Karin Viikmaa
Riigi Tugiteenuste Keskus
18.02.2024 nr 4-5/19/45
EE-CLIMATE programmi üheksanda
finantsvahearuande esitamine
Austatud Karin Viikmaa
Esitame Euroopa Majanduspiirkonna Finantsmehhanismist 2014-2021 rahastatava EE-CLIMATE
programmi "Kliimamuutuste leevendamine ja nendega kohanemine" üheksanda
finantsvahearuande.
Lugupidamisega
(allkirjastatud digitaalselt)
Tanel Ross
Finantsosakonna juhataja
Lisa: EE-CLIMATE programmi üheksas finantsvahearuanne
Teadmiseks:
[email protected],
[email protected]
Eleri Seer, 605 0298
[email protected]
Suur-Ameerika 1 / Tallinn 10122 / 626 2802/
[email protected] / www.kliimaministeerium.ee/
Registrikood 70001231
DocuSign Envelope ID: 2C637256-D9CD-4686-BC8E-DFEA63C45600
Interim financial report EEA Financial Mechanisms 2014 – 2021
Interim financial report number 9
Programme summary
Programme operator Ministry of Climate - Estonia
Beneficiary State Estonia
Programme title Climate Change Mitigation and Adaptation
Programme code EE-CLIMATE
Eligible Expenditure € 7,058,823.53
Programme grant rate 85.00 %
Programme grant amount € 6,000,000.00
EEA Grant Amount € 6,000,000.00
Norway Grant Amount € 0.00
Start date of eligibility 10/05/2017
Final date of eligibility 31/12/2024
1 Version 2.0 as of 05/02/2024 15:24:16 CET
DocuSign Envelope ID: 2C637256-D9CD-4686-BC8E-DFEA63C45600
Part A - Statement of actual expenditure incurred and interest
earned
Incurred expenditure - summary
Interim financial report number 9
Start date of incurred expenditure period 01/07/2023
End date of incurred expenditure period 31/12/2023
Previously
Incurred this Available
incurred Total to date Total Budget
period balance
expenditure
Eligible
€ 1,683,110.57 € 2,461,174.56 € 4,144,285.13 € 7,058,823.53 € 2,914,538.40
expenditure
EEA Grants € 1,430,643.98 € 2,091,998.38 € 3,522,642.36 € 6,000,000.00 € 2,477,357.64
Co-financing € 252,466.59 € 369,176.18 € 621,642.77 € 1,058,823.53 € 437,180.76
Incurred expenditure - details
Title: Programme management
Previously
Incurred this Available
incurred Total to date Budget
period balance
expenditure
Eligible
€ 296,360.11 € 80,715.05 € 377,075.16 € 705,823.53 € 328,748.37
expenditure
Brief description of actual expenditure incurred
The second half of 2023 projects are in implementing stage. Two projects were completed. The project from
the reserve list which was granted in May 2023 was contracted and also started implementing.
Within Programme Management there were expenditures regarding salary of one PO employee (July-Dec),
organizing CC meeting in Oslo and also expenditures of participating Portugal and Czeck EEA Grants
Midterm events.
EIC worked with the approval of payments and transfer of payments to Project Promoters, also monitoring
projects and Communication activities costs.
Eligible expenditures
Eligible expenditure - EUR
€ 80,715.05
Total
€ 80,715.05
Title: Outcome 1: Ecosystem resilience increased (EEA Grants)
Previously
Incurred this Available
incurred Total to date Budget
period balance
expenditure
Eligible
€ 345,460.52 € 120,063.28 € 465,523.80 € 800,000.00 € 334,476.20
expenditure
Brief description of actual expenditure incurred for the outcome
Expenditures incurred were related to Project management costs; participation costs of seminars; pathway
analysis of invasive alien species; Control of invasive alien species; research and analyses of alien species;
methodologies of biological survey (e-DNA); assessment of the biological impact of marine non-indigenous
species; purchase of small equipment; communication costs and; training costs.
Eligible expenditures
Eligible
Project expenditure -
EUR
EE-CLIMATE-0011 € 42,248.85
2 Version 2.0 as of 05/02/2024 15:24:16 CET
DocuSign Envelope ID: 2C637256-D9CD-4686-BC8E-DFEA63C45600
EE-CLIMATE-0012 € 77,814.43
Total
€ 120,063.28
Title: Outcome 2: Increased ability at the local level to reduce emissions and adapt to a changing
climate (EEA Grants)
Previously
Incurred this Available
incurred Total to date Budget
period balance
expenditure
Eligible
€ 674,677.05 € 1,545,653.85 € 2,220,330.90 € 3,753,000.00 € 1,532,669.10
expenditure
Brief description of actual expenditure incurred for the outcome
Projects’ expenditures in the second half of 2023 were related to different construction works (planning,
landscaping, planting, etc); communication costs, workshops, sowing native seeds, planting trees and
project management costs.
Eligible expenditures
Eligible
Project expenditure -
EUR
EE-CLIMATE-0022 € 273,912.38
EE-CLIMATE-0016 € 162,554.04
EE-CLIMATE-0026 € 41,928.12
EE-CLIMATE-0021 € 172,259.20
EE-CLIMATE-0024 € 266,463.90
EE-CLIMATE-0023 € 135,373.45
EE-CLIMATE-0025 € 30,213.91
EE-CLIMATE-0020 € 234,053.95
EE-CLIMATE-0019 € 228,894.90
Total
€ 1,545,653.85
Title: Outcome 3: Framework for Circular Economy strengthened (EEA Grants)
Previously
Incurred this Available
incurred Total to date Budget
period balance
expenditure
Eligible
€ 366,612.89 € 714,742.38 € 1,081,355.27 € 1,800,000.00 € 718,644.73
expenditure
Brief description of actual expenditure incurred for the outcome
Expenditures incurred were related to project management costs, workshops, and meetings; studies;
communication costs; equipment for re-use centers; and study visits.
Eligible expenditures
Eligible
Project expenditure -
EUR
EE-CLIMATE-0013 € 414,221.59
EE-CLIMATE-0014 € 48,021.72
EE-CLIMATE-0015 € 94,893.89
EE-CLIMATE-0017 € 157,605.18
Total
€ 714,742.38
Interest Earned
3 Version 2.0 as of 05/02/2024 15:24:16 CET
DocuSign Envelope ID: 2C637256-D9CD-4686-BC8E-DFEA63C45600
Interest generated on accounts established by the Programme Operator for funds
intended for regranting for 2023
EEA Grants Total
€ 0.00 € 0.00
Cumulative Interest generated on accounts established by the Programme Operator for
funds intended for regranting
EEA Grants Total
€ 272.64 € 272.64
Comment
No interest earned
4 Version 2.0 as of 05/02/2024 15:24:16 CET
DocuSign Envelope ID: 2C637256-D9CD-4686-BC8E-DFEA63C45600
Part B - Statement of proposed expenditure
Proposed expenditure - summary
Start date of proposed expenditure period 01/05/2024
End date of proposed expenditure period 31/10/2024
Previous
Interim
advance and Available
payment this Total to date Budget
interim balance
period
payments
Eligible
€ 6,150,896.57 € 639,888.56 € 6,790,785.13 € 7,058,823.53 € 268,038.40
expenditure
EEA Grants € 5,228,262.08 € 543,905.28 € 5,772,167.36 € 6,000,000.00 € 227,832.64
Co-financing € 922,634.49 € 95,983.28 € 1,018,617.77 € 1,058,823.53 € 40,205.76
Title: Programme management
Brief description of activities to be financed
Programme management costs: approval of payments and transfer of payments to Project Promoters, monitoring
of projects and reviews, information, and communication work.
Previous
Interim
advance and Available
payment this Total to date Budget
interim balance
period
payments
Eligible
€ 510,646.11 € 49,929.05 € 560,575.16 € 705,823.53 € 145,248.37
expenditure
* For management costs it is not possible to request more than € 635,241.18 of the total amount as 10.00 % is
retained for the programme closure.
Title: Outcome 1: Ecosystem resilience increased (EEA Grants)
Brief description of activities to be financed
Project management costs; travelling costs; pathway analysis of invasive alien species; analyses of alien
species; e-DNA sampling; purchase of small equipment; communication costs.
Previous
Interim
advance and Available
payment this Total to date Budget
interim balance
period
payments
Eligible
€ 670,460.52 € 112,063.28 € 782,523.80 € 800,000.00 € 17,476.20
expenditure
Title: Outcome 2: Increased ability at the local level to reduce emissions and adapt to a changing
climate (EEA Grants)
Brief description of activities to be financed
Project management costs; climate change mitigation and adaptation measures’ implementation costs
(construction costs); seminars and training costs; publication costs (incl. information materials). organizing final
event.
Previous
Interim
advance and Available
payment this Total to date Budget
interim balance
period
payments
Eligible
€ 3,440,677.05 € 279,653.85 € 3,720,330.90 € 3,753,000.00 € 32,669.10
expenditure
Title: Outcome 3: Framework for Circular Economy strengthened (EEA Grants)
Brief description of activities to be financed
Project management costs; travelling costs; preparation of guides and information materials; organizing costs
for final event, seminars, trainings; equipment for workshops; circular economy related analyses in local
municipalities.
Previous
Interim
advance and Available
payment this Total to date Budget
interim balance
period
payments
5 Version 2.0 as of 05/02/2024 15:24:16 CET
DocuSign Envelope ID: 2C637256-D9CD-4686-BC8E-DFEA63C45600
Eligible
€ 1,529,112.89 € 198,242.38 € 1,727,355.27 € 1,800,000.00 € 72,644.73
expenditure
6 Version 2.0 as of 05/02/2024 15:24:16 CET
DocuSign Envelope ID: 2C637256-D9CD-4686-BC8E-DFEA63C45600
Programme operator
Full legal name: Ministry of Climate - Estonia (EE)
Programme operator signature
I certify that I am duly authorised to sign this interim financial report and that the proposed
expenditure described in Part B from which this interim payment is calculated is a realistic
estimate of the expenditure that will actually be required by the Programme in the period
referred to in Part B.
I have thoroughly reviewed the actual expenditure incurred declared in Part A, and co -
financing provided in Part B of this report, and confirm that the information provided is accurate.
I confirm that this Programme is carried out as described in the Programme Agreement and
that the incurred expenditure is correctly represented.
Overall implementation status (including milestones):
Programme is implemented according to the plan.
Question Answer Comment
Management and control The setup of management and control
systems of the Programme system for the programme started in 2019.
Operator set up fulfilling the The compliance audit of the management
Yes
general principles set out in the and control system of the EE-Climate
Regulation and approved by the programme has started in April 2020 and
National Focal Point (Art 5.7) finished 13 July 2020.
Separate interest-bearing bank
accounts dedicated to the funds
intended for regranting Yes Responsibility of CA.
established and maintained (Art
5.6.1 (m))
EE-CLIMATE Programme webpage is
operated by the webpage of Ministry of the
Climate. Information about the open calls
Information and publicity
Yes can be found on the webpage of
obligations fulfilled (Art 3.3)
Implementing Agency. Information articles,
press releases etc about opening Call II
were published in media by POIA.
Monitoring and verifications
Constant communication via e-mails and
conducted to ensure quality
phone calls with project promoters.
and/or regularity of Yes
Participating in the meetings of steering
implementation (Art 5.6.1 (g) and
committee of pre-defined project.
Art 5.6.2)
Project promoters of Call I and pre-defined
Annual monitoring of a sample of
Yes project submitted their annual project reports
projects conducted (Art 5.6.1 (i))
and these were checked by POIA.
Project-specific statistical data is
Project specific data is entered in reporting
entered and up to date in the Yes
database.
reporting database (Art 5.6.1 (s))
7 Version 2.0 as of 05/02/2024 15:24:16 CET
DocuSign Envelope ID: 2C637256-D9CD-4686-BC8E-DFEA63C45600
Special conditions and
Programme-specific rules set out There are no programme-specific rules set
N/A
in the programme agreement out in the programme agreement.
fulfilled (Art 5.6.1 (x))
All irregularities, their
investigation and any remedies Yes All occurred irregularities are reported.
taken reported (Art 5.6.1 (v))
For the Programme Operator
2/9/2024
Tallinn
Signed in ................................. on ................
......................................................................
8 Version 2.0 as of 05/02/2024 15:24:16 CET
DocuSign Envelope ID: 2C637256-D9CD-4686-BC8E-DFEA63C45600
Certification of actual expenditure incurred and co-financing
Interim financial report number 9
Start date of incurred expenditure period 01/07/2023
End date of incurred expenditure period 31/12/2023
Actual expenditure incurred this period € 2,461,174.56
Start date of proposed expenditure period 01/05/2024
End date of proposed expenditure period 31/10/2024
Co-financing committed to date € 1,018,617.77
Co-financing for incurred expenditure paid € 621,642.77
Interest earned 2023 € 0.00
The Certifying Authority hereby certifies that:
The Certifying Authority hereby certifies that:
(i) the summary of eligible expenditure submitted by the Programme Operator is in full
conformity with the supporting documents;
(ii) the supporting documents have been examined and found to be authentic, correct and
accurate;
(iii) the summary of eligible expenditure is based on verifiable accounting which is in
compliance with generally accepted accounting principles and methods;
(iv) the summary of eligible expenditure falls within eligible expenditure under the Regulation
for the implementation of the EEA / Norwegian Financial Mechanisms 2014-2021;
(v) the summary of expenditure is incurred as part of the implementation of the Programme in
accordance with the Programme Agreement;
(vi) sufficient audit trail exists;
(vii) co-financing committed to date has been made available;
(viii) co-financing in relation to incurred expenditure has been paid;
(ix) when relevant, that the interest earned at PO account is correct.
For the Certifying Authority
Signed in ................................. on ................
......................................................................
9 Version 2.0 as of 05/02/2024 15:24:16 CET