NCA PERMITTING MONITORING EXERCISE 2023 - DDL 30 November
Majandus- ja Kommunikatsiooniministeerium · 21. august 2023
- Viit
- 24.1-6/2023/3980-1
- Registreeritud
- 21. august 2023
- Dokumendi liik
- Sissetulev kiri
- Adressaat
- ENER C4
- Saabumis/saatmisviis
- e-post
- Funktsioon
- 24.1 EL ja rahvusvahelise koostöö korraldamine
- Sari
- 24.1-6/S Rahvusvahelise koostöö korraldamisega seotud kirjavahetus (Arhiiviväärtuslik)
- Toimik
- 24.1-6/2023
- Vastutaja
- Silver Tammik (Majandus- ja Kommunikatsiooniministeerium, Kantsleri valdkond, EL ja rahvusvahelise koostöö osakond)
Failid
Sisu (failidest)
Saatja: [email protected]
Teema: NCA PERMITTING MONITORING EXERCISE 2023 - DDL 30 November
Kuupäev: 2023-08-18 13:43
Dear National Competent Authority Representatives,
According to Article 32(2) of the revised TEN-E Regulation [Regulation (EU)
2022/869 of the European Parliament and of the Council of 30 May 2022], the
reporting requirements defined in Article 5(6) of Regulation No 347/2013
remain in effect for projects on the 5th PCI list, therefore "each year, the
competent authorities referred to in Article 8 shall report to the
respective Group on the progress and, where relevant, on delays on the
implementation of projects of common interest located on their respective
territory with regard to the permit granting processes, and on the reasons
for such delays."
As in previous years we have launched a dedicated EU survey that you must
fill in to fulfilling the reporting requirement.
The survey is available here:
<https://ec.europa.eu/eusurvey/runner/c41d2b84-bf3e-c27d-a8ac-ab67a38122d3>
https://ec.europa.eu/eusurvey/runner/c41d2b84-bf3e-c27d-a8ac-ab67a38122d3
Please note that the report should provide the information with the state of
play on 30 June 2023.
Please fill the form in not later than 30th November 2023.
Should you have any questions related to this reporting exercise, or in case
of any technical issues with accessing or completing the survey, please
contact us through this email ([email protected]
<mailto:[email protected]> ).
Yours sincerely,
ENER C4 Permitting Team