Estonian EU External Border Programme
2014-2020
Project No: ER58
Project full name: Increasing entrepreneurial culture and
competitivess among artisans and
craftsmen in Võru and Pskov
Project acronym: BestNest
Project Partner Name (LP) Võru Town Government
Thematic objective: TO 1 Business and SME development
Audit No: EVP-13/2024
Audited organization: Võru Town Government
Final audit report
13.09.2024
SUMMARY OF AUDIT RESULTS
Audit outcome:
Based on the audit work performed, the auditors have obtained reasonable assurance that the
expenditure declared is in all material aspects legal and regular and in compliance with the programme
rules apart several significant and non-significant findings related to non-compliance with national
procurement laws.
Audit opinion 1 :
significant and non-significant findings
List of significant findings:
4.1.1 Non-significant finding – Eco friendliness criteria has not been met
4.1.2 Non-significant finding – Insufficient rules to ensure avoiding conflicts of interest
4.1.3 Non-significant finding– Not enough time was given for submission of tenders after modifying
the basic documents through clarification
4.2.1 Non-significant finding – Tenderer warrant was not requested
4.2.2 Non-significant finding – The beneficiary has not requested evidence about the average salary
the employees of the tenderer
4.2.3 Non-significant finding – Subcontractors absence of grounds for elimination was not verified
4.2.4 Non-significant finding – Insufficient rules to ensure avoiding conflicts of interest
4.2.5 Non-significant finding – Decision not to subdivide the procurement into parts within the
proceedings was not stated in the procurement documents
4.2.6 Significant finding – Clarifications were not submitted within the timeframe set by law
4.2.7 Significant finding – Not enough time was given for submission of tenders after modifying the
basic documents
4.2.8 Significant finding – The Beneficiary has not verified the successful tenderer’s compliance
4.3.1 Non-significant finding – Tenderer warrant was not requested
4.3.2 Non-significant finding – Insufficient rules to ensure avoiding conflicts of interest
1
Sig nificant findings are those that have or may have a financial impact (i.e. ineligible expenditure). Non-significant findings are those that have no financial
impact but whose correction will help the beneficiary to lower risks while implementing the project.
2
4.3.3 Non-significant finding – Subcontractors absence of grounds for elimination was not verified
4.3.4 Non-significant finding – Procurement contract has been fulfilled in a different way from the
original conditions
4.3.5 Non-significant finding – Decision not to subdivide the procurement into parts within the
proceedings was not stated in the procurement documents
The project audit has been carried out in compliance with the International Standards for the Professional Practice
of Internal Auditing.
We wish to thank the auditee for the assistance and cooperation provided during the audit.
We confirm that the final audit report consists of 17 pages.
3
TABLE OF CONTENTS
SUMMARY OF AUDIT RESULTS..................................................................................................................................................2
TABLE OF CONTENTS..................................................................................................................................................................4
PART A............................................................................................................................................................................................5
1. AUDIT OBJECT AND AUDITED EXPENSES ........................................................................................ 5
2. LIMITATIONS ........................................................................................................................ 6
3. AUDIT FOLLOW-UP ACTIVITIES ................................................................................................... 7
PART B............................................................................................................................................................................................8
AUDIT FINDINGS......................................................................................................................... 8
4.1 Public procurement 263351 findings............................................................................................................................8
4.1.1 Non-significant finding – Eco friendliness criteria has not been met....................................................................8
4.1.2 Non-significant finding – Insufficient rules to ensure avoiding conflicts of interest ...........................................9
4.1.3 Non-significant finding– Not enough time was given for submission of tenders after modifying the basic
documents through clarification..........................................................................................................................................9
4.2 Public procurement 236205 findings......................................................................................................................... 10
4.2.1 Non-significant finding – Tenderer warrant was not requested.......................................................................... 10
4.2.2 Non-significant finding – The beneficiary has not requested evidence about the average salary of the
employees of the tenderer................................................................................................................................................. 10
4.2.3 Non-significant finding – Subcontractors absence of grounds for elimination was not verified .................... 11
4.2.4 Non-significant finding – Insufficient rules to ensure avoiding conflicts of interest ........................................ 11
4.2.5 Non-significant finding – Decision not to subdivide the procurement into parts within the proceedings was
not stated in the procurement documents...................................................................................................................... 12
4.2.6 Significant finding – Clarifications were not submitted within the timeframe set by law................................ 12
4.2.7 Significant finding – Not enough time was given for submission of tenders after modifying the basic
documents .......................................................................................................................................................................... 13
4.2.8 Significant finding – The Beneficiary has not verified the successful tenderer’s compliance......................... 14
4.3 Public procurement 259004 findings......................................................................................................................... 15
4.3.1 Non-significant finding – Tenderer warrant was not requested.......................................................................... 15
4.3.2 Non-significant finding – Insufficient rules to ensure avoiding conflicts of interest ........................................ 15
4.3.3 Non-significant finding – Subcontractors absence of grounds for elimination was not verified .................... 15
4.3.4 Non-significant finding – Procurement contract has been fulfilled in a different way from the original
conditions............................................................................................................................................................................ 16
4.3.5 Non-significant finding – Decision not to subdivide the procurement into parts within the proceedings was
not stated in the procurement documents...................................................................................................................... 16
4
PART A
1. Audit object and audited expenses
1.1 GENERAL INFORM ATION AB OUT THE AUDIT
P roject na me: Increasing entrepreneurial culture and competitivess among
artisans and craftsmen in Võtu and Pskov
P roject a cronym: BestNest
P roject number: ER58
Stra tegic a nd thema tic objective: TO 1 Business and SME development
B eneficia ry a udited (L P ): Võru Town Government
Conta ct person of the beneficia ry: Kait Kabun
Da te of subsidy contra ct: 21.08.2020
Audit scope a nd period: 01.09.2020-31.08.2023
1.2 INFORM ATION AB OUT THE AUDIT
B a sis: - Agreement on financing and implementation of Cross-
Border Cooperation Programme “Estonia-Russia” 2014-
2020
- Audit Authority’s work plan for 2024.
Objective: To provide an audit opinion that:
- the operation was selected in accordance with the
selection criteria for the cross-border programme.
- the expenditure declared to the participating nations and
the Commission corresponds to the accounting records
and that the required supporting documentation
demonstrates an adequate audit trail.
- for expenditure declared to the participating nations and
the Commission, outputs and results underpinning
payments to the beneficiary have been delivered.
P erson(s) ca rrying out the a udit: Indrek Alliksaar, KPMG Baltics OÜ, Auditor
Tanel Kullison, KPMG Baltics OÜ, Auditor
Liina Lember, KPMG Baltics OÜ, Auditor
Maarja Mändmaa, KPMG Baltics OÜ, Auditor
Kärt Kibus, KPMG Baltics OÜ, Auditor
Audit dura tion: 21.06.2024 – 13.09.2024
M ethodology: Audit manual of the Estonia-Russia Programme
5
Audit procedures performed a t the During the on-the-spot check, interviews were conducted with
beneficia ry a udited: the persons involved in project implementation and
analysis/evaluation was made of the following:
- project’s actual implementation.
- documentation related to project implementation.
- eligibility of costs.
- arrangement of book-keeping related to the project.
- existence of co-financing.
- use of the logos.
Sa mpling methodology (if applicable, then - population size: EUR 377 708,93
information shall be provided by the Audit
- sampling method: Monetary Unit Sampling
Authority):
1.3 AUDITED EX P ENSES
Total amount of certified expenses subject 01.09.2020-31.08.2023, EUR 377 708,93
to auditors’ opinion on the ba sis of cost
documents:
Size of the sa mple (EUR; %) 2 : EUR 353 015,99, 93,5%
Ineligible expenditure identified (EUR): a mount
Na tiona l
EU P rivate sector
public Tota l
contribution contribution
contribution
Ineligible a mount (EUR): 0 0 0 0
Ineligible amount outside the a udit scope 0 0 0 0
(EUR):
Error ra te (%) 3 : 0%
2. Limitations
The audit procedures were carried out in compliance with internationally accepted auditing standards4 and the audit
report was prepared using the principles of independence and objectivity.
Auditors conclude that all data presented during the audit and other oral and written information made available
during the audit presents a true and fair view of the activities performed during the project implementation and are
sufficient to provide an opinion about the project. In case of additional information that was not provided or was not
known to auditors, the conclusions reached by auditors might have been different.
2
If a sample was not used for auditing, the size of the sample is the total population in euros and the share of audited expenses to total population is 100%.
3
Share of ineligible expenses to audited expenses (%). If a sample was used for auditing, the share of ineligible expenses to the sample size shall be used.
4
The International Professional Practices Framework (IPPF) of the Institute of Internal Auditors.
6
3. Audit follow-up activities
The beneficiary shall take into account the findings and recommendations made in Part B and the decisions made
by the Managing Authority. The Audit Authority shall monitor the implementation of recommendations made by the
auditors.
7
PART B
AUDIT FINDINGS
1. Use of funding as intended
The funding has been used in material aspects in the intended manner, in a reasonable and efficient way and in
accordance with the objectives and requirements laid down in the subsidy contract and the programme manual
apart from several findings related to non-compliance with national procurement laws.
2. Accuracy of book-keeping records
The book-keeping records for the project are in all material aspects in compliance with the current legislation.
3. Amount and timing of funding
The granting of funding has in all material aspects been made available in the amount foreseen and on time, and the
co-financing has been guaranteed.
4. Carrying out of public procurements
The beneficiary has not carried out public procurements in compliance with the current legislation.
4.1 Public procurement 263351 findings
Võru Linnavalitsus launched an open procurement no 263351 “Loomekoja sisustuse ost” in the Public Procurement
Registry on 13th April 2023. As a result of the procurement a contract no 321 was concluded with Saloni Büroomööbli
AS (10289177) to buy furniture.
4.1.1 Non-significant finding – Eco friendliness criteria has not been met
According to § 77 section 61 of the Public Procurement Act criteria: Where eco friendliness criteria have been set to
supplies or services that constitute the subject matter of the public contract, the procurement documents must
contain terms and conditions that take into account the energy and environmental impact throughout the service
life.
The eco friendliness criteria have been established for furniture by a regulation issued by the Minister of the
Environment 5.
The Beneficiary has not been in compliance with § 77 section 61 of the Public Procurement Act by failing to add
mandatory environmentally friendly terms in procurement documents. Mandatory environmentally friendly terms are
set out in Annex 1 to Regulation No 35 of the Minister for the Environment.
5 https://www.riigiteataja.ee/dynaamilised_lingid.html?dyn=123022023007&id=102072021013;121022023005
8
Risk to the project implementation: If the beneficiary does not comply with the laws and regulations it may result in
ineligible costs to the project.
Recommendation on the project implementation: We recommend following regulation issued by the Minister of the
Environment and Public Procurement Act.
4.1.2 Non-significant finding – Insufficient rules to ensure avoiding conflicts of interest
According to § 3 clause 4 of the Public Procurement Act criteria: the authority or the entity avoids a competition-
distorting conflict of interest.
The internal rules for procurement are not sufficient to ensure substantive measures to avoid conflicts of interest
set out in Public Procurement Act § 3 clause 4, as the members of the procurement committee are not required to
confirm the absence of conflicts of interest in writing forms or in document management system, which is contrary
to the transparency and verifiability principles set out in § 3 clause 1.
According to the audit’s assessment this is a non-significant finding, as an indirect measure to prevent conflicts of
interest is established in clause 22 of the procurement regulations, and no connections between the members of the
procurement committee and the tenderers were identify.
Risk to the project implementation: If the beneficiary does not ensure sufficient measures to avoid conflicts of interest
in internal procurement rules it may result in ineligible costs to the project.
Recommendation on the project implementation: We recommend establishing a rule in procurement regulation or
another internal document, requiring members of the procurement committee to confirm the absence of conflicts
of interest in writing, either in the document management system, through a separate confirmation letter, or in the
Public Procurement Register.
4.1.3 Non-significant finding– Not enough time was given for submission of tenders after
modifying the basic documents through clarification
According to § 46 section 3 of the Public Procurement Act criteria: Clarifications or documents allowing for
clarification submitted regarding procurement documents must not contain new information without which it is not
possible to submit tenders or without which the submitted tenders would become non-compliant with the
procurement documents or their content would change. It is prohibited to modify the procurement documents based
on the clarifications and documents allowing for clarification.
The Beneficiary has not been in compliance with § 46 section 3 of the Public Procurement Act by submitting
clarifications which contained more detailed information without following the procedure established in the Public
Procurement Act § 81. The Beneficiary has given more detailed information by answering questions ID736811ja
ID737710.
According to the audit’s assessment this is a non-significant finding. The State Shared Service Centre has explained
it with following arguments we agree with:
The information contained in the response ID 736811 given by the contracting authority, that Teraslehte tööpinna
peal ei tule ja infoleti fassaad on sile Toronto Elm, is presented in the drawing "Ruum 113 infolett". Since the written
notes on the drawing and the drawing itself have been ambiguous, the contracting authority has explained which
requirement should be considered more precisely. Therefore, it is not a question of the contracting authority
providing new substantive information that was not included in the procurement documents, but a clarification,
which the tenderers had to use in case of differences in the procurement documents.
This is also the case with response ID 737710, where the information provided by the contracting authority was
included in various drawings (“RUUM 101 SEINAKAPP RIIULITE ja TEHNIKA”, “RUUM 112 SEINAKAPP”, “RUUM 113
VITRIINKAPP” and “RUUM 113 INFOLETT”) and in the text notes of these drawings. Since the written notes and the
9
drawings itself were somewhat ambiguous, the contracting authority explained which information should prevail,
thus not providing new information. At this point, it must also be emphasized that the subsection 3 of section 46 of
Public Procurement Act prohibits the provision of such new information, 1) without which it is not possible to submit
tenders or 2) without which the submitted tenders would become non-compliant with the procurement documents
or 3) their content would change. The contracting authority has merely explained in subsection 4 of response ID
737710 his preferences regarding the content of the box. However, the tenderer's offer would have been equivalent
in any case if he had offered any set of sockets Simon Ofiblock Line K45. In addition, it is not possible to claim that
the contents of the box would change the cost of the tenders.
This finding was changed from significant to non-significant after additional relevant information and explanations
were provided by the auditee and Programme authorities.
Risk to the project implementation: If the competition is not effectively used, it may result in the project’s goals not
being achieved at the best possible price.
Recommendation on the project implementation: We recommend following Public Procurement Act so that any
indirect conflict with § 46 section 3 be avoided in the future.
4.2 Public procurement 236205 findings
Võru Linnavalitsus launched an open procurement no 236205 “Loomekoja ehitamine” in the Public Procurement
Registry on 14th May 2021. As a result of the procurement a contract no 447 was concluded with Lasten Ehitus OÜ
(14048507) to reconstruct the existing manufactory suitable for the activities of Loomekoda.
4.2.1 Non-significant finding – Tenderer warrant was not requested
According to § 122 section 3 of the Public Procurement Act criteria: In the case of a public works contract or works
concession, the contracting authority or entity requires in the procurement documents that the tenderer warrant in
their tender that they will not enlist, in the performance of the contract, a subcontractor who would be subject to
replacement under subsection 7 of this section.
The Beneficiary has not been in compliance with § 122 section 3 of the Public Procurement Act by failing to request
tenderer warrant in their tender.
Risk to the project implementation: If the beneficiary does not comply with the laws and regulations it may result in
ineligible costs to the project.
Recommendation on the project implementation: We recommend following Public Procurement Act.
4.2.2 Non-significant finding – The beneficiary has not requested evidence about the average
salary of the employees of the tenderer
According to § 115 section 2 clause 2 of the Public Procurement Act criteria: In the case of a public works contract
or a works concession whose estimated value equals or exceeds the public procurement threshold, the contracting
authority or entity is required to ask the tenderer whose tender it intends to declare suitable for a clarification
specified in subsection 1 of this section where: 2) the average salary of the employees of the tenderer or the
subcontractors specified in its tender was during the reference period less than 70 per cent of the average salary in
the same period in the field corresponding to the subject-matter of the public contract.
According to § 115 section 3 of the Public Procurement Act criteria: In order to identify the circumstances provided
for in clause 2 of subsection 2 of this section, the contracting authority or entity requires the tenderer to submit
within a reasonable time limit set by the contracting authority or entity such a certificate issued by the competent
authority of the country where the tenderer and the subcontractor specified in the tender is established, which
contains the following information:
10
1) the average salary paid by the tenderer during the reference period;
2) the average salary of each subcontractor specified in the tender during the reference period;
3) the average salary during the reference period in the field corresponding to the subject-matter of the public
contract in the country where the tenderer and the subcontractor specified in the tender are established.
The Beneficiary has not requested the evidence specified in § 115 section 3 from the successful tenderer in the
public procurement no 236205, thereby preventing the procurer from verifying whether the tenderer is not in the
situation referred in § 115 section 2 and seeking clarification thereon.
Risk to the project implementation: If the beneficiary does not comply with the laws and regulations it may result in
ineligible costs to the project.
Recommendation on the project implementation: We recommend following Public Procurement Act.
4.2.3 Non-significant finding – Subcontractors absence of grounds for elimination was not verified
According to § 122 section 5 of the Public Procurement Act criteria: In the case of a public works contract or works
concession, the contracting authority or entity verifies, during procurement proceedings, the inapplicability of
grounds for exclusion mentioned in subsection 1 of § 95 of this Act – or, in the fields of defense and security, in
clauses 1, 4 or 5 of that subsection – regarding the subcontractors mentioned in the successful tenderer’s tender
and, following the award of the contract, regarding any subcontractor who is added in the course of its performance.
Such verification is not required in a negotiated procedure without prior publication or during performance of the
contract awarded as a result of that procedure. The Beneficiary has not been in compliance with § 122 section 3 of
the Public Procurement Act by failing to require tenderer warrant in their tender.
There is no evidence to ascertain whether the contracting authority has verified all the absence of grounds for
elimination of the subcontractors added after the conclusion of the procurement contract based on § 122 section 5
of the Public Procurement Act.
Risk to the project implementation: If the beneficiary does not comply with the laws and regulations it may result in
ineligible costs to the project.
Recommendation on the project implementation: We recommend following Public Procurement Act.
4.2.4 Non-significant finding – Insufficient rules to ensure avoiding conflicts of interest
According to § 3 clause 4 of the Public Procurement Act criteria: the authority or the entity avoids a competition-
distorting conflict of interest.
The internal rules for procurement are not sufficient to ensure substantive measures to avoid conflicts of interest
set out in Public Procurement Act § 3 clause 4, as the members of the procurement committee are not required to
confirm the absence of conflicts of interest in writing forms or in document management system, which is contrary
to the transparency and verifiability principles set out in § 3 clause 1.
According to the audit’s assessment this is a non-significant finding, as an indirect measure to prevent conflicts of
interest is established in clause 22 of the procurement regulations, and no connections between the members of the
procurement committee and the tenderers were identify.
Risk to the project implementation: If the beneficiary does not ensure sufficient measures to avoid conflicts of interest
in internal procurement rules it may result in ineligible costs to the project.
Recommendation on the project implementation: We recommend establishing a rule in procurement regulation or
another internal document, requiring members of the procurement committee to confirm the absence of conflicts
of interest in writing, either in the document management system, through a separate confirmation letter, or in the
Public Procurement Register.
11
4.2.5 Non-significant finding – Decision not to subdivide the procurement into parts within the
proceedings was not stated in the procurement documents
According to § 27 section 2 of the Public Procurement Act criteria: Where a public procurement, which has not been
divided into parts within the proceedings and whose estimated value equals or exceeds the public procurement
threshold – or the international threshold, where this Act does not provide a threshold for such a procurement – the
contracting authority or entity states, in the procurement documents, the reasons for its decision not to subdivide
the procurement into parts within the proceedings. The duty to state the reasons does not apply if the public contract
is awarded under a framework agreement or based on a dynamic purchasing system.
The Beneficiary has not stated in procurement documents the reasons for its decision not to subdivide the
procurement into parts within the proceedings. The Beneficiary has stated the reasons in the protocol of approval
of basic documents which is not publicly available on Public Procurement nor in the public procurer's document
management register.
According to the audit’s assessment this is a non-significant finding. The State Shared Service Centre has explained
it with following arguments we agree with:
According to the explanatory letter of the Public Procurement Act, the contracting authority can only be criticized if
his justification is not substantial. However, whether the reasons are expedient and relevant cannot be contested.
Therefore, there are no specific rules regarding the possible content and scope of justifications. In the commented
edition of the Public Procurement Act, it has been found regarding subsection 2 of section 27 of the Public
Procurement Act, that such a reason may consist in the fact that the subdivision of the public procurement into lots
makes the performance of the contract excessively complicated or costly, or the need to coordinate the activities of
the contractors of the different parts may seriously threaten the proper performance of the contract (Directive
2014/24/EU recital 78). According to the explanatory letter of the Public Procurement Act, the subdivision of the
public procurement into lots in construction comes into question only if the separate lots are functioning
independently and the building can be used even if the construction of some parts is stuck. In this particular case,
one “creative house” was established, that is, one building, which means that the contracting authority ordered one
complete solution. If the public procurement was divided into lots, several contractors would have had to operate on
one work site at the same time, and the contracting authority himself would have had to take on the role of project
manager. The existence of such competence, however, cannot be expected from the contracting authority, which is
why it is justified to order the entire construction work of the building from one contractor.
Summing up all of the above, making a financial correction is not justified. This finding was changed from significant
to non-significant after additional relevant information and explanations were provided by the auditee and
Programme authorities.
Risk to the project implementation: If the beneficiary does not comply with the laws and regulations it may result in
ineligible costs to the project. The State Shared Service Centre has applied financial corrections to the maximum
extent (25%), which covers the identified deficiencies. Additional corrections are not recommended as a result of
procurement verification.
Recommendation on the project implementation: We recommend following Public Procurement Act.
4.2.6 Significant finding – Clarifications were not submitted within the timeframe set by law
According to § 46 section 1 of the Public Procurement Act criteria: The contracting authority or entity makes
clarifications pertaining to procurement documents, or documents that allow for clarification, electronically available
within three working days following receipt of a corresponding request for clarification. Where the entire public
procurement communication and information exchange does not take place electronically, the authority or entity
submits clarifications or documents allowing for clarification within the same time limit to all of the economic
operators interested in the public procurement, which are known to the authority or entity, in a form reproducible in
writing.
12
The Beneficiary has not been in compliance with § 46 section 1 of the Public Procurement Act by submitting
clarifications later than three working days in seven cases and not answering clarification at all in one case.
In our opinion answering questions ID 594122, ID 592884, ID 592873, ID 592717, ID 592625, ID 592622, ID 592377
does not constitute as significant violation as there were more than 6 days remaining before the deadline for
submitting tenders after the contracting authority’s response.
A significant violation is not answering clarification ID 593062 at all and answering timely submitted clarification ID
595581 with delay and only 3 days remained before the deadline for submitting offers.
In accordance with Annex 1 p. 2.1 subsection 4 of the European Commission's 14.05.2019 violation guide No.
C(2019) 3452, a 10 percent financial correction rate must be applied if the tender receipt deadline is not extended
and the procurement documents are significantly changed.
Risk to the project implementation: Competition was not effectively used, resulting in the project’s goals not being
achieved at the best possible price. The State Shared Service Centre has applied financial corrections to the
maximum extent (25%), which covers the identified deficiencies. Additional corrections are not recommended as a
result of procurement verification.
Recommendation on the project implementation: We recommend following Public Procurement Act.
Comments of the beneficiary audited: Jääme teiste tähelepanekute puhul oma varasemalt antud seisukohtade juurde.
Me ei pidanud vajalikuks nende kohta esitada oma seisukohta põhjusel, et isegi kui asuda seisukohale rikkumise
esinemise osas, on need rikkumised kaetud varasemalt meile määratud finantskorrektsiooniga.
Comments of the Financial Control and Managing Authority/Joint Technical Secretariat: We agree with the finding, and
we have also drawn the beneficiary’s attention to said deficiencies during the procurement inspection and according
financial correction has been applied.
4.2.7 Significant finding – Not enough time was given for submission of tenders after modifying
the basic documents
According to § 46 section 3 of the Public Procurement Act criteria: Clarifications or documents allowing for
clarification submitted regarding procurement documents must not contain new information without which it is not
possible to submit tenders or without which the submitted tenders would become non-compliant with the
procurement documents or their content would change. It is prohibited to modify the procurement documents based
on the clarifications and documents allowing for clarification.
The Beneficiary has not been in compliance with § 46 section 3 of the Public Procurement Act by submitting
clarifications which contained new information without following the procedure established in the Public
Procurement Act § 81. The Beneficiary has given new information by answering questions ID 597046, 595665,
595581, 594858. 594702, 594692, 594237, 593897, 593026, 592575, 592421.
In our opinion, this is a significant violation, as the last answers changing the basic documents of tender No. 236205
were given by the beneficiary on 7.06.2021. The deadline for submitting offers was 10.06.2021. Providing new
information 3 days before the submission of tenders is disproportionate within the meaning of § 3 clause 1 of the
Public Procurement Act, which could have affected the final results of the procurement. Modifying public
procurement documents through explanations is not allowed, because interested parties are not obligated to review
the information contained in the communication section of Public Procurement Register.
In accordance with Annex 1 p. 2.1 subsection 4 of the European Commission's 14.05.2019 violation guide No.
C(2019) 3452, a 10 percent financial correction rate must be applied if the tender receipt deadline is not extended
and the procurement documents are significantly changed.
Risk to the project implementation: Competition was not effectively used, resulting in the project’s goals not being
achieved at the best possible price. The State Shared Service Centre has applied financial corrections to the
13
maximum extent (25%), which covers the identified deficiencies. Additional corrections are not recommended as a
result of procurement verification.
Recommendation on the project implementation: We recommend following Public Procurement Act.
Comments of the beneficiary audited: Jääme teiste tähelepanekute puhul oma varasemalt antud seisukohtade juurde.
Me ei pidanud vajalikuks nende kohta esitada oma seisukohta põhjusel, et isegi kui asuda seisukohale rikkumise
esinemise osas, on need rikkumised kaetud varasemalt meile määratud finantskorrektsiooniga.
Comments of the Financial Control and Managing Authority/Joint Technical Secretariat: We agree with the finding, and
we have also drawn the beneficiary’s attention to said deficiencies during the procurement inspection and according
financial correction has been applied.
4.2.8 Significant finding – The Beneficiary has not verified the successful tenderer’s compliance
According to § 120 section 1 of the Public Procurement Act criteria: A public contract is awarded on the terms and
conditions set out in the procurement documents and in accordance with the tender that has been declared
successful.
The Beneficiary has not verified the successful tenderer’s compliance with the terms of the procurement contract or
lacks evidence regarding the verification of compliance with the conditions set out in contract clauses 11,17 and 28.
The procurer has failed to fulfil of contract clause 33.
In our opinion significant violation is the failure to fulfill the requirements of clause 17 of the contract. According to
clause 6.1.1 of the contract, the contractor was required to provide a performance guarantee to the client in the
amount specified in clause 17 of the contract, before entering the contract. Thus, the contracting authority included
a special condition in the procurement contract, which in essence served as a selection criterion for the successful
tenderer, as it required the fulfillment of the condition before the contract was signed. During the audit such evidence
was not submitted.
In accordance with Annex 1 p. 2.2 subsection 14 of the European Commission's 14.05.2019 violation guide No.
C(2019) 3452, it is a violation with a financial impact, according to which the rate of financial correction is 25%.
Risk to the project implementation: If the beneficiary does not comply with the laws and regulations it may result in
ineligible costs to the project. The State Shared Service Centre has applied financial corrections to the maximum
extent (25%), which covers the identified deficiencies. Additional corrections are not recommended as a result of
procurement verification.
Recommendation on the project implementation: We recommend following Public Procurement Act and to follow
conditions set out in procurement documents.
Comments of the beneficiary audited: Olete asunud punktis 4.2.8 seisukohale, et hankija ei ole kontrollinud pakkuja
vastavust nõutule. Viidatud seisukohale olete jõudnud meile arusaamatul moel. Nimelt ei ole viidatud nõude näol
tegemist küsimusega pakkuja vastavuse kohta vaid sõlmitud hankelepingu täitmise osas. Hankija oli riigihanke
alusdokumentide hulka kuuluva hankelepingu punktis 2 „2. ÜLDTINGIMUSTE TÄIENDUSED, MUUDATUSED VÕI
MITTE-KOHALDAMINE“ alapunktis 4 muutnud ETÜ 2013 tingimust ja kohustanud töövõtjat esitama tellijale 7 päeva
jooksul peale lepingu allkirjastamist täitmisaja tagatise eritingimuste punktis 17 toodud suuruses ehk tegemist on
nõuet üle kandva tingimusega pakkujate kontrollimise faasist lepingu täitmise faasi. Eelnevast tulenevalt olete
lõppjärelduses ekslikult asunud seisukohale, et täitmistagatis tuleb esitada enne hankelepingu sõlmimist.
Additional comments of the auditors: The auditors stand by their opinion but have explained more thoroughly the
circumstances of violations.
Comments of the Financial Control and Managing Authority/Joint Technical Secretariat: We agree with the finding
regarding the non-submission of performance bond, and according financial correction has been drawn up.
14
4.3 Public procurement 259004 findings
Võru Linnavalitsus launched an open procurement no 259004 “Loomekoja ehitamine” in the Public Procurement
Registry on 6th January 2023. As a result of the procurement a contract no 144 was concluded with OÜ Kagukatus
(12884910) to o complete the construction work of the Loomekoja building.
4.3.1 Non-significant finding – Tenderer warrant was not requested
According to § 122 section 3 of the Public Procurement Act criteria: In the case of a public works contract or works
concession, the contracting authority or entity requires in the procurement documents that the tenderer warrant in
their tender that they will not enlist, in the performance of the contract, a subcontractor who would be subject to
replacement under subsection 7 of this section.
The Beneficiary has not been in compliance with § 122 section 3 of the Public Procurement Act by failing to request
tenderer warrant in their tender.
Risk to the project implementation: If the beneficiary does not comply with the laws and regulations it may result in
ineligible costs to the project.
Recommendation on the project implementation: We recommend following Public Procurement Act.
4.3.2 Non-significant finding – Insufficient rules to ensure avoiding conflicts of interest
According to § 3 clause 4 of the Public Procurement Act criteria: the authority or the entity avoids a competition-
distorting conflict of interest.
The internal rules for procurement are not sufficient to ensure substantive measures to avoid conflicts of interest
set out in Public Procurement Act § 3 clause 4, as the members of the procurement committee are not required to
confirm the absence of conflicts of interest in writing forms or in document management system, which is contrary
to the transparency and verifiability principles set out in § 3 clause 1.
According to the audit’s assessment this is a non-significant finding, as an indirect measure to prevent conflicts of
interest is established in clause 22 of the procurement regulations, and no connections between the members of the
procurement committee and the tenderers were identify.
Risk to the project implementation: If the beneficiary does not ensure sufficient measures to avoid conflicts of interest
in internal procurement rules it may result in ineligible costs to the project.
Recommendation on the project implementation: We recommend establishing a rule in procurement regulation or
another internal document, requiring members of the procurement committee to confirm the absence of conflicts
of interest in writing, either in the document management system, through a separate confirmation letter, or in the
Public Procurement Register.
4.3.3 Non-significant finding – Subcontractors absence of grounds for elimination was not verified
According to § 122 section 5 of the Public Procurement Act criteria: In the case of a public works contract or works
concession, the contracting authority or entity verifies, during procurement proceedings, the inapplicability of
grounds for exclusion mentioned in subsection 1 of § 95 of this Act – or, in the fields of defense and security, in
clauses 1, 4 or 5 of that subsection – regarding the subcontractors mentioned in the successful tenderer’s tender
and, following the award of the contract, regarding any subcontractor who is added in the course of its performance.
Such verification is not required in a negotiated procedure without prior publication or during performance of the
contract awarded as a result of that procedure. The Beneficiary has not been in compliance with § 122 section 3 of
the Public Procurement Act by failing to require tenderer warrant in their tender.
15
The beneficiary has failed to verify the absence of grounds for elimination of the subcontractors added after the
conclusion of the procurement contract based on § 122 section 5 of the Public Procurement Act.
Risk to the project implementation: If the beneficiary does not comply with the laws and regulations it may result in
ineligible costs to the project.
Recommendation on the project implementation: We recommend following Public Procurement Act.
4.3.4 Non-significant finding – Procurement contract has been fulfilled in a different way from the
original conditions
Pursuant to Section 123 (1) point 7 of the Public Procurement Act, it is possible to change the procurement contract
if such a change is not significant. According to Section 123 (2) of the Public Procurement Act, the amendment is
significant especially if 1) the amendment adds a condition that would have expanded the number of possible
participants in the public procurement if the basic documents of the public procurement had contained such a
condition; 2) the amendment results in a change in the ratio of contractual obligations arising from the procurement
contract in favor of the entrepreneur in a manner not stipulated in the procurement contract.
Procurement contract has been fulfilled in a different way from the original conditions set out in contract clause 17.
According to the audit’s assessment this is a non-significant finding. The State Shared Service Centre has explained
it with following arguments we agree with:
The validity of the guarantee was to be 6 months, the guarantee provided by the contractor was valid for 5 months.
We consider that the requirement for a guarantee of a shorter validity period of 1 month would not have affected the
circle of bidders in such a way that more bidders could participate in the tender. The bidder who received a letter of
guarantee from the bank with validity period of 5 months would have also received it for 6 months. Also, the balance
of contractual obligations has not changed in favor of the entrepreneur, as despite the length of the guarantee's
validity, he still had to provide the guarantee. Consequently, it is an insignificant change.
Even if it is admitted that by accepting the submission of a guarantee with a shorter validity period that is one month
shorter the Beneficiary has violated the principles of equal treatment of persons, procurement transparency and
effective use of competition, in a situation where the change has no impact on the circle of bidders, there is
consequently no possible financial impact on the EC budget.
This finding was changed from significant to non-significant after additional relevant information and explanations
were provided by the auditee and Programme authorities.
Risk to the project implementation: If the beneficiary does not comply with the laws and regulations it may result in
ineligible costs to the project.
Recommendation on the project implementation: We recommend following Public Procurement Act and to follow
conditions set out in procurement documents.
4.3.5 Non-significant finding – Decision not to subdivide the procurement into parts within the
proceedings was not stated in the procurement documents
According to § 27 section 2 of the Public Procurement Act criteria: Where a public procurement, which has not been
divided into parts within the proceedings and whose estimated value equals or exceeds the public procurement
threshold – or the international threshold, where this Act does not provide a threshold for such a procurement – the
contracting authority or entity states, in the procurement documents, the reasons for its decision not to subdivide
the procurement into parts within the proceedings. The duty to state the reasons does not apply if the public contract
is awarded under a framework agreement or based on a dynamic purchasing system.
The Beneficiary has not stated in procurement documents the reasons for its decision not to subdivide the
procurement into parts within the proceedings. The Beneficiary has stated the reasons in the protocol of approval
16
of basic documents which is not publicly available on eRHR nor in the public procurer's document management
register.
According to the audit’s assessment this is a non-significant finding. The State Shared Service Centre has explained
it with following arguments we agree with:
According to the explanatory letter of the Public Procurement Act, the contracting authority can only be criticized if
his justification is not substantial. However, whether the reasons are expedient and relevant cannot be contested.
Therefore, there are no specific rules regarding the possible content and scope of justifications. In the commented
edition of the Public Procurement Act, it has been found regarding subsection 2 of section 27 of the Public
Procurement Act, that such a reason may consist in the fact that the subdivision of the public procurement into lots
makes the performance of the contract excessively complicated or costly, or the need to coordinate the activities of
the contractors of the different parts may seriously threaten the proper performance of the contract (Directive
2014/24/EU recital 78). According to the explanatory letter of the Public Procurement Act, the subdivision of the
public procurement into lots in construction comes into question only if the separate lots are functioning
independently and the building can be used even if the construction of some parts is stuck. In this particular case,
one “creative house” was established, that is, one building, which means that the contracting authority ordered one
complete solution. If the public procurement was divided into lots, several contractors would have had to operate on
one work site at the same time, and the contracting authority himself would have had to take on the role of project
manager. The existence of such competence, however, cannot be expected from the contracting authority, which is
why it is justified to order the entire construction work of the building from one contractor.
Summing up all of the above, making a financial correction is not justified.
This finding was changed from significant to non-significant after additional relevant information and explanations
were provided by the auditee and Programme authorities.
Risk to the project implementation: If the beneficiary does not comply with the laws and regulations it may result in
ineligible costs to the project.
Recommendation on the project implementation: We recommend following Public Procurement Act.
5. Granting of state aid
The state aid has been granted to the project and used by the beneficiary in correct manner, in accordance with the
state aid rules.
6. Communication and publicity
When informing and disclosing the use of funding, the beneficiary has in all material aspects followed the current
legislation.
We confirm tha t the fina l a udit report ha s 17 pa ges.
Audit mana ger: Audit supervisor:
Tanel Kullison Indrek Alliksaar
Auditor Auditor
Tallinn, 13.09.2024
17
Hr Kalvi Kõva
Võru Linnavalitsus Meie 16.09.2024 nr 10-5/4076-1
[email protected]
Auditi lõpparuande edastamine
Austatud härra linnapea
Edastame Teile projekti nr „BestNest“ (ER58) auditi lõpparuande nr EVP-13/2024.
Täname Teid meeldiva koostöö ja osutatud abi eest.
Lugupidamisega
(allkirjastatud digitaalselt)
Anu Alber
finantskontrolli osakonna juhataja
auditeeriva asutuse juht
Lisa:
Auditi lõpparuanne
Sama:
Pr Tiina Sams, Riigi Tugiteenuste Keskus (
[email protected])
Henry Kibin 5885 1356
[email protected]
Suur-Ameerika 1 / 10122 Tallinn / 611 3558 /
[email protected] / www.rahandusministeerium.ee
registrikood 70000272