EUROPEAN COMMISSION
DIRECTORATE-GENERAL FOR ENERGY
Directorate C – Green Transition and Energy System Integration
C.4 – Infrastructure and Regional Cooperation
Best practices on the permit granting
system applicable to smart grids projects
The Platform of National Competent Authorities in charge of the permit granting
process for projects of common interest (NCA Platform) is a voluntary cooperation
forum, which counts with the participation of the National Competent Authorities
(NCAs) in charge of the permitting decisions for projects of common interest (PCIs) ( 1)
from all of the EU Member States. The NCA Platform aims to create a forum to share
best practices, encourage cross-border cooperation and consolidate technical knowledge,
ensuring that solutions to current issues are identified.
The NCA Platform also aims to support Member States to adequately implement
the TEN-E Regulation permitting provisions and accelerate the implementation of PCIs,
identifying measures to speed up general infrastructure permit granting processes and
develop, standardise, and streamline the national system.
The discussions held in the NCA Platform revealed the need to identify best
practices on the permitting of smart grid projects which require different planning from
traditional grid projects. The particular characteristics of smart grids projects, namely
geographic location non-linearity, leads to some practices applied by NCAs to the permit
granting of traditional transmission infrastructure not being transferable ( 2). The
suggestions for improving smart grids’ permit granting processes may also benefit other
project categories since it incentivizes system flexibility and the ability to identify and
address inefficiencies.
1. INTRODUCTION
The revised TEN-E Regulation strengthened the existing provisions on PCI
permitting. Under the Regulation, PCIs must be treated as projects of highest national
significance, consequently they should benefit from any existing accelerated procedures
and national priority status. Additionally, the TEN-E Regulation imposes a
(1) Article 8(1) of the TEN-E Regulation.
(2) Large electricity and gas interconnectors constitute the most usual PCIs and, therefore, the categories in which
NCAs have been able to develop best practices and lessons learned.
Commission européenne/Europese Commissie, 1049 Bruxelles/Brussel, BELGIQUE/BELGIË – Tel. +32 22991111
Office: DM24 06/117 – Tel. direct line +32 229-59274
comprehensive, but flexible, permitting regime structure with a maximum duration of 3.5
years (3).
Specifically relevant in the context of smart grids, the TEN-E Regulation reflects
the different circumstances, works, and overall structure of smart-grid projects, when
compared to traditional transmission infrastructure projects. It does so, by establishing a
flexible and adaptable permitting regime and empowering NCAs and the national
legislators to tailor the procedural requirements to the reality of different project
types (4). It should also be mentioned that the TEN-E Regulation also establishes
requirements, namely for public consultation ( 5) which must be enforced in an
appropriate and proportional manner that reflects the projects’ potential impact on the
population, keeps any delays to a minimum and ensures public participation while
minimizing public opposition.
Aiming to identify how the permitting of smart grid projects can be addressed in
an efficient manner, the Commission contacted the current smart grid PCI promoters to
collect first-hand experiences on issues faced and potential solutions to be implemented
by Member States. This exercise regards electricity smart grid projects, but the findings
apply as well to future smart gas grids projects due to a series of similar characteristics.
2. SPECIAL CHARACTERISTICS OF SMART GRIDS PCIS’ PERMITTING PROCESS
CONTEXT AND ASSOCIATED ISSUES
In light of the tailored approach of the TEN-E Regulation to permitting, which
establishes that permit granting processes must be fit for purpose, key features of smart
grids projects that must be reflected upon by the national authorities to structure the
permit granting processes in line with Article 10(6) of the TEN-E Regulation.
Smart-grid project promoters have reported that, in several jurisdictions, the permit
granting process applicable to smart grid projects is not fitted to the project needs.
Promoters consider that the process fails to provide suitable decisions in an expedited
manner placing economic and organisational burdens on promoters. As developed below,
NCAs should build up their knowledge on how smart grid projects are dealt with across
the EU, assimilating best practices on matters of spatial planning, environmental
requirements, and options for permitting acceleration. This should be followed up with
assessments of the national permit system, and implementation of the necessary
adjustments. On the side of the promoters, they should build up knowledge and capacity
on PCI permitting, as discussed below.
(3) Article 2(9) TEN-E Regulation, https://eur-lex.europa.eu/legal-
content/EN/TXT/?uri=uriserv%3AOJ.L_.2022.152.01.0045.01.ENG&toc=OJ%3AL%3A2022%3A152%3ATOC.
(4) Amongst other things, the Regulation suggests that, when smart-grid projects, due to their specific elements, do not
require the performance of an environmental impact assessment, the pre-application phase of the permitting process
can be shortened or even skipped.
(5) This requirement aims at fostering public acceptance for the projects.
2
2.1. The Promoter
While PCIs are frequently developments of the transport grid infrastructure, falling
under the remit of the Transmission System Operators (TSOs), smart grids projects often
regard the upgrade or development of new assets, closer to consumers and renewable
energy production, therefore, at the distribution system level. They are mostly promoted
by Distribution System Operators (DSOs).
Following Chapter III of the TEN-E Regulation, PCIs are characterised as necessary
and are to be afforded the most rapid treatment in administrative procedures and the
status of highest national significance. While the TEN-E Regulation does not
differentiate between DSO and TSO promoted PCIs, DSOs promoting smart grid PCIs
have identified differences in treatment. Specifically lack access to the status of highest
national significance and to the accelerated permitting regime, both of which are
available for TSO promoted PCIs. Additionally, the DSOs have reported that the
permitting system applied to their smart grid PCIs is designed to meet the specificities of
the TSO promoted projects. This design presents incompatibilities with DSO promoted
PCIs, specifically the timelines for presenting information for authorizations and studies
requirements, which do not account for projects’ characteristics and their inability to
conduct certain assessments and produce documentation within its timeframe.
This differences in treatment place DSO backed PCIs in a comparatively worst
permitting situation to TSO backed projects and may disincentivize DSOs from applying
for PCI status. This may jeopardize the contribution of the smart grid projects towards
reaching the objectives of the TEN-E Regulation. Therefore, the most beneficial
treatment should be available to both TSO and DSO promoted PCIs, providing them with
priority status in national administrative and legal procedures ( 6) and labelling them with
the highest national status applicable in the respective Member State.
In accordance with Article 8 of the TEN-E Regulation, the permitting schemes in
place should contribute to the most efficient and timely granting of the comprehensive
decision (7). Additionally, following Article 10 of the TEN-E Regulation, national
authorities are to accelerate the permit granting process for each category of PCI adapting
their requirements for start of the permitting process and project submission in
accordance with the project nature, size, need (or not) for an environmental impact
assessment and any other need of fewer authorisations to reach the ready to build phase.
In this sense, Article 10, empowers Member States to exclude the requirement of a pre-
application phase for permitting granting processes dealing with projects that do not
require it or would not benefit from it. Lastly, the Article clarifies that its time limit
requirements should not be applied to the prejudice of shorter permitting durations
imposed by the Member State (8).
From the combined reading of the provisions results that permit granting processes
should be tailored to the project’s needs and characteristics and their difference from
classical energy transmission projects cannot lead to a worst treatment. It follows that, to
ensure an efficient national permit granting process for smart grids, NCAs must assess to
what extent DSO-promoted projects are treated in a suitable manner, i.e. to what extent
(6) To the extent these are available at the national level.
(7) Article 8(3) TEN-E Regulation
(8) Article 10 (3) and (9) TEN-E Regulation
3
does the national system ensure that all benefits available to TSO project promoters are
also available to DSOs. Alternatively, in case such beneficial regimes are not directly
applicable to DSOs, NCAs should assess whether DSOs are treated under a permitting
regime with an equivalent degree of benefits. In that sense, NCAs should also ensure that
the national requirements are suitable to be imposed on DSO promoted PCIs. That
implies that they do not represent unnecessary or unjustifiable burdens on smart-grid
PCIs that are not faced by identical non-PCI projects at DSO level, nor that the burdens
faced could only be justified to apply to TSOs due to their different configuration,
monopolistic position, broader geographical coverage, or any other distinctive trait not
shared with DSOs. (9)
In parallel, DSOs should build the capacity that allows them to efficiently manage
the smart grids permit granting process, and devise and submit all the necessary
documentation in a timely manner. This can be done by developing the internal
competence and expertise to deal with permitting matters or through the comprehensive
use of contractors with relevant experience.
2.2. Decentralization of project location and contact with the authorities
concerned
A smart grid project may consist of reinforcements and the development of new
infrastructure in a non-linear fashion, i.e. in punctual locations covering a considerably
wide geographic area.
Promoters have reported that the contact with authorities concerned is not always
mediated by the NCAs, identifying an issue of lack of guidance and support when
communicating with the different authorities. This lack of guidance hinders the
promoter’s ability to meet the different requirements they face. In addition, lack of
support from the NCAs, allows for the authorities concerned to request whatever
documentation they consider necessary according to their own interpretation of the
applicable rules, meaning that promoters are dealing with different requirements for the
same issue depending on the region or municipality. The promoters are not able to
dispute the authorities’ concerned interpretation of the regime without incurring
substantial delays afferent with launching legal challenges or administrative complaints.
Furthermore, as regards the communication with the national environmental authorities,
promoters have reported that, these are contacted late in pre-application phase of the
permitting process, after the notification of the projects. This leads to environmental
concerns regarding the projects materializing late, leaving a short timeframe for the
promoters and the authorities to react. This requires quick adaptations of the project by
the project promoters which is not ideal.
The TEN-E Regulation establishes in Article 8(3) different permitting schemes
which can translate in different responsibilities for NCAs leading them to establish
different relationships with the authorities concerned. In short:
(9) Generally, the system should provide equivalent treatment to TSO and DSO backed PCIs in terms of administrative
and legal treatment with all forms of expedited and most beneficial treatment, as well as any other forms of support
available to certain promoters. Differences in treatment should take place only, when justified by different technical
specifications of the project, and even then, the NCA should strive to ensure that the quickest and most beneficial
permitting treatment possible is available to the PCI promoters.
4
- Under the integrated scheme, NCAs will issue the sole legally binding decision,
therefore any contact with authorities concerned is expected to be of the
initiative of the NCA and not involve the promoter.
- Under the coordinated scheme, the legally binding decisions are issued by the
authorities concerned, or the NCA, in the absence of a decision by the authority
concerned. The NCA should coordinate the process drawing up schedules,
organising work groups and managing the contact with the authorities
concerned. As such, under this scheme, contact with the authorities concerned
is expected to be mainly handled by the NCAs with minimal involvement of the
promoter. Where the involvement is necessary it is to be facilitated and
mediated by the NCA.
- Under the collaborative scheme, NCAs cannot issue decisions in the absence of
one by the authorities concerned, but they retain the role of coordinators of the
procedure, drawing schedules and monitoring compliance. Under this scheme,
contact with the authorities concerned can be expected to involve project
promoters, who represent their own interests, but the dialogue should be
initiated, facilitated, and mediated by the NCA which manages the procedure.
Even if the permitting needs cannot be considered simultaneously, NCAs should
work with project promoters establishing clusters of works that can be authorized
simultaneously due to their geographical proximity or overlapping time frame when
determining the permitting schedules mentioned above.
Furthermore, where PCIs require decisions to be taken in two or more Member
States, Article 8(5) establishes that the relevant NCAs should ensure efficient and
effective cooperation and communication among themselves across the permit granting
process. Additionally, it provides that Member States should provide joint procedures to
the extent possible and provide in particular joint assessments of environmental impacts.
Lastly, the establishment of the duration and implementation of the permit granting
processes as provided by Article 10(6) of the TEN-E Regulation applies in this situation
as well. The NCAs must cooperate with the promoter, and other authorities concerned,
assessing the scope of the reports and documents to be provided by promoters as part of
the application file (including any environmental reports) and mediate the contact with
promoters when missing information is identified. During the pre-application procedure,
NCAs should establish the scope of the documents and reports required under the
checklist established in the manual of procedures and draft (in cooperation with
promoters and authorities concerned) a schedule which specifies the decisions and
opinions to be obtained, procedure stages and their duration, major milestones, concerned
stakeholder, authority resources planned and additional resources that might be needed
(10).
Moreover, the TEN-E Regulation clarifies that requests for information and
documentation are to be made during the pre-application phase. In the statutory permit
granting phase additional requests can only be made if justified by changes of
circumstances (11). Consequently, the diverse interpretations of the authorities concerned
(10) TEN-E Regulation Article 10m paragraph 6 (a) and (b) and Annex VI paragraphs (1) (e) and (2).
(11) TEN-E Regulation article 10(6) a) and c) and final
5
leading to requests for additional assessments after the pre-application phase indicate an
inadequate implementation of the TEN-E Regulation.
To address the mentioned issues, NCAs must respect the TEN-E Regulation
provisions, while taking into consideration the entirety of the project’s geographic scope.
Regarding, projects with physical infrastructure spamming over two different
Member States, the following scenarios could be considered:
- If the cross-border elements of project are physically connected it may not
make sense to split the projects into sections in each of the respective Member
States. In this situation the communication and coordination between the NCAs
is key to ensure that the projects are deployed and implemented within the
expected timeframe. The elements of the project should be seen as parts of a
whole, with assessments, document requests, public consultations, and any
other administrative steps not being duplicated by the NCAs, and authorities
concerned. To achieve it, the use of digital formats for consultations and
documents should be used to simplify and accelerate the communication across
authorities, and between authorities and promoters.
- When the project is not continuous across a border, it may be warranted to split
the project into two main sections. Nevertheless, the entirety of the project in
each jurisdiction should, as much as possible, be considered as a single project.
In this sense NCAs communication is essential to coordinate the schedule of
the permit granting process, having requests, as much as possible, issued
simultaneously. The coordination simplifies the procedure for promoters,
preventing one-sided delays from hindering the entirety of the project,
precluding unnecessary duplication of requests, and facilitating the promoter-
authority dialogue.
In what regards the specific issue of lack of communication between NCAs and
project promoters, the provisions of the TEN-E Regulation impose a need to provide
timely and comprehensive support to project promoters. To do so, NCAs should maintain
constant contact with promoters during the permit granting process offering support and
guidance where needed. This can be achieved by, amongst other things, holding bilateral
discussions early after the project receives the PCI status, to assess the project permitting
and public consultation needs, advise on how to best address them, and establish and
support contacts with the relevant authorities. Such dialogues ensure compliance with the
requirements of Article 10 of the TEN-E Regulation, improves the early-identification of
issues, simplifying their mitigation, and guides promoters from other jurisdictions. The
support of NCAs is also of particular relevance in the relation between promoters and
authorities concerned in charge of environmental impact assessments. The NCAs
experience as regards permitting different projects, with different environmental issues,
makes them a key support with other authorities concerned. This may help in the early
identification of issues and of available exemptions from environmental assessments.
Considering the added benefits, it is warranted for Member States to allocate financing
for specific NCA resources offering guidance and support for project promoters.
6
2.3. Sequential nature of the permitting procedure
When compared to standard PCIs of grid development and reinforcement, smart
grid projects are not capable of addressing all their permit needs at the beginning of the
project implementation. This is caused by the need to build part of the project before
reaching the necessary degree of certainty over the remaining infrastructure needs ( 12).
However, project promoters have been requested to provide NCAs with the precise
planed location of their assets and the associated environmental impact studies during the
pre-application phase, when they often lack such detailed information for the entire
project. As a result, promoters have “sliced” their projects into smaller sections that they
can detail with certainty, before completing the design of the subsequent sections of the
projects. This implies that permits are requested sequentially for the “sections” of the
projects, leading to require several permits (at least one for each project section) to
complete a single project.
The “slicing” of projects and its non-linear implementation of decentralised assets,
also affects how public consultations are conducted. These will take place in a non-
centralized manner and tend to focus on the local element of the grid in the concerned
area. Due to their proximity with the affected communities these local public
consultations can be used to foster public acceptance. On the flipside, this is reported to
result in more technical public consultations, as the discussions focusing on elements in
isolation from the whole project is perceived to affect the overall impression of the
public. , In this respect, it would seem recommended for project promoters to take such
matters into account when drafting the concept for public participation in line with
Article 9(3) of the TEN-E Regulation in order to achieve the best public engagement that
both fosters public acceptance at regional and local level, but also takes the entire project
into account. Moreover, project promoters should invest into building their capacity to
design early public consultations that allows for the public to gain knowledge about the
entire project without being overwhelmed by its technical details. To acquire the capacity
required, promoters should either resort to contractors with experience on public
consultation and stakeholders’ engagement or ensure that their internal resources are able
to deploy a non-technical, comprehensive, and effective project for local consultation.
Additionally, the promoters must ensure that the project website is kept up to date with
all relevant information available in the relevant languages as provided for under article
9(7) of the TEN-E Regulation. On the NCAs side, while they will have to rely on
promoters’ ability to draft project public consultations, if the NCA has the practical
experience with similar projects it may provide guidance on the format, timing, and
geographical separation and centralisation of the consultations leading to an efficient
process that complies with the requirements of Article 9 of the TEN-E Regulation.
Lastly, on the subject of public consultations it is also relevant to foster the use of
digital communication tools and the sharing of the relevant documents also in digital
format in line with Annex VI of the TEN-E Regulation. This fosters engagement with the
public by facilitating access to relevant information and allowing to reach stakeholders
from broader geographic areas.
Regarding the issue of multiple permit requests, it is important to consider and
assess the possibilities for the tailoring the permitting granting procedures to smart grid
(12) Necessary degree of certainty, in this context, means that the project promoter has reached a stage in which it
understands the project needs enough to establish a local planning which is clear enough to meet the detail
threshold required by the permitting authorities under the national regime.
7
PCIs and acknowledge that projects may be composed of a multitude of small
investments: either new assets or modernizations of existing investments. As such, it is
warranted to access possibilities to reduce the number of assets that require permits too
only new assets that substantially alter the existing infrastructure, or those capable of
having an impact on the environment. In that sense, minor changes as upgrades,
maintenance, or the addition of parallel infrastructures of reduced impact might not
require permits and should be able to rely on the authorisations in place for the original
infrastructure.
2.4. Validity of the permits
The promoters have also reported that some Member States’ systems impose a
maximum duration for certain permits, requiring the promoters to request an extension or
a new permit, particularly for building permits (13). In some cases, this implies that
promoters have to do, or re-do, certain assessments and studies, leading projects to be
delayed beyond the maximum duration of 3.5 years ( 14), even if the project did not
require an environmental assessment or pre-application phase.
In the case of smart grid PCI’s, works tend to last for around five years, and the
validity of the building permits as reported by most project promoters is shorter than five
years. Therefore, requesting additional/new permits is unavoidable. Promoters already
mitigate the effects by “slicing” projects into sections, or clusters of assets, and balancing
the permit validity with the need to conduct works sequentially. Promoters also tackle the
issue by planning the project development with different asset clusters’ allowing permit
granting processes to run in parallel as much as possible. Promoters also submit re-
permitting requests before the expiry of the respective permits. However, these
mitigation measures may result in burdensome and complex project planning, and do not
exclude the risk that “repeated” sets of permits are required for a single project section.
The TEN-E Regulation defines the comprehensive decision in article 2(3) as the
result of the permit granting procedure indicating that projects have reached a ready to
build phase (15). The TEN-E Regulation does not address the validity of the
comprehensive decisions and its constituting elements, but it stands to reason that the
national legal systems must establish validity regimes that do not devoid the decision of
its fundamental role of marking that works can be started. Furthermore, validity regimes
must also not jeopardise the projects’ ability to comply with the maximum duration of
the permit granting process under the TEN-E Regulation. In this sense, the impact of the
validity of the permits must be balanced with their role as a legal safeguard against
changes of circumstances and an incentive for permit holders to conduct the works within
a reasonable period. To comply with the TEN-E Regulation while balancing the Member
States interest on permits validity, permits duration must be calibrated according to the
reality of the projects. In order to do so for smart grid projects four measures could be
identified:
(13) Average reported duration of 2-3 years.
(14) Article 10(2) TEN-E Regulation
(15) The permit granting procedure is described in article 10 of the TEN-E Regulation and the comprehensive decision
as the document or set of documents resulting of the permitting process is addressed in Article 8 of the TEN-E
Regulation.
8
- First, issuing permits with a duration that matches the estimated completion of
the projects, as this should exclude the need to request additional permits.
- Second, ensure that the validity period does not run out when works are
ongoing. This can also translate into not counting the work periods towards the
validity limit, penalising only promoters who do not conduct works.
- Third, ensure that permits are automatically renewed for ongoing projects
without additional costs and especially without the need to conduct additional
assessments.
- Fourth, deploy longer lasting permits encompassing an array of works and
allowing the promoter to conduct the works in the order that is most suitable
with the project design.
Lastly, the permitting schedules established by the NCAs in cooperation with
promoter and authorities concerned should afford sufficient time for projects to conduct
their works serving as much as possible as a basis to extend the validity of permits and
limiting the need to request additional permits on the basis of new assessments.
2.5. Project costs
When compared to other infrastructure projects, smart grid projects, although varied
in size and cost, tend not to be as costly as larger infrastructure. Nonetheless, due to the
different type of works they entail (16) and the sequential manner in which they need to
be implemented, they can require intricate financial planning dealing with personnel
allocation, uncertain equipment costs, and unclear administrative costs of acquiring the
necessary authorizations and conducting the associated assessments.
Promoters have reported that, in some jurisdictions, permit granting processes for
sequential permits have associated charges. In fact, promoters stated that in certain
jurisdictions those costs can be identical to that of the first request, which is calculated as
a percentage of the project cost. Considering the size of PCIs, their costs can be
significant, and their multiplication represents a considerable burden. In the case of smart
grids, the potential costs increase may disincentivize promoters from requesting permits
in the most expedited manner. Promoters may have an interest to behave in the most
cost-efficient manner, which may justify halting permit requests until the developments
for parallelly-developed elements are finalised before launching the next permits’ “batch
request”. Such behaviours can result in sub-optimal construction, and permit granting
duration.
The TEN-E Regulation does not provide suggestions for financial planning and
resources allocation. Nevertheless, it does call for simplification and streamlining of
permit granting procedure, consequently pushing for a reduction of the administrative
costs faced by project promoters to the minimum possible (17). Additionally, as seen
(16) Refurbishment and upgrade of existing grid infrastructure, creation of new substations and creation of a
communication infrastructure parallel to the grid in a large and non-continuous geographical area.
(17) See TEN-E Regulation paragraphs (42) (43) of the preamble, together with the objectives described in Article 1
paragraph 2. (b), and the willingness to streamline environmental assessment procedures from Article 7 (5).
9
above, during the pre-application procedure NCAs must cooperate with the promoter,
and other authorities concerned, establishing a schedule which specifies the decisions and
opinions to be obtained, procedure stages duration, major milestones, concerned
stakeholders, authority resources planned, and any additional resources required. Lastly,
the TEN-E Regulation also addresses the issue indirectly by requiring that the permit
granting processes are established in the most efficient way, therefore in a manner
tailored to address the project needs (18).
To address the cost concerns applicable to smart grids in line with the Regulation,
the permitting granting procedure’s cost must be reduced to a minimum necessary. As
such, one could consider possible centralisations of permitting procedures and ensuring a
suitable validity for the permits to reduce administrative costs. However, the fundamental
action in this regard, is that NCAs assess their national systems and assure that the
process fits project characteristics and, to the extent possible, avoid the need for re-
application or renewal of permits, as these can lead to delays and hurdles in
implementation. NCAs should also ensure that the permitting schedules established in
cooperation with the promoter and the authorities concerned afford the project sufficient
time to conduct its works.
(18) TEN-E Regulation, Article 8(3): “Member States shall implement the schemes in a manner which, according to
national law, contributes to the most efficient and timely issuing of the comprehensive decision.”
Please note that the requirements of the TEN-E regulation are flexible and are to be fulfilled in a suitable manner
that does not add administrative steps to the permitting granting processes or leads to delays.
10
Saatja: "EVANGELISTA Hugo" <
[email protected]>
Teema: Smart Grid Best Practices Paper_Draft
Kuupäev: 2023-04-12 13:44
Dear Members,
I am glad to share with you the draft paper (attached and uploaded on
CIRCABC). In order to keep continue with its development we ask you for any
written comments that you may have within one month.
We will also have an opportunity to address any pressing comments in the
next NCA platform meeting, but we would like remind you that we stand
available to any bilateral exchange to improve the text, and incentivise you
to reach out to us if helpful.
Once the text is finalized we intend to publish the non-paper on our
website, making it easily available to all interested parties.
Thank you all for your continued collaboration.
Kind regards,
HUGO EVANGELISTA
Legal & Policy Assistant
European Commission
Directorate-General for Energy (ENER)
Infrastructure and Regional Cooperation (ENER.C.4)
BRU-DM24 06/117
B-1049 Brussels/Belgium
+32 229 - 59274
<mailto:
[email protected]>
[email protected]