Sissetulev kiriAvalik
Kiri
Veeteede Amet · 16. juuli 2019
- Viit
- 6-1-6/1656
- Registreeritud
- 16. juuli 2019
- Dokumendi liik
- Sissetulev kiri
- Adressaat
- Balticconnector
- Saabumis/saatmisviis
- e-post
- Funktsioon
- 6-1 Navigatsiooni korraldamine
- Sari
- 6-1-6 Kirjavahetus navigatsiooniteabe küsimustes
- Toimik
- 6-1-6/2019
- Vastutaja
- Darja Jokk (Veeteede Amet, Kasutajad, Hüdrograafia ja navigatsioonimärgistuse teenistus, Kartograafiaosakond)
Sisu (failidest)
Saatja: Olavi Heinlo
Saatmisaeg: 16. juuli 2019 9:56
Adressaat: Darja Jokk
Koopia: Kaidi Katus
Teema: FW: Balticconnector offshore pipeline construction work in the
sea
completed
Tere Darja!
Palun t�hista navigatsioonihoiatus Baltic Connectori ehitust��de kohta
ja v�ta �hendust Priit Heinla-ga,
et selgitada, millal saame teostusjoonised ning kas seoses Baltic
Connectori ehitamisega paigaldatud
veelaused seadmed (Hoiatus nr 41) on samuti eemaldatud v�i on need
endiselt asukohtades.
T�nan!
Olavi
From: Kaidi Katus
Sent: Tuesday, July 16, 2019 9:41 AM
To: Olavi Heinlo <[email protected]>; Kert S�smalainen
<[email protected]>
Subject: Ed: Balticconnector offshore pipeline construction work in the
sea completed
Olavi, selle teate alusel v�ib vast hoiatuse maha v�tta.
Kaidi
Saatja: Mauno Napari [mailto:[email protected]]
Saatmisaeg: Tuesday, July 16, 2019 9:05 AM
Adressaat: Kaidi Katus <[email protected]>
Teema: Balticconnector offshore pipeline construction work in the sea
completed
Balticconnector offshore pipeline construction
work in the sea completed
Construction work in the sea for the Balticconnector project offshore
pipeline was completed Friday 12
July 2019. Pipe laying was finished at the end of June, and the shielding
work was begun in mid-June.
Now that the shielding work has been finished, all construction work in
the sea has been completed. Next,
the offshore pipeline will be pressure-tested in July-August, after which
the pipeline will be emptied and
dried.
"We are satisfied that the construction work for the offshore pipeline
has progressed on schedule and that
we can begin the final phases of the pipeline according to plan. We are
progressing at a good pace
towards the end of the year when the pipeline will be commissioned," says
Tom Fr�mling, Baltic
Connector Oy's Project Director.
The offshore pipeline will be connected to the onshore pipelines in
Finland and Estonia during the
autumn. The Balticconnector pipeline will be fully ready at the end of
2019, and gas will start to flow in the
pipeline on 1 January 2020 as the Finnish gas market opens.
Hyv�� kes��,
T. Manu
Yours sincerely
Mauno Napari
Project Manager
Offshore Pipeline, Owners Engineering
Porkkalankatu 1, FI-00180 Helsinki
+358 40 5955 567
[email protected]
www.balticconnector.fi