Annex 1. Proposed Amendments to Grant Agreement No INEA/CEF/ICT/A2015/1156737
Grant Agreement Proposed amendment to the Grant Agreement
reference
Page 1 Change the official address of HWISC. We propose to
change it as follows:
Uus-Tatari 25, 10134 Tallinn, Estonia
HWISC is represented by the Director Ms. Katrin Reinhold
Page 6 section 6.3 – The communication details for HWISC have changed. We
Communication details of would propose to update the contact details as follows:
the beneficiaries
Katre Pruul
Head of data management division
Uus-Tatari 25, 10134 Tallinn, Estonia
E-mail address:
[email protected]
Page 9 Article I.1 – We would propose to update the text as follows:
Scope and Objectives of
the action [...] Estonia is planning to implement cross-border Patient
Summary during the first quarter of 2020 (Country A and B)
[...].
Page 9 Article I.3 – We propose to update the indicative end dates of the
Activities activities as follows.
For activity 1 - 31/01/2020
For activity 2 - 31/01/2020
Page 11 Activity 2: We propose to update the text as follows:
Service Testing, Approval
and Deployment The NCPeH and the portal will be registered for the 2019
T2.2. Pre-live testing and Project-a-thon as NCP-A, NCP-B and Portal for the Patient
Projectathon Summary Service.
The decision of participating in the 2020 Project-a-thon will
be made by the beneficiaries in the course of the Action
depending on the differences introduced by the adoption of
the new EC guidelines for Patient Summary and
ePrescription.
Page 12 Activity 3: We propose to change the timeline in the text as follows:
Operation The approver and deployed services will be provided
T3.1. Service provision according to the release plan:
and monitoring - 2018: ePrescription country B
- 2019: ePrescription country A
- 2020: Patient Summary country A and B and
ePrescription services will be aligned with the new EC
guidelines.
Page 14-15 Article I.4 – We propose to change the indicative completion dates for
Milestones and Means of milestones number 6, 7 and 8 as follows:
Verification Milestone 6 – 30/11/2019
Milestone 7 – 31/03/2020
Milestone 8 – 31/01/2020