5.1 Template for the PDP cost (budget)
Programme: OCR
Project title: Open Cyber Range
Project Promoter: Estonian Ministry of Defence
Total project cost: 3 331 765 €
Project grant rate: 100%
Project duration: 36 months
Legend: EST price is 6 500€/per month, for NOR it is 9 000€/per month, combined price is calculated as 8 000€/per month.
Number of units Unit price (€) Total cost (€)
Unit Type of expenditure Comments/additional information
(a) (b) (a) x (b)
1. DIRECT EXPENDITURES - Reg. Art. 8.2 & Art. 8.3
Project management
Cost of staff assigned to the
OCR Project Manager Month 36,00 5 352,00 192 672,00 1 FTE
project - Reg. Art. 8.3.1.a
Travel and subsistence
4 travels per year for three people (project manager + any
Travel costs Travels 36,00 1 000,00 29 000,00 allowances for staff - Reg. Art.
other function supporting the efforts)
8.3.1.b
Cost of new or second hand
ICT quipment includes computer and smartphone with
ICT equipment for OCR Project Manager Kit 1,00 3 000,00 - equipment - Reg. Art. 8.3.1.c
software and licenses required to implement the project
& Art. 8.3.2
Costs of consumables and
Communication costs Month 36,00 30,00 - Mobile and landline costs, includes mobile data
supplies - Reg. Art. 8.3.1.e
Costs entailed by other
OCR visual identity development, this includes wireframe for
contracts awarded by PP for
OCR identity development Days 800,00 25,00 - the website, presentation background, roll-up design etc. All
the purpose of carrying out
those include logo, colorschema, fonts etc.
the project - Reg. Art. 8.3.1.f
Costs entailed by other
contracts awarded by PP for OCR website to promote the capability and connect users to
OCR website and connectivity to the OCR Days 800,00 60,00 -
the purpose of carrying out the OCR capability
the project - Reg. Art. 8.3.1.f
Costs entailed by other
OCR Framework includes legal status, ruleset, business
contracts awarded by PP for
OCR Framework development Days 1 200,00 20,00 26 000,00 model, contractual relationships with academia, start-ups
the purpose of carrying out
and enterprises etc.
the project - Reg. Art. 8.3.1.f
Costs arising directly from
requirements imposed by the
Other costs 1,00 14 013,00 86 093,00 Publicity, translation, memorabilia, etc
project contract - Reg. Art.
8.3.1.g
All outsourcing 168 000,00
-
-
-
Total 1.1: 501 765,00
Output / Activity 1 - Initial hardware and software environment
Cost of new or second hand
Consists of Dell or Cisco servers, either raw computing or
WP1 - Servers Kit 1,00 300 000,00 214 466,40 equipment - Reg. Art. 8.3.1.c
with some storage
& Art. 8.3.2
Cost of new or second hand Prefered solution is EMC XtremeIO that has proven its
WP1 - Fast data storage Kit 1,00 350 000,00 188 896,50 equipment - Reg. Art. 8.3.1.c capability in the Estonian Cyber Range setup or equivalent
& Art. 8.3.2 solution, for activity use in live environments
Cost of new or second hand
Slow data storage is used for storing virtual machines,
WP1 - Slow data storage Kit 1,00 100 000,00 140 616,00 equipment - Reg. Art. 8.3.1.c
templates, configurations, scenarios etc for on-demand use
& Art. 8.3.2
Cost of new or second hand
Routers, switches, cables etc needed to connect OCR
WP1 - Networking equipment Kit 1,00 150 000,00 43 893,00 equipment - Reg. Art. 8.3.1.c
together and to the Internet
& Art. 8.3.2
Costs entailed by other Any work (installation, initial setup etc.) or additional
contracts awarded by PP for datacenter small equipment (PDU-s, rack blinds, cabling or
WP1 - Civil works Days 800,00 50,00 266 836,22
the purpose of carrying out cabling accessories, KVM, monitoring tools etc.) needed to
the project - Reg. Art. 8.3.1.f set up the OCR environment
Cost of new or second hand
E.g. IPS or any other hardwar/software needed to enhance
WP1 - Security equipment Kit 1,00 120 000,00 5 291,88 equipment - Reg. Art. 8.3.1.c
security of the OCR
& Art. 8.3.2
-
-
-
-
Total 1.2: 860 000,00
Output / Activity 2 - Software Development
No specific WP - general work to be done under the project -
develop and implement OCR specific requirements such as
specifications for APIs, minimal security requirements,
Development on technical requirements to achive initial Cost of staff assigned to the
Month 12,00 8 000,00 97 000,00 requirements for federating technical capabilities, guidelines
operational capability project - Reg. Art. 8.3.1.a
for documentation, KPIs, evaluate existing capabilities
(market research), analyse solutions (e.g. proprietary vs
open source) etc.
The goal is to develop language to define scenarios at an
Cost of staff assigned to the
WP2 - Scenario Language Development Month 3,00 8 000,00 abstract level. Compilers and generator will follow and allow
project - Reg. Art. 8.3.1.a
61 500,00 the automatic generation of low level artifacts
Cost of staff assigned to the The goal is to develop language to define artefacts to be
WP5 - Language Development for Digital Library Month 4,00 8 000,00
project - Reg. Art. 8.3.1.a stored in Digital Library
Cost of staff assigned to the Tools to run and operate activities on the OCR – chat, wiki,
WP17 - Collaboration tools on OCR Month 12,00 8 000,00 93 700,00
project - Reg. Art. 8.3.1.a project management tools etc.
Develop connections and make available additional external
capabilities that supplement OCR capabilities and support
OCR activities, this is achieved through integration and/or
federation of other capabilities, this might include public
Cost of staff assigned to the
WP18 - Hybrid systems related to the OCR Month 40,00 8 000,00 152 000,00 cloud services for additional computing power, specialized
project - Reg. Art. 8.3.1.a
Cyber Ranges/Labs for specific task (ICS, IoT etc.)
This activity will be broken down to smaller parts during the
project development, currently 3 different hybrid systems
are foreseen
T.2.5. software development for SDL 1) scenario
88 000,00
management, 2) DL management
T.2.6. Digital Library Development (move from 3) 175 000,00
-
Total 1.3: 667 200,00
Output / Activity 3 - Research and development on OCR tools
Middleware to operate the OCR, in case of Estonian CR vLM
is used on top of VMware, in case of Norway OpenStack is
Cost of staff assigned to the
WP3 - Management system (VMWare) Month 6,00 6 500,00 39 000,00 used. This includes also support systems like git,
project - Reg. Art. 8.3.1.a
chef/puppet, etc.
This also includes potential sanitization and integrity tools
Middleware to operate the OCR, in case of Estonian CR vLM
is used on top of VMware, in case of Norway OpenStack is
Cost of staff assigned to the
WP4 - Management system (OpenStack) Month 6,00 9 000,00 54 000,00 used. This includes also support systems like git,
project - Reg. Art. 8.3.1.a
chef/puppet, etc.
This also includes potential sanitization and integrity tools
Component to store and organize artifacts for re-use –
Cost of staff assigned to the
WP6 - Digital Library development Month 12,00 8 000,00 - scenarios, virtual machines, test cases, configurations etc,
project - Reg. Art. 8.3.1.a
creating marketplace
3 types of simulation:
1. Simulate a core part of Internet for OCR use (BGP, DNS,
Cost of staff assigned to the NTP etc servers „on 6 continents“)
WP8 - User Simulation Month 12,00 8 000,00 85 000,00
project - Reg. Art. 8.3.1.a 2. User agents for several operating systems to simulate
user behavior (e.g. standard user, admin)
3. Capability to insert noise between any system on OCR
In general traffic collection and distribution capability, but
Cost of staff assigned to the
WP9 – Traffic simulation/generation Month 12,00 8 000,00 92 100,00 also storing console events, snapshots, screenshots and
project - Reg. Art. 8.3.1.a
video from virtual machines, playback capability
In general traffic collection and distribution capability, but
Cost of staff assigned to the
WP10 - Activity Monitoring Month 12,00 8 000,00 105 000,00 also storing console events, snapshots, screenshots and
project - Reg. Art. 8.3.1.a
video from virtual machines, playback capability
Cost of staff assigned to the Different views for teams (red, blue, green, white) with
WP11 - Situational awareness Month 12,00 8 000,00 108 000,00
project - Reg. Art. 8.3.1.a distinct data about exercise or training environment
Cost of staff assigned to the Technics and procedures to gather information from OCR in
WP12 - Scoring and evalution module Month 12,00 8 000,00 100 300,00
project - Reg. Art. 8.3.1.a order to evaluate and score the activities
Cost of staff assigned to the Planning tool with feedback from technical environment,
WP13 - Feedback module Month 12,00 8 000,00 87 000,00
project - Reg. Art. 8.3.1.a lessons identified and lessons learned
Cost of staff assigned to the Evaluation social aspect in OCR, e.g. behavioral analysis
WP14 - Social aspect module Month 12,00 8 000,00 90 400,00
project - Reg. Art. 8.3.1.a connected to OCR activities
Federating EE (OCR) and NO Ranges – connectivity,
Cost of staff assigned to the
WP15 - Federation of Cyber Ranges Month 6,00 8 000,00 48 000,00 command and control, information sharing, resource
project - Reg. Art. 8.3.1.a
sharing etc.
Costs entailed by other
Security testing of the hardware and software environment
Outsourced - Security testing and validation of the OCR contracts awarded by PP for
Days 100,00 1 200,00 - set up during the project, security testing is conducted in
capability the purpose of carrying out
multiple iterations
the project - Reg. Art. 8.3.1.f
Total 1.4: 808 800,00
Output / Activity 4 - Populating OCR with content
This includes research and development on content
requirements.
Populate OCR library with sample software, virtual
machines, attack simulations, scenarios, trainings, exercises,
Cost of staff assigned to the
WP7 - Populating the digital library Month 24,00 8 000,00 319 000,00 test environments and other artifacts, document the use of
project - Reg. Art. 8.3.1.a
forenamed items in a way that they are reusable by the OCR
users
This might be broken down into subprojects during the
execution
Technics and procedures to test, experiment and evaluate
Cost of staff assigned to the new software and solutions in X number of different
WP16 - Testing facility Month 12,00 8 000,00 100 000,00
project - Reg. Art. 8.3.1.a configurations; possible tiered sertification system for
software that has gone through the testing
Costs entailed by other Malicious content is usually in a form of exerciseware that
contracts awarded by PP for differs from actual malware in the ways of built in security
Custom malicious content for the Digital Library Days 30,00 1 600,00 75 000,00
the purpose of carrying out measures (e.g. Works only in dedicated environments and
the project - Reg. Art. 8.3.1.f on specific conditions)
-
-
-
-
Total 1.5: 494 000,00
Total 1: 3 331 765,00
2. INDIRECT COSTS - Reg. Art. 8.5
Total 2: -
TOTAL PDP COST (1 + 2): 3 331 765,00
Total project management cost (€): 501 765,00
Total output related cost (€): 2 830 000,00
PROJEKTILEPINGU MUUTMISE KOKKULEPE NR 1
Majandus- ja Kommunikatsiooniministeerium, registrikood 70003158, asukoht Suur-
Ameerika 1, 10122 Tallinn, mida esindab majandus- ja infotehnoloogiaminister Tiit Riisalo,
kes tegutseb põhimääruse alusel (edaspidi ka Programmioperaator),
Ettevõtluse ja Innovatsiooni Sihtasutus, registrikood 90006012, asukoht Lasnamäe 2, 11412
Tallinn, mis on Ettevõtluse Arendamise Sihtasutuse õigusjärglane ja mida esindab juhatuse liige
Sigrid Harjo, kes tegutseb SAS § 18 lg 1 alusel (edaspidi Programmi elluviija),
ja
Kaitseministeerium, registrikood 70004502, asukoht Sakala 1, 15094 Tallinn, mida esindab
innovatsiooni osakonna juhataja Miiko Peris, kes tegutseb kaitseministri 01.07.2019
käskkirjaga nr 186 antud volituse alusel (edaspidi Projekti elluviija),
edaspidi eraldi Pool ja koos Pooled,
arvestades Projekti elluviija 20.02.2024 taotluses nr 2-8/24/1 esitatud vajadust muuta projekti
eelarvet ning pikendada projekti elluviimise tähtaega kuni 30.04.2024,
muudavad Pooled 19.03.2021 sõlmitud projektilepingut (edaspidi Leping) selle punktist 5.2
lähtuvalt tagasiulatuvalt alates 29.02.2024 järgmiselt:
1) sõnastavad punkti 1.6 järgmiselt:
„1.6. Projekti abikõlblikkuse perioodi lõppkuupäev on 30.04.2024.“;
2) sõnastavad punkti 1.7.3. järgmiselt:
„1.7.3. Projekti elluviija – Projekti teostamise eest vastutav isik, Open Cyber Range
projektijuht, Heidi Raudsepp, tel:+372 53435486, e-post:
[email protected].“;
3) sõnastavad punkti 3.2.9. järgmiselt:
„3.2.9. säilitama taotluse, toetuse ja Projekti teostamisega seonduvat
originaaldokumentatsiooni vähemalt 31. detsembrini 2031. a;“;
4) sõnastavad punkti 3.2.19.9. järgmiselt:
„3.2.19.9. 31.05.2024 (kulud 01.11.2023–30.04.2024);“;
5) sõnastavad punkti 3.2.20. järgmiselt:
„3.2.20. esitama Projekti lõpparuande ja maksetaotluse e-toetuste infosüsteemi hiljemalt
30.06.2024;“;
6) asendavad Lepingu lisa 2, mis kannab pealkirja „5.1 Template for the PDP (budget)“
käesoleva kokkuleppe lisaga.
POOLTE ALLKIRJAD:
Programmioperaator:
(allkirjastatud digitaalselt)
Tiit Riisalo
Programmi elluviija:
(allkirjastatud digitaalselt)
Sigrid Harjo
Projekti elluviija:
(allkirjastatud digitaalselt)
Miiko Peris
2