Article 5 of the Financial Regulations3 provides: “In accordance with the provision set out
in Article [9.1 (e)] of the Statute of the Observatory, the credit balance of the last closed
and approved financial year shall be credited to the Budget of Receipts for the second
financial year succeeding the one in question […]. The Executive Council may authorise a
different allocation of the aforesaid credit balance”.
The allocation of the credit balance for the 2023 financial year was the subject of a
decision by the Executive Council in June 20244 with the aim of topping up the fund for
1
References to the 2024 budget relate to the final budget (document OBS 2024.12), for which income has
increased slightly (income from products and services and bank interest). Amounts may therefore differ a little
from those communicated to members in the non-paper of 29 August 2024.
2
Cf. Mid-term Strategy 2024-2028, ibid., paras. 6.6., 7.4.4. and 8.4.
3
Cf. Financial Regulations of the European Audiovisual Observatory, document OBS 2018.01.
4
Cf. document OBS 2024.05-II, Allocation of the credit balance of the 2023 financial year.
OBS 2024.13-fin EN Budget 2025 - Adopted 2772-6597-9147 v.1
Page 4
BUDGET 2025
co-financed projects in the light of the negotiation of a two-year Contribution Agreement.
The sum of EUR 260 085.68 is allocated to the 2025 budget, a significant increase
compared to 2024.
2.1.2. Fund for the extension of the Observatory’s premises
In 2017, the Observatory proposed to the City of Strasbourg, the owner of the Villa
Schutzenberger, which houses the Observatory’s offices, that it contribute EUR 100 000 to
work to convert the garage adjoining the villa into additional working space, in exchange
for a rent-free period corresponding to the amount of the work. In 2018, the Executive
Council approved the creation of a fund to finance this contribution and the necessary
outlays to fit out the new offices. Since 2019, a number of technical, legal and financial
setbacks have forced the City of Strasbourg to postpone the project. The work, which was
begun in 2020, is suspended owing to a legal dispute5. According to information provided
by the City of Strasbourg, the dispute has been solved, allowing the project to resume. In
view of the Observatory’s ever-pressing need for more office space and a meeting-room
equipped with videoconferencing facilities, this is very good news.
The appropriations amounting to EUR 131 700 to cover both the Observatory’s
contribution and the fitting out costs make up almost the entire fund and are entered in
the 2025:
•Contribution to the renovation work EUR 100 000
•Purchase of furniture, fitting out the offices and
other outlays (installation of a videoconference facility) EUR 31 700
The balance of the fund, EUR 8 300, is reserved for finalising the fitting-out work and will
be used in 2026 if construction has been completed during the financial year.
2.1.3. Income from products and services
The receipts entered under budget head 2 are sharply down due to the 28% fall in the
volume of CA3. They make up 15% of the Observatory’s activity budget.
As a result of the previous MtS, the co-financed projects are now exclusively aimed at
increasing the Observatory’s information offering beyond its core mission.
The Observatory hopes to increase its income from its main publication, the online
Yearbook, despite the difficult market in which it is sold and while maintaining the
balance between its public service remit and the requirement to generate income from its
services. LUMIERE Pro is aimed at an even smaller user group, with sales made under a
sub-licence agreement.
5
Cf. Action Plan 2023, OBS 2022.09-III, section 2.1. Goals related to management and development.
OBS 2024.13-fin EN Budget 2025 - Adopted 2772-6597-9147 v.1
Page 5
BUDGET 2025
Figure 3 – Income from products and services
2.a. Publications
4.a. Compulsory and related services
contributions 2,0%
69,5%
2.a.
Agreements
and other
services
0,6%
2.b. Contribution
Agreement
Other 12,5%
20,5%
2.c. EPRA
5,3%
1.a. Credit balance
6,5%
3. Bank interest Fund Extension of
0,2% premises
3,3%
2.1.3.1. Publications and services
The Observatory disseminates most of its output free of charge in order to fulfil its
mission to ensure greater transparency in the audiovisual sector. Three publications and
services are for sale due to restrictions on the dissemination of the data they contain: the
online Yearbook, LUMIERE Pro and FOCUS – World Film Market Trends. These restrictions
are imposed by the providers on which the Observatory relies for their preparation.
The target for sales of the Observatory’s paid productions has been increased by 4%.
OBS 2024.13-fin EN Budget 2025 - Adopted 2772-6597-9147 v.1
Page 6
BUDGET 2025
Figure 4 – Sales of publications and online services, 2023
Yearbook online
45%
LUMIERE Pro
54%
FOCUS - Film
market trends
1%
It should also be pointed out that the 2025 edition of FOCUS – World Film Market Trends
is contingent upon the conclusion of an agreement with the Cannes Film Market on the
Observatory’s contribution to the event.
2.1.3.2. Co-financed project
The third Contribution Agreement between the Observatory and the European
Commission (CA3), concluded in 2024 for two years, is included in the 2025 budget. The
co-financing of the European Commission's grant agreements amounts to 95%. The
Observatory’s 5% co-financing is provided by the fund for co-financed projects6.
The volume of activities carried out as part of the second year of CA3 will fall sharply. As
a result, this project’s share of the activity budget is now just 13%, compared with 18% in
2024.
6
Cf. document OBS 2016.07 rev “Creation of a fund for co-financed projects — Allocation to the revised 2016
budget. Proposal for a decision”.
OBS 2024.13-fin EN Budget 2025 - Adopted 2772-6597-9147 v.1
Page 7
BUDGET 2025
Figure 5 – Weight of the co-financed projects in the activity budget, 2016-2025
4 000
Thousands
3 500
3 000
2 500
2 000
1 500
1 000
500
-
2016 2017 2018 2019 2020 2021 2022 2023 2024 2025
PAGoDA/CA Other resources
2.1.3.3. The EPRA special budget
After a sharp increase in 2024, the EPRA budget rises by 3.7%. Under the Memorandum of
Understanding, concluded between EPRA and the Observatory, the amounts remitted by
EPRA cover all the costs of hosting its Secretariat.
2.1.4. Bank interest
Investments in term deposit accounts in 2024 ought to enable the Observatory to rely on
income that should remain substantial.
2.1.5. Members’ compulsory contributions
In accordance with the Observatory’s Financial Regulations, the method of calculating the
scale of members’ contributions is based on Council of Europe Committee of Ministers
Resolution (94)31 governing the scales pertaining to the Partial Agreements.
Belgium’s contribution is shared between the French Community (49%), the Flemish
Community (49%) and the German-speaking Community (2%).
In order to respond to the impact of inflation on its costs, the Observatory is requesting a
2% increase in its members’ compulsory contributions. This translates into a modest rise
of 1.9% in the resources for financing the Observatory’s core activities (“ordinary budget”,
OBS 2024.13-fin EN Budget 2025 - Adopted 2772-6597-9147 v.1
Page 8
BUDGET 2025
excluding the funds for the implementation of the project to extend the offices). This will
not enable the Observatory to balance its budget without additional measures (cf. para.
2.2).
Figure 6 – Changes in members’ compulsory contributions over ten years
(Base 100 = 2016)
130%
125%
120%
115%
110%
105%
100%
95%
90%
85%
80%
2016 2017 2018 2019 2020 2021 2022* 2023 2024 2025
* Including the entire contribution due from the Russian Federation.
Figure 7 – Proportion of members’ compulsory contributions in the activity budget
(Own resources + co-financed projects)
100%
Credit balance Bank interest
Extension of
90% Core products and services premises
PAGoDA/Contributio
80%
n Agreements
70%
60%
50%
40%
Obligatory
contributions
30%
20%
10%
Past contribution
(Russian Federation)
0%
2021 2022 2023 2024 2025
OBS 2024.13-fin EN Budget 2025 - Adopted 2772-6597-9147 v.1
Page 9
BUDGET 2025
Figure 8 – Total income budget, 2023-2025
4 500
Thousands EUR
4 000
3 500
3 000 Credit balance
Extension of premises
2 500 Core products and services
Contribution Agreements
2 000
EPRA
1 500 Bank interest
Obligatory contributions
1 000
500
-
2023 2024 2025
2.2. Expenditure
The expenditure budget is organised by type of expenditure grouped under eight budget
heads. For budget monitoring purposes, the allocation of resources is structured around
cost centres, which in turn group together the analytical sections corresponding to the
projects included in the action plan. The cost centres are the two departments, the IT and
Visibility units and the Administration.
The remarks on the expenditure budget follow this operational approach to a large
extent.
Ordinary budget Activity budget Special budget
Department for Market Department for Market Budget of the European Platform
Information Information of Regulatory Authorities (EPRA)
Department for Legal Information Department for Legal Information
Visibility Unit Visibility Unit
IT Unit IT Unit
Administration Administration
Co-financed projects
As the EPRA special budget has no impact on the Observatory’s budget, the remarks on
expenditure only relate to the activity budget.
OBS 2024.13-fin EN Budget 2025 - Adopted 2772-6597-9147 v.1
Page 10
BUDGET 2025
Unless otherwise stated, comparisons with the 2024 budget relate to the final budget for
the financial year.
In order to balance the budget, the Secretariat has limited the increase in certain
expenditure items, thereby taking a controlled budget risk given the cost-cutting
capabilities it has demonstrated in the last few years.
2.2.1. General remarks on the managerial projects
2.2.1.1. Staff
After a period in 2023 and 2024 marked by numerous staff changes, the Observatory
should be back to its full staff complement in 2025, subject to the reshuffling of some
jobs. The difficulties encountered by the Department for Legal Information (DLI) in
recruiting the successor to a Senior Analyst who has left the Observatory have resulted in
the reclassification of his post. Pending the conclusion of the recruitment procedure, the
temporary staff member taken on in September 2024 will remain in post until February
2025.
In addition, the increasing importance of IT tools and the strategy of insourcing their
development in an effort to ensure efficiency and independence make it necessary to
reclassify the post of Head of the IT Unit. Owing to the seniority of the incumbent, this
measure is budget neutral.
Para. 2.2.2.1 sets out the changes in the staff budget.
2.2.1.2. Use of artificial intelligence
In 2024, the Observatory paved the way for the introduction of AI in two areas of the
Secretariat’s work. The complexity of the projects has forced it to postpone their
implementation until 2025.
The foundations of the plan to use machine translation for the IRIS Newsletter have been
laid, with the introduction of a new method of remuneration for proofreaders, who will
play a key role in the success of the undertaking. The 2025 budget includes the scales
that will be offered to proofreaders. They may be adjusted during the year.
The impact of this measure concerns budget line 3.2 Translation and proofreading (cf.
para. 2.2.2.3Error! Reference source not found.). The underlying software development is b
eing carried out in-house (cf. para. 2.2.3.1).
In 2024, the Observatory has also studied solutions for automating and computerising
accounting documents with the aim of improving procurement flows, accounting and the
management of accounting documents, thus increasing efficiency while meeting the
expectations expressed by the Board of External Auditors with regard to reliable audit
OBS 2024.13-fin EN Budget 2025 - Adopted 2772-6597-9147 v.1
Page 11
BUDGET 2025
trails. The implementation of the project is scheduled for the end of 2025 as it is not a
priority, so its budget impact is very limited.
2.2.1.3. Sustainability
By further improving access to the results of its work on its website, the Observatory has
completed concrete measures to reduce its carbon footprint even more: printing and the
mailing of publications have been reduced to an absolute minimum by favouring
electronic distribution. However, although the funds allocated to the layout and printing
of publications will be reduced in 2025 the figure for postal charges has had to be
increased because of the sharp price rises in 2024.
Similarly, whenever possible and appropriate, the Observatory now prefers to take part
online in events to which it has been invited.
It should be noted that while it is up to the members to choose the format of Executive
Council and Advisory Committee meetings the Secretariat will continue to advocate face-
to-face meetings of its statutory bodies. However, in view of the cancellations recorded in
2024, this budget provides for the two meetings of the Bureau of the Executive Council to
be held by videoconference.
Staff travel expenses are slightly down overall, despite the foreseeable increase in
transport costs.
2.2.2. The programme of activities
The Observatory’s work relies essentially both on the expertise of its team and on the
network that it leads, so staff costs are the biggest expenditure item. Excluding the
project to extend the premises, it is followed by the “Partnership and network” item.
2.2.2.1. Human resources
In 2025, all the jobs in the revised organisation chart resulting from the restructuring of
the Secretariat should be filled.
This budget incorporates an overall increase in salary costs resulting from four factors:
◼ The salary adjustment granted to staff of the Coordinated Organisations in 2025
should reflect the level of inflation. The method used for this adjustment is to
take a benchmark calculation based on salary increases in a group of reference
national civil services. The Council of Europe Committee of Ministers decides on
the adjustment for the Organisation.
◼ The agreement on the 2024 salary adjustment provided for a two-stage
adjustment. The second, negative adjustment of -0.8%, will be made on 31
December 2024.
◼ The cost of pensions should rise significantly.
OBS 2024.13-fin EN Budget 2025 - Adopted 2772-6597-9147 v.1
Page 12
BUDGET 2025
◼ Staff grade changes and family situation also have an appreciable impact.
The proportion of staff costs in the activity budget is 2.6% higher compared with 2024.
Total staff costs rise by 4%.
2.2.2.2. Department for Market Information (DMI)
The DMI’s programme of activities is based mainly on recurring projects, which is
reflected in the stability of its budget. Systematic calls for tenders have enabled the
department to obtain the best prices in a market where competition remains limited. The
DMI intends to further improve its control of data purchasing costs by concluding
framework contracts with a capped price rise clause. Finally, the department will be
increasing its use of machine translation.
Translation and proofreading costs fall by 12.5%.
The data purchases budget falls by 11.4%.
Travel costs are slightly higher (2.3%).
The activities under the third Contribution Agreement make up 22.5% of the department’s
resources. They accounted for a third in 2024, with a particularly high proportion of data
purchases.
2.2.2.3. Department for Legal Information (DLI)
The project to machine-translate articles in the monthly newsletter IRIS – Legal
Observations of the European Audiovisual Observatory will be introduced at the
beginning of the year. It is based on in-house IT development and the creation of a
trilingual glossary of technical terms.
The change in the method of remunerating proofreaders has led the Observatory to revise
the expected gain downwards. It is nonetheless significant.
The budget takes into account a volume of translation similar to that of 2024, and the use
of the incumbent partners, EMR - Institute of European Media Law and IViR - Institute for
Information Law, is based on the two framework partnership agreements with these
organisations.
Translation and proofreading costs fall by 13.8%.
The Partnership and network budget is back to the level of the last adopted budget (only
one framework agreement was partially implemented in 2024).
Travel costs are 44% higher (+EUR 2 300) because the department will be back to its full
staff complement.
The activities under the third Contribution Agreement make up 23.2% of the department’s
resources, which is by and large the same proportion as in 2024.
OBS 2024.13-fin EN Budget 2025 - Adopted 2772-6597-9147 v.1
Page 13
BUDGET 2025
2.2.3. The support units
The units carry out cross-department activities, supporting the work of the departments at
various stages.
2.2.3.1. IT
The team consists of the head of the unit and two IT specialists with complementary
backgrounds, one of whom is on 80% FTE.
The strategy launched in 2020 of insourcing IT projects has resulted in savings on IT
maintenance and development costs. These savings are in addition to efficiency gains,
which primarily benefit the DMI, whose activities are largely based on IT tools, and enable
control to be taken of these key tools. In 2024, the unit has also developed budget
preparation software, which will also handle budget monitoring in 2025, as well as the
interface and glossary on which the machine translation of the IRIS newsletter will be
based.
As in-house IT developments are not fixed assets, capital expenditure is now reduced to a
symbolic amount. In order to better reflect the IT Unit’s work volume, the appropriations
covering the unit’s staff costs, previously included in the Administration’s budget, have
been transferred to the unit. These include IT staff costs as well as costs relating to the
agreement between the Council of Europe’s Directorate of Information Technology (DIT)
and the Observatory on staff computer workstations, which covers a number of underlying
services7.
As a result of the adjustment to the scope of these services, the breakdown of
appropriations covering this agreement has had to be reviewed: the proportion relating to
the working environment (budget line 2.2 Office equipment) has been reduced in favour
of infrastructure and security services and other tools provided by the DIT (budget line 2.6
Maintenance). The respective proportions in respect of the “Stationery and office
equipment” and “Maintenance” items are now 34% and 66%, compared with 47% and 53%
in 2024. The services provided by the DIT will continue to be enhanced by the
introduction of AI tools. The sharp increase in the “Total cost of ownership” (TCO) partially
rebilled to the Observatory, announced in 2024 and then postponed, will apply in 2025.
This increase reflects the sharp rise in the cost of software licences, the strengthening of
the IT security item, the renewal of workstations in connection with the Council of
Europe’s “New way of working” policy, especially to facilitate remote working, and
bringing into line the number of workstations invoiced with the number of Observatory
staff at the end of the transition period negotiated in 2020.
The Observatory remains dependent on outside companies for very specific software:
although the budget preparation and monitoring software is developed in-house, the
7
See para. 2.2.1.1on extending the scope of responsibility of the Head of the IT Unit.
OBS 2024.13-fin EN Budget 2025 - Adopted 2772-6597-9147 v.1
Page 14
BUDGET 2025
management and accounting tools, as well as certain specific applications like the
planned invoice digitisation solution (see also para. 2.2.1.2), are based on proprietary
software. Whenever possible, the Observatory takes advantage of the conditions of the
framework contracts concluded by the Council of Europe, for example for the electronic
signature solution implemented in 2024.
The budget includes a 51% increase in the costs rebilled by the Council of Europe for staff
workstations and associated services, taking into account the parameters set out above and an
increase in costs in line with the Syntec index. This increase mainly concerns budget line 2.6
Maintenance and explains the sharp rise in the appropriations allocated to this budget line in
the activity budget.
As the Unit now has full control over a large proportion of the Observatory’s IT tools, especially
the commercial interface of the online Yearbook, it can forego the modest sum of EUR 5 300
(EUR 1 800 in investments, under line 6.2 Software - purchases and development, and EUR
3 500 under line 3.3 Other services and external assistance, which covers IT services intended
for providing ad hoc support to outside companies.
2.2.3.2. Visibility
The only notable change in the Visibility Unit’s budget is the inclusion in the
corresponding cost-accounting section of appropriations covering the unit’s staff costs,
reflecting the unit assistant’s contribution to the Administration’s work.
The unit contributes to the overall budgetary effort to minimise costs and the resources
allocated to the organisation of events and promotional activities are lower. Accordingly,
reception costs are down by one third. The Observatory’s efforts in the area of sustainable
development (see para. 2.2.1.3) are partially outweighed here by the increase in postal
charges. Only the Translation and proofreading item has been increased to take account
of the rise in the number of press releases and other informative communications.
Excluding the impact of the transfer of staff costs, the visibility budget remains decreases by
5.2%).
2.2.3.3. Administration
The appropriations allocated to administration have fallen sharply both as a result of the
transfer of staff appropriations to the IT and Visibility units and of the amounts covering
the agreement on staff computer workstations in the IT Unit (see paras. 2.2.3.1 and 2.2.3.2
above). Excluding these technical measures, the Administration budget has increased by
10%, due almost entirely to the inclusion of funds earmarked for the project to extend the
Observatory’s premises. This project has a marked impact on budget heads 2. Support
costs and 6. Investments:
⎯ EUR 100 000 is entered in budget line 2.8 Rent and costs of premises.
OBS 2024.13-fin EN Budget 2025 - Adopted 2772-6597-9147 v.1
Page 15
BUDGET 2025
⎯ EUR 31 700 is entered in budget lines 6.1 IT hardware, 6.3 Office furniture and 6.4
Office equipment and installation.
The Administration also contributes to the budget process and, excluding the project to
extend the premises and the increase in staff costs (see also para. 2.2.2.1), its budget
remains stable (+0.4%).
Item 3.1 Translation and proofreading is down, mainly due to the foreseeable reduction in
the costs of interpretation for the Executive Council meeting8. In addition, although the
machine translation of the statutory bodies’ working documents is not on the agenda in
view of their importance, the Secretariat does not rule out its use for test purposes
The project to extend the premises contributes to a large extent to the slight increase in
the total budget.
Figure 9 – Composition of the expenses budget, 2021-2025 activity budget
100%
90%
80%
70%
60%
50%
40%
30%
20%
10%
0%
2021 2022 2023 2024 2025
Staff Support costs External services
Marketing Documentation Investments
Partnership and network Flexible allocation
8
In accordance with the Executive Council’s decision, the meeting will be held in Vienna, which will mean
lower travel costs for the team of interpreters.
OBS 2024.13-fin EN Budget 2025 - Adopted 2772-6597-9147 v.1
Page 16
BUDGET 2025
2.2.4. The European Platform of Regulatory Authorities
The EPRA budget is approved by the EPRA Executive Board and implemented by the EPRA
Secretariat. It will increase by 3.7% in 2025.
2.3. Implementation of the budget
2.3.1. Contribution Agreements
Once signed, the Contribution Agreements are subject to the payment of 80% of the
amount of its co-financing by the European Commission. Throughout their
implementation, the Observatory carries out analytical monitoring of expenditure and
calls in the balance from the Commission at the end of the contract.
It should be noted that projects co-financed by the Commission include a flat-rate
allocation equivalent to a maximum of 7% of eligible expenditure to cover the
administrative costs of these projects. The corresponding expenditure that this provision
is meant to finance is entered directly into the Observatory’s “ordinary” budget.
2.3.2. The EPRA budget
Pursuant to the Memorandum of Understanding between the Observatory and EPRA (see
1.2.3 above), the EPRA Executive Board arranges for two advances to be remitted to the
Observatory, one at the beginning and one in the middle of the financial year. The final
calculation of the expenditure incurred in connection with the service results in the
offsetting of sums paid at the close of the accounts for the financial year. The agreement
is therefore budget-neutral for the Observatory since EPRA pays all the costs associated
with hosting it.
2.3.3. Role of the reserve
A large proportion of the Observatory’s budget is financed by members’ compulsory
contributions. Article 21 of the Financial Regulations provides that the Executive Director
“shall [...] (p)rior to any commitment of the Observatory's funds [...] ensure that the funds
are available under the appropriate Sub-head of the Budget”.
The implementation of the Action Plan depends to a significant extent on the proper
collection of the compulsory contributions. A member’s failure to pay constitutes a risk
that the Observatory takes into account in the budget in the form of a “reserve”. This
groups together the expenditure allocated to specific measures that are planned for the
second half of the year and whose implementation depends on a good level of collection
of contributions. At the end of the deadline for the payment of the compulsory
contributions (in practice at the beginning of July), if the level of collection is satisfactory
OBS 2024.13-fin EN Budget 2025 - Adopted 2772-6597-9147 v.1
Page 17
BUDGET 2025
and it considers that any incident likely to jeopardise the implementation of the budget
can be ruled out, the Observatory gives the green light to the measures whose funding
has been budgeted in the reserve.
Many projects require long preparation, so selecting activities for placing in the reserve is
a difficult exercise. The activities concerned total EUR 87 700 and are listed in Table 10.
2.3.4. Transfers within the budget
The budget is subject to analytical monitoring throughout the financial year. In
accordance with established practice, the Executive Director can have transfers made
between budget heads during the financial year as follows:
1. up to a maximum of 10% of the initial amount without the Executive Council’s
authorisation,
2. up to a maximum of 20% of the initial amount after the Executive Council’s
authorisation.
Any transfers will be included in the amending budget submitted to the Executive
Council.
OBS 2024.13-fin EN Budget 2025 - Adopted 2772-6597-9147 v.1
Page 18
BUDGET 2025
3. Summary tables
In accordance with the provisions of Article 16 of the Financial Regulations, the budget is
presented in comparison with the last two financial years.
3.1. The total budget
Table 1. Total budget: Receipts
2023 2024 2025
Final budget Final budget Budget
EUR % EUR % EUR %
1a. Credit balance 253 853,30 6,6% 202 159,14 5,1% 260 085,68 6,5%
1b. Fund extension of premises - 0,0% 0,0% 131 700,00 3,3%
2a. Income from products and services 106 500,00 2,8% 108 300,00 2,7% 107 600,00 2,7%
2b. Cofinanced projects (Contribution 694 200,00 18,2% 699 200,00 17,5% 500 300,00 12,5%
Agreement)
2c. EPRA 193 800,00 5,1% 206 800,00 5,2% 214 500,00 5,3%
3. Bank interest 2 000,00 0,1% 48 000,00 1,2% 10 000,00 0,2%
4. Contributions of member states 2 571 246,70 67,3% 2 738 440,86 68,4% 2 793 214,32 69,5%
Total 3 821 600,00 100,0% 4 002 900,00 100,0% 4 017 400,00 100,0%
Table 2. Total budget: Expenses
2023 2024 2025
Final budget Final budget Budget
EUR % EUR %
1. Staff 2 699 200 70,7% 2 794 100 69,8% 2 901 000 72,2%
2. Support costs 241 000 6,3% 266 100 6,6% 389 900 9,7%
3. External services 322 600 8,4% 335 500 8,4% 277 500 6,9%
4. Marketing 47 100 1,2% 49 900 1,2% 44 200 1,1%
5. Documentation 6 000 1,2%
0,2% 5 700 0,1% 4 800 0,1%
6. Investments 5 800 0,1% 15 100 0,4% 35 200 0,9%
7. Partnerships and network 484 900 12,7% 521 500 13,0% 349 800 8,7%
8. Flexible allocation 15 000 0,4% 15 000 0,4% 15 000 0,4%
Total 3 821 600 100,0% 4 002 900 100,0% 4 017 400 100,0%
OBS 2024.13-fin EN Budget 2025 - Adopted 2772-6597-9147 v.1
Page 19
BUDGET 2025
Table 3. Total budget: Expenses, breakdown by budget head
2023 2024 2025
Final budget Final budget budget
EUR EUR % EUR %
1. Staff 2 699 200 70,7% 2 794 100 69,8% 2 901 000 72,1%
1.1 Permanent staff - salaries, soc. charges&pensions 2 538 000 2 698 300 2 827 500
1.2 Temporary staff 155 500 75 000 61 900
1.3 Staff training 5 000
1.4 Other staff costs and recruitment costs 5 700 12 500 11 600
1.5 Trainees 3 300
2. Support costs 241 000 6,3% 266 100 6,6% 389 900 9,7%
2.1 Council of Europe services 35 200 35 200 34 800
2.2 Stationery and office equipment 36 500 48 600 42 200
2.3 Communications: telephone, fax, mailing costs 6 600 5 700 6 500
2.4 Travel 46 600 46 300 47 800
2.5 Insurances 2 600 2 900 3 000
2.6 Maintenance 59 200 69 900 95 500
2.7 Bank charges 2 200 1 600 1 400
2.8 Premises rental costs 50 900 54 000 157 000
2.9 Miscellaneous 1 200 1 900 1 700
3. External services 322 600 8,4% 335 500 8,4% 277 500 6,9%
3.1 Translation and proofreading 240 200 232 500 198 900
3.2 Layout and print 30 400 32 700 28 800
3.3 Other services and external assistance 38 400 50 900 32 800
3.4 External experts travel and accommodation 13 600 19 400 17 000
4. costs
Marketing 47 100 1,2% 49 900 1,2% 44 200 1,2%
4.1 Marketing and promotion 26 100 26 200 26 600
4.2 Receptions 21 000 23 700 17 600
5. Documentation 6 000 0,2% 5 700 0,1% 4 800 0,1%
6. Investments 5 800 0,1% 15 100 0,4% 35 200 0,9%
6.1 IT Hardware 900 11 200 8 900
6.2 IT Software (purchase and development) 4 400 2 400 1 500
6.3 Office furniture 500 19 700
6.4 Office equipment&installation - Sundry investments 1 500 5 100
7. Partnership and network 484 900 12,7% 521 500 13,0% 349 800 8,7%
7.1 Partnership contracts 40 000 6 500 40 000
7.2 Collaboration with correspondents, data 444 900 515 000 309 800
purchaseallocation for unexpected expenses
8. Flexible 15 000 0,4% 15 000 0,4% 15 000 0,4%
Total 3 821 600 100,0% 4 002 900 100,0% 4 017 400 100,0%
OBS 2024.13-fin EN Budget 2025 - Adopted 2772-6597-9147 v.1
Page 20
BUDGET 2025
3.2. Activity budget
Table 4. Activity budget: Receipts
2023 2024 2025
Final budget Final budget Budget
EUR % EUR % EUR %
1a. Credit balance 253 853,30 7,0% 202 159,14 5,3% 260 085,68 6,8%
1b. Fund extension of premises 0,0% 0,0% 131 700,00 3,5%
2a. Income from products and services 106 500,00 2,9% 108 300,00 2,9% 107 600,00 2,8%
2b. Cofinanced projects (Contribution 694 200,00 19,1% 699 200,00 18,4% 500 300,00 13,2%
3. Bank) interest
Agreement 2 000,00 0,1% 48 000,00 1,3% 10 000,00 0,3%
4. Contributions of member states 2 571 246,70 70,9% 2 738 440,86 72,1% 2 793 214,32 73,4%
Total 3 627 800,00 100% 3 796 100,00 100% 3 802 900,00 100%
Table 5. Activity budget: Receipts, breakdown of products and services
2023 2024 2025
Final budget Final budget Budget
EUR % EUR % EUR %
Publications and related services 75 500,00 70,9% 77 800,00 71,8% 81 600,00 75,8%
Agreements (Film Market, …) 30 000,00 28,2% 25 000,00 23,1% 25 000,00 23,2%
Consulting activities 4 500,00 4,2%
Other services 1 000,00 0,9% 1 000,00 0,9% 1 000,00 0,9%
Total 106 500,00 100,00% 108 300,00 100,0% 107 600,00 100,0%
OBS 2024.13-fin EN Budget 2025 - Adopted 2772-6597-9147 v.1
Page 21
BUDGET 2025
Table 6. Activity budget: Receipts, breakdown of co-financed projects
2023 2024 2025
Final budget Final budget Budget
EUR % EUR % EUR %
Contribution Agreement 2 (2023) 694 200,00 100%
Grant European Commission 659 500,00
Cofinancing Fund 34 700,00
Contribution Agreement 3 (2024-2025) 699 200,00 100% 500 300,00 100,0%
Grant European Commission 664 400,00 475 100,00
Cofinancing Fund 34 800,00 25 200,00
Total 694 200,00 100% 699 200,00 100% 500 300,00 100,0%
OBS 2024.13-fin EN Budget 2025 - Adopted 2772-6597-9147 v.1
Page 22
BUDGET 2025
Table 7. Activity budget: Breakdown of members’ contributions
2023 2024 2025
Final budget Final budget Budget
% scale CoE EUR % scale CoE EUR % scale CoE EUR
RES(94)31 RES(94)31 RES(94)31
Albania 0,1460 3 754,02 0,1460 3 998,12 0,1460 4 078,09
Armenia 0,1460 3 754,02 0,1460 3 998,12 0,1460 4 078,09
Austria 1,5046 38 686,98 1,4798 40 523,45 1,4507 40 521,16
Belgium 1,8182 46 750,41 1,8096 49 554,83 1,7925 50 068,37
Bosnia and Herzegovina 0,1460 3 754,02 0,1460 3 998,12 0,1460 4 078,09
Bulgaria 0,3383 8 698,53 0,3478 9 524,30 0,3564 9 955,02
Croatia 0,2578 6 628,68 0,2587 7 084,35 0,2601 7 265,15
Cyprus 0,1460 3 754,02 0,1460 3 998,12 0,1460 4 078,09
Czechia 0,9460 24 323,99 0,9537 26 116,51 0,9574 26 742,23
Denmark 1,1718 30 129,87 1,1743 32 157,51 1,1794 32 943,17
Estonia 0,1460 3 754,02 0,1460 3 998,12 0,1460 4 078,09
Finland 0,9215 23 694,04 0,9113 24 955,41 0,8914 24 898,71
France 12,9000 331 690,82 12,9000 353 258,87 12,9000 360 324,65
Georgia 0,1460 3 754,02 0,1460 3 998,12 0,1460 4 078,09
Germany 12,9000 331 690,82 12,9000 353 258,87 12,9000 360 324,65
Greece 0,8130 20 904,24 0,7878 21 573,44 0,7725 21 577,58
Hungary 0,6628 17 042,22 0,6693 18 328,39 0,6622 18 496,67
Iceland 0,1460 3 754,02 0,1460 3 998,12 0,1460 4 078,09
Ireland 1,2999 33 423,64 1,3729 37 596,06 1,4480 40 445,74
Italy 12,9000 331 690,82 12,9000 353 258,87 12,9000 360 324,65
Latvia 0,1460 3 754,02 0,1460 3 998,12 0,1460 4 078,09
Liechtenstein 0,1460 3 754,02 0,1460 3 998,12 0,1460 4 078,09
Lithuania 0,2175 5 592,46 0,2241 6 136,85 0,2317 6 471,88
Luxembourg 0,2270 5 836,73 0,2332 6 386,04 0,2346 6 552,88
Malta 0,1460 3 754,02 0,1460 3 998,12 0,1460 4 078,09
Montenegro 0,1460 3 754,02 0,1460 3 998,12 0,1460 4 078,09
Netherlands 3,0611 78 708,43 3,0583 83 749,74 3,0462 85 086,89
North Macedonia 0,1460 3 754,02 0,1460 3 998,12 0,1460 4 078,09
Norway 1,3023 33 485,35 1,3044 35 720,22 1,4208 39 685,99
Poland 2,5045 64 396,87 2,5357 69 438,65 2,5518 71 277,24
Portugal 0,9040 23 244,07 0,8914 24 410,46 0,8767 24 488,11
Romania 1,1098 28 535,70 1,1266 30 851,28 1,1398 31 837,06
Slovak Republic 0,4208 10 819,81 0,4198 11 495,98 0,4166 11 636,53
Slovenia 0,2016 5 183,63 0,2035 5 572,73 0,2022 5 647,88
Spain 4,9889 128 276,93 4,8539 132 921,18 4,7144 131 683,30
Sweden 1,8194 46 781,26 1,8392 50 365,41 1,8329 51 196,83
Switzerland 2,3519 60 473,15 2,3753 65 046,19 2,3708 66 221,53
Türkiye 3,8526 99 059,85 3,8417 105 202,68 3,8741 108 211,92
United Kingdom 12,9000 331 690,82 12,9000 353 258,87 12,9000 360 324,65
European Union 12,9000 331 690,82 12,9000 353 258,87 12,9000 360 324,65
Morocco 1,0527 27 067,52 1,0757 29 457,41 1,0648 29 742,15
Total 100% 2 571 246,70 100% 2 738 440,86 100% 2 793 214,32
OBS 2024.13-fin EN Budget 2025 - Adopted 2772-6597-9147 v.1
Page 23
BUDGET 2025
Table 8. Activity budget: Expenses
2023 2024 2025
Final budget Final budget Budget
EUR % EUR % EUR %
1. Staff 2 531 400 69,8% 2 613 800 68,9% 2 717 500 71,3%
1.1 Permanent staff salaries, soc. charges&pensions 2 370 200 2 518 000 2 694 400
1.2 Temporary staff 155 500 75 000 11 500
1.3 Staff training 5 000
1.4 Other staff costs and recruitment costs 5 700 12 500 11 600
1.5 Trainees 3 300
2. Support costs 224 800 6,2% 248 100 6,5% 368 000 9,7%
2.1 Council of Europe services 35 200 35 200 34 800
2.2 Stationery and office equipment 33 900 45 200 39 300
2.3 Communications: telephone, fax, mailing costs 6 400 5 500 6 400
2.4 Travel 40 100 38 900 38 200
2.5 Insurances 2 500 2 800 2 900
2.6 Maintenance 55 900 66 300 89 500
2.7 Bank charges 2 100 1 500 1 300
2.8 Premises rental costs 47 700 51 000 154 100
2.9 Miscellaneous 1 000 1 700 1 500
3. External services 312 800 9,0% 327 000 8,6% 268 400 7,1%
3.1 Translation and proofreading 238 700 231 300 197 700
3.2 Layout and print 30 300 32 500 28 600
3.3 Other services and external assistance 33 200 46 800 28 900
3.4 External experts travel and accommodation 10 600 16 400 13 200
4. costs
Marketing 47 100 1,4% 49 900 1,3% 44 200 1,2%
4.1 Marketing and promotion 26 100 26 200 26 600
4.2 Receptions 21 000 23 700 17 600
5. Documentation 6 000 0,2% 5 700 0,2% 4 800 0,1%
6. Investments 5 800 0,2% 15 100 0,4% 35 200 0,9%
6.1 IT Hardware 900 11 200 8 900
6.2 IT Software (purchase and development) 4 400 2 400 1 500
6.3 Office furniture 500 19 700
6.4 Office equipment&installation - Sundry investments 1 500 5 100
7. Partnership and network 484 900 12,9% 521 500 13,7% 349 800 9,2%
7.1 Partnership contracts 40 000 6 500 40 000
7.2 Collaboration with correspondents, data purchase 444 900 515 000 309 800
8. Flexible allocation for unexpected expenses 15 000 0,4% 15 000 0,4% 15 000 0,4%
Total 3 627 800 100,0% 3 796 100 100,0% 3 802 900 100,0%
OBS 2024.13-fin EN Budget 2025 - Adopted 2772-6597-9147 v.1
Page 24
BUDGET 2025
Table 9. Activity budget: Expenses, breakdown by cost accounting section (1)
Administration
information
Transversal
information
& support
Visibility
Subtotal
projects
Market
Legal
IT
EUR
1. Staff 753 800 593 200 125 500 255 300 659 200 2 387 000
1.1 Permanent staff salaries, soc. charges&pensions 753 800 584 900 122 300 255 300 647 600 2 363 900
1.2 Temporary staff 8 300 3 200 11 500
1.3 Staff training
1.4 Other staff costs and recruitment 11 600 11 600
1.5 costs
Trainees
2. Support costs 13 300 7 500 17 900 118 400 210 900 368 000
2.1 Council of Europe services 34 800 34 800
2.2 Stationery and office equipment 1 500 36 700 1 100 39 300
2.3 Communications: telephone, fax, 4 200 2 200 6 400
2.4 mailing
Travel costs 13 300 7 500 12 200 5 200 38 200
2.5 Insurances 2 900 2 900
2.6 Maintenance 81 700 7 800 89 500
2.7 Bank charges 1 300 1 300
2.8 Premises rental costs 154 100 154 100
2.9 Miscellaneous 1 500 1 500
3. External services 21 700 160 200 1 000 16 000 11 400 48 900 259 200
3.1 Translation and proofreading 8 200 144 300 1 000 9 600 28 600 191 700
3.2 Layout and print 13 500 9 700 3 900 1 500 28 600
3.3 Other services and external 100 700 11 400 13 500 25 700
3.4 assistance
External experts travel and 6 100 1 800 5 300 13 200
4. accommodation
Marketing costs 400 3 400 33 000 7 400 44 200
4.1 Marketing and promotion 400 26 200 26 600
4.2 Receptions 3 400 6 800 7 400 17 600
5. Documentation 4 800 4 800
6. Investments 11 500 23 700 35 200
6.1 IT Hardware 8 900 8 900
6.2 IT Software (purchase and 1 500 1 500
6.3 development)
Office furniture 19 700 19 700
6.4 Office equipment&installation - Sundry investments 1 100 4 000 5 100
7. Partnership and network 171 700 50 200 221 900
7.1 Partnership contracts 40 000 40 000
7.2 Collaboration with correspondents, data purchase 171 700 10 200 181 900
8. Flexible allocation for unexpected 15 000 15 000
expenses
Total
960 900 814 500 5 800 192 400 396 600 965 100 3 335 300
(See following page)
OBS 2024.13-fin EN Budget 2025 - Adopted 2772-6597-9147 v.1
Page 25
BUDGET 2025
Activity budget: Expenses, breakdown by cost accounting section (2)
Total activity
Agreement 3
Contribution
budget
EUR
1. Staff 330 500 2 717 500
1.1 Permanent staff salaries, soc. charges&pensions 330 500 2 694 400
1.2 Temporary staff 11 500
1.3 Staff training
1.4 Other staff costs and recruitment costs 11 600
1.5 Trainees
2. Support costs 368 000
2.1 Council of Europe services 34 800
2.2 Stationery and office equipment 39 300
2.3 Communications: telephone, fax, mailing 6 400
2.4 costs
Travel 38 200
2.5 Insurances 2 900
2.6 Maintenance 89 500
2.7 Bank charges 1 300
2.8 Premises rental costs 154 100
2.9 Miscellaneous 1 500
3. External services 9 200 268 400
3.1 Translation and proofreading 6 000 197 700
3.2 Layout and print 28 600
3.3 Other services and external assistance 3 200 28 900
3.4 External experts travel and accommodation 13 200
4. costs
Marketing 44 200
4.1 Marketing and promotion 26 600
4.2 Receptions 17 600
5. Documentation 4 800
6. Investments 35 200
6.1 IT Hardware 8 900
6.2 IT Software (purchase and development) 1 500
6.3 Office furniture 19 700
6.4 Office equipment&installation - Sundry investments 5 100
7. Partnership and network 127 900 349 800
7.1 Partnership contracts 40 000
7.2 Collaboration with correspondents, data purchase 127 900 309 800
8. Flexible allocation for unexpected expenses 15 000
Total 467 600 3 802 900
OBS 2024.13-fin EN Budget 2025 - Adopted 2772-6597-9147 v.1
Page 26
BUDGET 2025
Table 10. Activity budget: Expenses, breakdown of the reserve
Reserve Part in
Department/Unit Project / Activity reserve
EUR
Market Information Report on Investments of AV services in original
17 900 100%
European content
Staff missions 1 300 12%
Legal Information Collaboration with correspondents, purchase of data 2 000 35%
Translation and proofreading of IRIS publication(s) 34 500 37%
Legal workshop 10 200 100%
Staff missions 1 400 19%
Transversal projects Subscriptions to professional magazines 500 10%
Visibility Printing of institutional brochures 1 200 100%
Conference in Brussels 9100 100%
Printing and distribution of visibility material 1 000 100%
IT Assistance to IT projects 2 900 100%
Administration Staff missions 700 13%
Flexible allocation 5 000 33%
Total 87 700
OBS 2024.13-fin EN Budget 2025 - Adopted 2772-6597-9147 v.1
Page 27
BUDGET 2025
3.3. Special budget
Table 11. Special budget: Receipts
2023 2024 2025
Final budget Final budget Budget
EUR % EUR % EUR %
EPRA 193 800 100% 206 800 100% 214 500 100%
OBS 2024.13-fin EN Budget 2025 - Adopted 2772-6597-9147 v.1
Page 28
BUDGET 2025
Table 12. Special budget: Expenses
EPRA 2023 2024 2025
Final budget Final budget Budget
EUR % EUR % EUR %
1. Staff 167 800 86,6% 180 300 87,2% 183 500 85,5%
1.1 Permanent staff salaries, soc. charges&pensions 167 800 180 300 133 100
1.2 Temporary staff 50 400
1.3 Staff training
1.4 Other staff costs and recruitment costs
1.5 Trainees
2. Support costs 16 200 8,4% 18 000 8,7% 21 900 10,2%
2.1 Council of Europe services
2.2 Stationery and office equipment 2 600 3 400 2 900
2.3 Communications: telephone, fax, mailing costs 200 200 100
2.4 Travel 6 500 7 400 9 600
2.5 Insurances 100 100 100
2.6 Maintenance 3 300 3 600 6 000
2.7 Bank charges 100 100 100
2.8 Premises rental costs 3 200 3 000 2 900
2.9 Miscellaneous 200 200 200
3. External services 9 800 5,1% 8 500 4,1% 9 100 4,2%
3.1 Translation and proofreading 1 500 1 200 1 200
3.2 Layout and print 100 200 200
3.3 Other services and external assistance 5 200 4 100 3 900
3.4 External experts travel and accommodation 3 000 3 000 3 800
4. costs
Marketing
4.1 Marketing and promotion
4.2 Receptions
5. Documentation
6. Investments
6.1 IT Hardware
6.2 IT Software (purchase and development)
6.3 Office furniture
6.4 Office equipment&installation - Sundry investments
7. Partnership and network
7.1 Partnership contracts
7.2 Collaboration with correspondents, data purchase
8. Flexible allocation for unexpected expenses
Total 193 800 100,0% 206 800 100,0% 214 500 100,0%
OBS 2024.13-fin EN Budget 2025 - Adopted 2772-6597-9147 v.1
Page 29
BUDGET 2025
3.4. Staffing table
3.4.1. Posts and positions
In 2025, the staff complement will remain at 28. On 1 January, the Observatory will have 23
staff employed on permanent contracts, four junior analysts recruited in 2023 under the Young
Professionals programme on contracts limited to a total of four years, and one temporary staff
member, pending the completion of a recruitment procedure.
3.4.2. Assignments
For budget monitoring purposes, the cost of each individual is assigned to a cost centre
(Department or Unit).
The following table shows the cost-centre allocation of the costs of each member of staff. The
contribution of staff participating in the activities of the Contribution Agreement (co-financed
project) included in the budget is indicated by the words “Part. (participation) CA3” in brackets.
When the budget is implemented, the time spent by these staff on Contribution Agreement
activities is subject to precise analytical tracking by profile and activity.
Within the activity budget, the third Contribution Agreement finances a total of 27 person
months of Analysts, i.e. 2.25 staff, 90% of a Senior Analyst and 46% of an IT Project Assistant,
as well as the time devoted to the project by the heads of department and the IT Officer.
EPRA covers all its staff budget costs.
OBS 2024.13-fin EN Budget 2025 - Adopted 2772-6597-9147 v.1
Page 30
BUDGET 2025
Table 13. Staffing table9
(1) Department/ Job Grade Profile Allocation Durati
on
Unit (mont
hs
1 Administration Executive Director A5 Permanent OBS - ADM 12
2 Administration Administrative assistant B3 Permanent OBS - ADM 12
3 Administration Head of Administration A1/A2/A3 Permanent OBS - ADM 12
4 Administration Accountant-assistant B3 Permanent OBS - ADM 12
5 Administration Administrative assistant B3 Permanent OBS - ADM 12
6 DLI Head of Department A4 Permanent OBS - DLI 12
(Part. AC3)
7 DLI Deputy Head of Department A1/A2/A3 Permanent OBS - DLI 12
(Part. AC3)
8 DLI Legal advisor A1/A2/A3 Permanent OBS - DLI 12
(Vacant)10 (Part. AC3)
9 DLI Junior Analyst B3 Junior OBS - DLI 12
professional (Part. AC3)
10 DLI Junior Analyst B3 Junior AC3 - AC3 12
professional (Part. AC3)
11 DLI Junior Analyst B3 Junior AC3 - AC3 6
professional (Part. AC3)
12 DLI Administrative assistant B3 Permanent OBS - DLI 12
13 DMI Head of Department A4 Permanent OBS - DMI 12
(Part. AC3)
14 DMI Deputy Head of Department A1/A2/A3 Permanent OBS - DMI 12
(Part. AC3)
15 DMI Senior Analyst B5 Permanent OBS - DMI 12
(Part. AC3)
16 DMI Senior Analyst B5 Permanent OBS - DMI 12
(Part. AC3)
17 DMI Senior Analyst B5 Permanent OBS - DMI 12
(Part. AC3)
18 DMI Analyst B4 Permanent OBS - DMI 12
(Part. AC3)
(continued on next page)
9
Situation at 1 January 2025.
10
The recruitment procedure, launched in 2024, will be completed in 2025. A temporary member of staff has been
carrying out some of the tasks since September 2024.
OBS 2024.13-fin EN Budget 2025 - Adopted 2772-6597-9147 v.1
Page 31
BUDGET 2025
(2) Department/ Job Grade Profile Allocation Durati
on
Unit (mont
hs
19 DMI Analyst B4 Permanent OBS - DMI 12
(Part. AC3)
20 DMI Junior Analyst B3 Junior AC3 - AC3 12
professional (Part. AC3)
21 DMI Administrative assistant B3 Permanent OBS - DMI 12
22 IT Responsible for Information Technology B511 Permanent OBS - IT 12
(Part. AC3)
23 IT IT assistant (80% FTE) B4 Permanent OBS - IT 12
(Part. AC3)
24 IT IT assistant B4 Permanent OBS - IT 12
(Part. AC3)
25 Visibility Responsible for Communication, Press & B5 Permanent OBS - VIS 12
PR
26 Visibility Administrative assistant B3 Permanent OBS VIS/ADM 12
27 EPRA EPRA Secretary B5 Permanent EPRA 12
28 EPRA Assistant to the EPRA Secretary B4 Permanent EPRA 12
(Vacant)12
11
The post will be reclassified at grade A1/A2/A3 in 2025 with no impact on the 2025 budget.
12
A recruitment procedure to replace the incumbent will be launched at the end of 2024. A temporary member of
staff will take on some of the tasks.
OBS 2024.13-fin EN Budget 2025 - Adopted 2772-6597-9147 v.1
Page 32
Saatja: MESHAYKINA Viktoria <
[email protected]>
Saaja: KUM min,
[email protected],
[email protected]
Teema: European Audiovisual Observatory: Call for Contribution 2025
Dear Sir or Madame,
First of all, I would like to take this opportunity to wish you all the best for 2025!
Please find enclosed letters from Ms Susanne Nikoltchev, Executive Director of the European Audiovisual Observatory.
Kind regards,
Viktoria MESHAYKINA
European Audiovisual Observatory
76 Allée de la Robertsau, 67000 Strasbourg Cedex, France
Tel : +33 (0)3 88 41 24 67
E-mail:
[email protected] <mailto:
[email protected]> , www.obs.coe.int <http://www.obs.coe.int>
COUNCIL OF EUROPE
Observatoire européen de [‘audiovisuel
European Audiovisual Observatory
%,.. Europäische Audiovisuelle Informationsstetle
S•
CONSEIL DE [EUROPE
MINISTRY OF CULTURE & EDUCATION OF
ESTON IA
Suur-Karja 23
15076 TALLINN
Estonia
By email.: min@kuLee
Strasbourg, 2 January 2025
Subject: Cailfor contribution to the budget of the European Audiovisual Observatory for 2025
Dear Sir or Madame,
I have the pleasure of confirming you that, in its meeting of 18 November 2024, the Financial
Committee of the European Audiovisual. Observatory formally adopted the 2025 Observatory
Budget amounting to EUR 4 017 400.
The Budget 2025 of the Observatory is appended.
Please note the mode of payment of members’ contributions, as stated in Articl.e 11, par. 2 and 3 of
the Financial Regul.ations of the Observatory: “Every Member shall pay at least one third of its
compulsory contribution in the course of the first three months of the year. The balance shall be payable
before the end ofa period ofsix months asfrom the date mentioned in the letter callingfor the contribution”.
We would be grateful. if you coul.d transfer to our bank account the contribution for Estonia,
amounting to EUR 4 078,09, within the deadlines l.aid down in the Financial Regul.ations. You
will find hereafter our bank details.
L Bank: Société Généra[e
InternationaL Banking Account Number
— Branch: Strasbourg Europe (02363)
FR76 30003 02363 0005003168923
L!BAN
BIC Bank identification Code SOGEFRPPSTG
PLease do not hesitate to contact the Observatory Secretariat (Sandra Lécaillier, telephone:
+33 (0)3 90 21 60 04, e-mail:
[email protected]) shouLd you need any further information
on the subject.
sincereLy,
Susanne Nikoltchev
Executive Director
Copies to Ms Edith Sepp-Dallas, Eesti Filmi Instituut
Observatoire européen de ‘audiovisue
76 al[ée de La Robertsau 67000 Strasbourg France
— —
Tél. : +33 (0)3 90 21 60 00
[email protected] www.obs.coe.int
—
—