Teema: Fwd: setting-up new PIANC MarCom WG 232 on Metocean-related risks during the
construction of marine works
Manused: image009.jpg; image010.jpg; image011.jpg; image012.jpg; image009.jpg;
image010.jpg; image011.jpg; image012.jpg; LETTER 232docx.pdf; ToR 232 - Metocean
related risk during the construction of Marine works.pdf; LETTER 232docx.pdf; ToR 232 -
Metocean related risk during the construction of Marine works.pdf
From: Sabine Vandevelde <
[email protected]>
Sent: Wednesday, May 27, 2020 12:10:26 PM
To: An Van Schel <
[email protected]>; andythomaspianc <
[email protected]>;
A.Pahl <
[email protected]>; Akula Rao <
[email protected]>; Bridges, Todd S ERDC-EL-
MS (Bridges, Todd S ERDC-EL-MS) <
[email protected]>; CHABRIER Valérie
<
[email protected]>; Ed Schmeltz <
[email protected]>; Wal, Egbert van der
<
[email protected]>; Eric Van den Eede <
[email protected]>; Eslie Vrolijk
<
[email protected]>; Biondi, Esteban <
[email protected]>; Esteban Lefler, Francisco
<
[email protected]>; geert vancappellen (
[email protected])
<
[email protected]>; 菜穂子 林田 <
[email protected]>; hayashida
work (
[email protected]) <
[email protected]>; Ian White
<
[email protected]>; hirasawa-k852a <
[email protected]>; Leen Weltens
<
[email protected]>; Neil Lawson <
[email protected]>; Pansic, Nicholas
<
[email protected]>; m-okada <
[email protected]>; Philippe Rigo (Philippe Rigo)
<
[email protected]>; Matthew Prumm <
[email protected]>; A Zaburtov
(
[email protected]) <
[email protected]>; anna-karin norlin <anna-karin.norling-
[email protected]>; A. Antunes <
[email protected]>; Gema Vázquez Sánchez
<
[email protected]>; 'Ban Hop tac Quoc te' (
[email protected])
<
[email protected]>; benjelloun m <'
[email protected]'>; Beom-koo
(
[email protected]) <
[email protected]>; Bergthora Thorkelsdottir <
[email protected]>; Chan
Dara <
[email protected]>; Bruno Georges <
[email protected]>; Yuan Peng
<
[email protected]>; Mario Germ�n Rodr�guez Viera <
[email protected]>; cwtca
<
[email protected]>; Dinar C. Istiyanto <
[email protected]>; Nybø, Elin Orø
<
[email protected]>; Escalante Raul <
[email protected]>; Fannar Gíslason
<
[email protected]>; Francisco Esteban Lefler <
[email protected]>; AERTS Freddy
<
[email protected]>; Geert Van Cappellen <
[email protected]>; Maria
Graça Neves <
[email protected]>; gucma l <
[email protected]>; gucma m
<
[email protected]>; Hector Estrella Miole <
[email protected]>; indonesia 1
(
[email protected]) <
[email protected]>; indonesia 2
(
[email protected]) <
[email protected]>; indonesia FD3 - Ridwan Djamaluddin
(
[email protected]) <
[email protected]>; iraanse sectie <
[email protected]>;
Mohammad Reza Allahyar <
[email protected]>; James R.D. <
[email protected]>;
Jaroslav Bimka <
[email protected]>; Jens Kirkegaard <
[email protected]>; Jos� Badia
<
[email protected]>; José jairo estrada daza (
[email protected]) <
[email protected]>; Jurong
Port <
[email protected]>; Jurong Port <
[email protected]>; Kaidi Katus
<
[email protected]>; Katrin.Haselbauer <
[email protected]>; Khanzadi
<
[email protected]>; Ljubisa Mihajlovic <
[email protected]>; Luis Eduardo Luvizotto Lolli
<
[email protected]>; Luisa Ottolenghi <
[email protected]>; Magenthran Ruthenavelu
<
[email protected]>; masaki yoneyama (
[email protected])
<
[email protected]>; Michael Behrendt <
[email protected]>;
Wolters, Milou (WVL) <
[email protected]>; Nadia Laraki (
[email protected])
<
[email protected]>; Natalia Suarez <
[email protected]>; Olle Lewis
(
[email protected]) <
[email protected]>; olli.holm <
[email protected]>;
Delgado <
[email protected]>; pianc USA (
[email protected]) <
[email protected]>;
Poolse FD <
[email protected]>; Rogelio Gordon <
[email protected]>; Romeo Ciortan
<
[email protected]>; Paul Scherrer <
[email protected]>; Esa Sirkiä
<
[email protected]>; Steve Kwok <
[email protected]>; s.atanasova <
[email protected]>;
Tran <
[email protected]>; urs.maurer <
[email protected]>; Kayla Waltemire
<
[email protected]>; Velly Indonesia <
[email protected]>; vietnam fd2
<
[email protected]>; Wangsvik Fridtjof <
[email protected]>; Xu Weijia
<
[email protected]>; Vandevoorde Carine <
[email protected]>;
Ana Lope Carvajal <
[email protected]>;
[email protected] <
[email protected]>; chaves
<
[email protected]>; Fabio Zapata <
[email protected]>; fabrice.daly
<
[email protected]>; Buffel Frederik <
[email protected]>; Gabriele.Peschken
<
[email protected]>; William Glamore <
[email protected]>;
Higashiyama S. <
[email protected]>; Hyun Dong Kim <
[email protected]>; yoneda
<
[email protected]>; jmuskatirovic <
[email protected]>; joe manous
(
[email protected]) <
[email protected]>; Johan Boon
<
[email protected]>; Johan en Remi - sec ned sectie <
[email protected]>; laurent.luchez
<
[email protected]>; liina <
[email protected]>; Marisa Ackhurst <
[email protected]>;
Moira Doherty <
[email protected]>; raul oberrauter <
[email protected]>;
sebastian garcia <
[email protected]>; tero sikio <
[email protected]>; Tore
Lundestad <
[email protected]>; Francisco Javier Zapata <
[email protected]>; Zi
Qian Yang <
[email protected]>
Cc: González Patiño, Noelia <
[email protected]>
Subject: setting-up new PIANC MarCom WG 232 on Metocean-related risks during the construction
of marine works
Dear All,
See attached files,
Kind regards,
Sabine Van de Velde
PIANC GENERAL SECRETARIAT
Graaf de Ferraris - 8th Floor
20, Boulevard du Roi Albert II B3 - 1000 Brussels - BELGIUM
Tel: + 32 2 553 71 61
E-mail:
[email protected]
Web: www.pianc.org
PIANC
MarCom WG 232
METOCEAN-RELATED RISKS
DURING THE CONSTRUCTION OF MARINE WORKS
Terms of Reference
1. Historical Background
Waterborne Transport Infrastructure is frequently subject to the effect of
maritime climate action both in service and during construction. This is
typically the case for dredging works, breakwaters, open sea jetties and
dolphins, as well as undersea pipelines and cables, offshore wind farms and
other offshore elements. The many aspects of sea-soil-structure interaction in
this hostile environment add specific risks to those usual in civil construction.
Marine climate is primarily defined by winds, tides, waves and sometimes ice.
Sea climate actions in service are usually analysed in detail at the design
stage both for ultimate and serviceability limit states as well as for operational
performance. However, conditions during construction have a great impact
on cost and construction schedule and can be the source of major delays
and cost overruns with complex contractual implications. These affect risk
sharing between the different agents and to the definition and application of
downtime and force majeure clauses.
Other natural hazards such as earthquakes and tsunamis are less likely to be
determinant during construction although in areas with high seismic activity
need to be considered, taking into consideration the duration of the
construction stage.
2. Objectives of the Working Group
This Working Group will provide a guidance document on marine climate risks
and risk management directly related to the construction stage of projects in
the marine environment.
3. Scope
The Working Group is expected to cover the following topics:
• Sources of uncertainty
• Risk analysis: climate analysis, risks of damage or failure of the works in
progress, impact on construction tolerance and downtime and on
Safety and Health.
• Tools for assessment:
o Available data on sea climate
o Hazard analysis related to the construction period
o Climate forecast for the construction stage
TOR Met-ocean related risks during the construction of Marine Works 1 26-05-2020
oSea-soil structure interaction analytic, numerical and physical
models.
o Simulations of construction processes for analysis
• Design strategies: consideration of construction risks at the design
stage. Resilient design facing construction risks.
• Mitigation strategies at the construction stage:
o Implementation of accurate sea climate forecast procedures
during construction
o Digitization: connected sites with sensors related to wave
climate, equipment and soil and structure response including
temporary elements and during all construction stages. Real
time data analysis is required for achieving efficiency, safety
and reliability
o Review of design improving resilience and reducing damage
probability
o Selection of appropriate equipment
o Selection of best available construction technologies, seasonal
construction, etc.
o Use of statistical simulation techniques in advance to real
construction in order to support the best technical options and
assess the impact of different scenarios on potential cost and
delays as well as the efficiency of mitigation measures.
Scenarios can cover variable climate scenarios and alternatives
for construction schedule, equipment and technologies
• Contractual framework based on appropriate and transparent risk
sharing and a reliable risk management program
• Impact on insurance
• Integrated management of marine climate risk during construction
through the implementation of specific operational integrated systems
• Case studies
4. Existing documents to be reviewed
PIANC MarCom Reports to be reviewed include:
• WG 31-2001 Life-Cycle Management of Port Structures - General
Principles
• WG 103-2008: Life Cycle Management of Port Structures,
Recommended Practice for Implementation
• WG 196-2016: Criteria for the selection of Breakwater types and their
related optimum safe levels
• Finished and ongoing WGs on specialized and multipurpose terminals
• Ongoing WG 194 A Framework for Early Contractor Involvement in
Infrastructure Projects
Other bibliography and Congress papers related to the topic should also be
analysed, including
• Construction Risk in Coastal Engineering, published by Thomas Telford,
London, 1988.
• Construction Health and Safety in Coastal and Maritime Engineering,
Thomas Telford, London, 2005.
TOR Met-ocean related risks during the construction of Marine Works 2 26-05-2020
5. Suggested product of the Working Group
The suggested product of the Working Group will be a guidance document
with recommendations for best practice for construction risk management
and case studies related to sea climate, for owners, designers, contractors
and insurance companies.
6. Desirable Disciplines of the Members of the Working Group
The WG should ideally include owners and concessionaries, engineering
consultants, contractors and dredging companies, insurers, and experts in risk
analysis.
7. Relevance for Countries in Transition
The report will be valuable for the development of port infrastructure in
countries in transition helping in mitigation of construction risks and their
undesired effects.
8. Climate Change Considerations
The probability and magnitude of extreme events during the construction
stage cannot be estimated only on the basis of conditions during previous
decades, and should allow for the tendency for future extreme events to be
more severe even in the short term. Nevertheless major relevant features of
climate change such as sea level rise, increased storminess, more severe
precipitation events and higher temperatures are generally related to a much
longer time frame than the construction stage and will not necessarily be
relevant.
9. Relevance to UN Sustainable Development Guidelines
The guideline will contribute to the Sustainable Development Goals (SDGs)
approved by the United Nations in 2015, particularly the development of
quality, reliable, sustainable and resilient infrastructure (SDG9).
TOR Met-ocean related risks during the construction of Marine Works 3 26-05-2020
PIANC
MarCom WG 232
METOCEAN-RELATED RISKS
DURING THE CONSTRUCTION OF MARINE WORKS
Terms of Reference
1. Historical Background
Waterborne Transport Infrastructure is frequently subject to the effect of
maritime climate action both in service and during construction. This is
typically the case for dredging works, breakwaters, open sea jetties and
dolphins, as well as undersea pipelines and cables, offshore wind farms and
other offshore elements. The many aspects of sea-soil-structure interaction in
this hostile environment add specific risks to those usual in civil construction.
Marine climate is primarily defined by winds, tides, waves and sometimes ice.
Sea climate actions in service are usually analysed in detail at the design
stage both for ultimate and serviceability limit states as well as for operational
performance. However, conditions during construction have a great impact
on cost and construction schedule and can be the source of major delays
and cost overruns with complex contractual implications. These affect risk
sharing between the different agents and to the definition and application of
downtime and force majeure clauses.
Other natural hazards such as earthquakes and tsunamis are less likely to be
determinant during construction although in areas with high seismic activity
need to be considered, taking into consideration the duration of the
construction stage.
2. Objectives of the Working Group
This Working Group will provide a guidance document on marine climate risks
and risk management directly related to the construction stage of projects in
the marine environment.
3. Scope
The Working Group is expected to cover the following topics:
• Sources of uncertainty
• Risk analysis: climate analysis, risks of damage or failure of the works in
progress, impact on construction tolerance and downtime and on
Safety and Health.
• Tools for assessment:
o Available data on sea climate
o Hazard analysis related to the construction period
o Climate forecast for the construction stage
TOR Met-ocean related risks during the construction of Marine Works 1 26-05-2020
oSea-soil structure interaction analytic, numerical and physical
models.
o Simulations of construction processes for analysis
• Design strategies: consideration of construction risks at the design
stage. Resilient design facing construction risks.
• Mitigation strategies at the construction stage:
o Implementation of accurate sea climate forecast procedures
during construction
o Digitization: connected sites with sensors related to wave
climate, equipment and soil and structure response including
temporary elements and during all construction stages. Real
time data analysis is required for achieving efficiency, safety
and reliability
o Review of design improving resilience and reducing damage
probability
o Selection of appropriate equipment
o Selection of best available construction technologies, seasonal
construction, etc.
o Use of statistical simulation techniques in advance to real
construction in order to support the best technical options and
assess the impact of different scenarios on potential cost and
delays as well as the efficiency of mitigation measures.
Scenarios can cover variable climate scenarios and alternatives
for construction schedule, equipment and technologies
• Contractual framework based on appropriate and transparent risk
sharing and a reliable risk management program
• Impact on insurance
• Integrated management of marine climate risk during construction
through the implementation of specific operational integrated systems
• Case studies
4. Existing documents to be reviewed
PIANC MarCom Reports to be reviewed include:
• WG 31-2001 Life-Cycle Management of Port Structures - General
Principles
• WG 103-2008: Life Cycle Management of Port Structures,
Recommended Practice for Implementation
• WG 196-2016: Criteria for the selection of Breakwater types and their
related optimum safe levels
• Finished and ongoing WGs on specialized and multipurpose terminals
• Ongoing WG 194 A Framework for Early Contractor Involvement in
Infrastructure Projects
Other bibliography and Congress papers related to the topic should also be
analysed, including
• Construction Risk in Coastal Engineering, published by Thomas Telford,
London, 1988.
• Construction Health and Safety in Coastal and Maritime Engineering,
Thomas Telford, London, 2005.
TOR Met-ocean related risks during the construction of Marine Works 2 26-05-2020
5. Suggested product of the Working Group
The suggested product of the Working Group will be a guidance document
with recommendations for best practice for construction risk management
and case studies related to sea climate, for owners, designers, contractors
and insurance companies.
6. Desirable Disciplines of the Members of the Working Group
The WG should ideally include owners and concessionaries, engineering
consultants, contractors and dredging companies, insurers, and experts in risk
analysis.
7. Relevance for Countries in Transition
The report will be valuable for the development of port infrastructure in
countries in transition helping in mitigation of construction risks and their
undesired effects.
8. Climate Change Considerations
The probability and magnitude of extreme events during the construction
stage cannot be estimated only on the basis of conditions during previous
decades, and should allow for the tendency for future extreme events to be
more severe even in the short term. Nevertheless major relevant features of
climate change such as sea level rise, increased storminess, more severe
precipitation events and higher temperatures are generally related to a much
longer time frame than the construction stage and will not necessarily be
relevant.
9. Relevance to UN Sustainable Development Guidelines
The guideline will contribute to the Sustainable Development Goals (SDGs)
approved by the United Nations in 2015, particularly the development of
quality, reliable, sustainable and resilient infrastructure (SDG9).
TOR Met-ocean related risks during the construction of Marine Works 3 26-05-2020
PIANC
The World Association for
Brussels, 27 May 2020.
Waterborne Transport Infrastructure
To the First Delegates of the
Qualifying Members of PIANC
To the National Sections’
Secretaries of PIANC
To the Platinum Partners of PIANC
To The Sister Associations of PIANC
Subject: Setting up of a new PIANC Working Group 232 on “Metocean-related risks during the
construction of marine works”
Dear Madam,
Dear Sir,
The setting up of a Joint PIANC MarCom Working Group 232 on “Metocean-related risks during the
construction of marine works”, has duly been approved as well as its terms of reference, which are
herewith enclosed.
We kindly ask you to inform the secretariat of MarCom by 1 August 2020 (copy to the General Secretariat)
about the name, qualification and (e-mail-) address of the expert, proposed by your country/organisation.
Please enclose a brief curriculum vitae of the proposed expert together with some details about her/his
professional experiences.
An additional expert per country/organisation, being a young professional, can participate in the Working
Group activities. Further I would like to remind you that Working Group Members should either be Individual
Member of PIANC, working for a Corporate Member or Platinum Partner, be an invited expert or a be a
member of a Sister Organisation.
We remind you that in accordance with PIANC rules, the costs incurred in taking part in Working Group
activities are borne by the member countries/organizations.
We thank you beforehand for your collaboration.
Yours sincerely,
Geert Van Cappellen,
Secretary-General.
Reply to:
Ms Noelia Gonzalez
[email protected]
PIANC
The World Association for
Brussels, 27 May 2020.
Waterborne Transport Infrastructure
To the First Delegates of the
Qualifying Members of PIANC
To the National Sections’
Secretaries of PIANC
To the Platinum Partners of PIANC
To The Sister Associations of PIANC
Subject: Setting up of a new PIANC Working Group 232 on “Metocean-related risks during the
construction of marine works”
Dear Madam,
Dear Sir,
The setting up of a Joint PIANC MarCom Working Group 232 on “Metocean-related risks during the
construction of marine works”, has duly been approved as well as its terms of reference, which are
herewith enclosed.
We kindly ask you to inform the secretariat of MarCom by 1 August 2020 (copy to the General Secretariat)
about the name, qualification and (e-mail-) address of the expert, proposed by your country/organisation.
Please enclose a brief curriculum vitae of the proposed expert together with some details about her/his
professional experiences.
An additional expert per country/organisation, being a young professional, can participate in the Working
Group activities. Further I would like to remind you that Working Group Members should either be Individual
Member of PIANC, working for a Corporate Member or Platinum Partner, be an invited expert or a be a
member of a Sister Organisation.
We remind you that in accordance with PIANC rules, the costs incurred in taking part in Working Group
activities are borne by the member countries/organizations.
We thank you beforehand for your collaboration.
Yours sincerely,
Geert Van Cappellen,
Secretary-General.