Dear members,
Please find attached the final agenda for Monday which includes an access link.
Please be reminded that the European Commission units in charge of the Renewable Energy Directive
and the Nature Restauration Law will be presenting in this meeting. As such, we incentivise you to use
this opportunity to clarify any concerns you might have with them and to bring to the discussion any
possible permitting acceleration measures that you are considering and that might have a link to
environmental law.
Additionally, please find attached the minutes from the last meeting for your approval. If I do not have
any comments on the minutes until next Friday, they will be uploaded on CIRCABC as per usual.
As this meeting has a shorter agenda, with only one national regime presentation, there will be an
ample opportunity for dialogue amongst ourselves and also with all the colleagues presenting. Looking
forward to a productive discussion with you all on Monday.
Kind regards,
Hugo
HUGO EVANGELISTA
Legal & Policy Assistant
European Commission
Directorate-General for Energy (ENER)
Infrastructure and Regional Cooperation (ENER.C.4)
BRU-DM24 06/117
B-1049 Brussels/Belgium
+32 229 - 59274
[email protected]
Need help? Go to https://help.webex.com
14:00 | (UTC+02:00) Brussels, Copenhagen, Madrid, Paris | 2 hrs
Join meeting
More ways to join:
Join from the meeting link
https://ecconf.webex.com/ecconf/j.php?MTID=m25a8e43ebbbeb43b9aa30daa63
bd63f9
Join by meeting number
Meeting number (access code): 2744 309 4440
Meeting password: ubPGsTH*348 (82747840 from phones)
Tap to join from a mobile device (attendees only)
+32-262-00867,,27443094440#82747840# Belgium Toll
+352-2730-0072,,27443094440#82747840# Luxembourg Toll
Some mobile devices may ask attendees to enter a numeric password.
Join by phone
+32-262-00867 Belgium Toll
+352-2730-0072 Luxembourg Toll
Global call-in numbers
Join from a video system or application
Dial
[email protected]
You can also dial 62.109.219.4 and enter your meeting number.
EUROPEAN COMMISSION
DIRECTORATE-GENERAL FOR ENERGY
Directorate C – Green Transition and Energy System Integration
C.4 – Infrastructure and Regional Cooperation
Meeting of the National Competent Authority (NCA) Platform
16 December 2022, Online
Minutes
The European Commission welcomed the NCAs by informing of last-minute cancelation
on the first agenda point (presentation) and thanking the members for their contributions
towards the 2022 monitoring exercise and the permitting regime mapping exercise. The
commission gave a status update on the ongoing platform initiatives and restated the
importance of identifying measures for permitting acceleration in all Member States.
1. Presentation of National Permitting Regimes
1.1. Presentation of the Latvian permitting regime
The Latvian NCA presentation elaborated on the status of highest national significance
which may be available to PCI projects and awarded by a Cabinet of Ministers order.
While this status is available for some PCIs, it requires additional requirements and
assessments. It is available only to key projects based on their specificities.
The national significance status accelerates the awarding of building permits and
simplifies coordination with landowners when projects affect their ownership rights.
Additionally, environmental assessments are required for lines of over 220 kV and wind
power over 50 MW, but the national significance status can speed up the assessment for
large wind and solar power plants. This leads to permits for capacity over 0,5 MW of
projects with this status being granted within a month (1).
More generally on the role of the NCA tackling permitting delays, this is focussed on
contacting the relevant municipal and environmental authorities (which retain their
autonomy) through information letters.
The Latvian NCA is also the RES one-stop shop. In terms of cross-border coordination,
they coordinate closely amongst the three Baltic States.
(1) Note that projects under 0,5 MW do not require a permit decision, but just an approval for connection
to the distribution grid.
Commission européenne/Europese Commissie, 1049 Bruxelles/Brussel, BELGIQUE/BELGIË - Tel. +32 22991111
Office: DM24 06/145 - Tel. direct line +32 229-62369
1.2. Presentation of the Italian permitting regime
The Italian NCA presented its national permitting process the PCI Sacoi 3, clarifying that
building permits can only be requested after the preliminary public consultations
(Conferenza di Servizi). The process continues, with an environmental impact
assessment (EIA), before the building permit is granted and the final public consultation
takes place. The final public consultation is in essence a validation of the first assessment
done by the TSO.
Regarding the preliminary and final public consultations, these ensure that, preparations,
impacts landowners and any other issues are identified in advance, giving promoter a
chance to adapt and change their project early on. Regarding EIAs the Italian NCA
informed that they might not be required for certain projects in the future, as changes in
procedure, mainly aimed to mitigate overlaps in procedure, made EIAs not necessary, for
example in the case of underground and submarine cables.
Both of these elements are made available for permitting processes regardless of PCI
status.
The Italian permitting regime is the same for all grid projects, PCI and non-PCIs. The
main goal of the procedure is not to overlap the same authorities in the permitting
process.
2. Substantive discussion:
2.1. Comprehensive decision under the TEN-E Regulation
The Commission clarified the definition of the comprehensive decision, in accordance
with what it means under the different permitting schemes of the TEN-E Regulation and
clarified that it should not lead to additional decision-making regardless of the document
format. In other words, following Art 8(3) para 5 of the TEN-E Regulation it must be
implemented in the most efficient manner and be already available after all the permits
that are in fact necessary to enter the ready to build stage (as e.g. building permits) are
obtained. It does not have to contain very local detailed permits, e.g. for parking near the
construction site or for the organisation of the construction site.
A short tour de table on the different NCAs practices took place:
IE - uses a letter format to grant project promoters certainty on the formal finalization of
the process and the consensus reached. It also marks the start of the period for review (8
weeks).
DK- Includes all the documents and decisions necessary to start works in the ground in a
descriptive permit listing. Minor details and authorisations are not included, but building
permits are as a way to ensure the relevance of the decision are included. The
environmental approvals take the most time to be obtained.
RO – All relevant permits are included in a final decision which lists all the permits
including the building permit, shortly after the permits themselves have been granted.
FR – No specific decision that all steps have been completed, just a step-by-step
approval. Authority reaches out to the promoter when all approvals have been obtained.
2
CY - Under its collaborative system the NCA is responsible facilitating, coordinating,
and monitoring the PCI licensing process, overseeing timely issuance of all opinions,
permits, approvals required by the relevant authorities, also of issuing the PCI licensing
manual.
MT- The NCA, under the integrated scheme, takes the binding decision as the competent
authority. Consultations of other authorities take place, with 30 days for consulted
authorities to reply, and the absence of replies amount to a positive decision.
2.2. Acceleration of permitting for grids
2.2.1. Presentation of the emergency regulation on the acceleration of
renewable energy deployment
The Commission made a presentation on the new emergency regulation on RES
deployment, currently under discussion for political agreement, addressing how it could
be relevant for the development of grids permitting.
2.2.2. Tour de table on national initiatives
IT – Proposals are already in force in Italy, namely the upgrade of existing EIA scheme
applies only to additional power capability.
AT – NCA informed that the ministry currently working on acceleration measures for
projects that do not require an EIA. When the act is finalized, it is expected to accelerate
RES deployment, but consent of the federal states still pending. This act will cover grids,
but an assessment on which grids will be covered is not yet available. Currently no
permit is required for cables up to 45KW.
DK – NCA looking into regulation impact on DSO and TSO and assessing the
possibilities increased building capacity. Currently looking into exemptions from the
natural restoration law requirements for PCIs, and the possibility of having permitting
procedures running in parallel to address any lack of flexibility in the system and ensure
cross-border connections. National exercise expected to be concluded in the spring.
2.3. Reporting under the TEN-E Regulation
2.3.1. ACER presentation on the PCI monitoring and data collection and
the challenge for future reporting exercises
ACER presented the PCI monitoring process under the old TEN-E Regulation, its tools
for data collection, and looking into challenges under the new TEN-E Regulation and the
solutions that create the least administrative burden. ACER suggested holding a detailed
presentation of its IT tools and experiment on PCI monitoring in the first semester of
2023.
2.3.2. Initial assessment of the 2022 NCA reporting exercise
The Commission presented the initial assessment of the 2022 NCA reporting exercise,
emphasising the overall status of projects and delays identified.
3
3. Miscellaneous & closing remarks:
The Commission thanked the NCAs for the first year of the Platform, recapping the
ongoing work on the smart grid permitting paper, national regime mapping exercise and
the revision of the guideline on streamlining environmental impact assessments, and
restating its commitment to finalise it on the first half of 2023.
In light of the ongoing exercises, the members agreed to hold the next NCA Platform
meeting mid-April 2023.
Actions Points
Next NCA platform meeting will take place mid-April 2023
The Commission to share the draft paper on Smart grid permitting with the
NCAs.
The Commission will circulate a draft agenda ahead of next meeting
The Commission to prepare and launch a mapping exercise of how
comprehensive decisions are addressed by the different NCAs.
The Commission will make all the presentations available on the NCA Platform
CIRCABC library.
NCAs to prepare to share their experience on PCI monitoring, consider any
additional data requirement compared to the current data collection, and discuss
legal or technical issues concerning the practical difficulties of ACER tools for
data collection. For an NCA meeting in the first semester of 2023.
NCAs to provide comments on the smart grids’ permitting paper ahead of the
next NCA platform meeting.
4
EUROPEAN COMMISSION
DIRECTORATE-GENERAL FOR ENERGY
Directorate C – Green Transition and Energy System Integration
C.4 – Infrastructure and Regional Cooperation
Meeting of the National Competent Authority (NCA) Platform
24 April, 14:00 - 16:00
Webex
Access Link: Webex (by CISCO)
AGENDA
14:00 - 14:10 Welcoming remarks
- Presentation of the results of the 2022 reporting exercise conclusions.
14:10 - 14:55 Discussions on substance
- Conclusion on Grid permitting under the revised Renewable Energy
Directive:
o Presentation for DG ENER Unit C.1 on the agreement reached with the
Parliament and the Council on the permit granting procedure applicable to
grids under the revised Renewable Energy Directive
o Tour de table
- Environmental assessments:
o Update from DG ENER on the need for MS to adopt measures to
streamline environmental impact assessments under the TEN-E
Regulation
o Presentation from DG ENV Unit D.3 on the Nature Restauration Law
negotiations and the concept of Overriding Public Interest
Commission européenne/Europese Commissie, 1049 Bruxelles/Brussel, BELGIQUE/BELGIË – Tel. +32 22991111
Office: DM24 06/117 – Tel. direct line +32 229-59274
o Tour de table
14:55 - 15:40 Presentation from Members on their national regimes:
- Presentation of the German permitting regime for PCIs
o Q&A
15:40 - 16:00 Miscellaneous & closing remarks
- Update on the non-paper “Best practices on permit granting systems applicable to
smart grids projects”
- Organisation of the upcoming meetings: attendees and date