Veeteede Amet · 28. oktoober 2015
Sisu (failidest)
IHB File N° CBSC-1
CIRCULAR LETTER 76/2015
26 October 2015
OUTCOME OF THE 13th MEETING OF THE CAPACITY BUILDING SUB-COMMITTEE
(CBSC13) AND THE 2016 CAPACITY BUILDING WORK PROGRAMME (2016-CBWP)
Reference: IHO CL 16/2015 dated 20 February – Thirteenth Meeting of the Capacity Building
Sub‐Committee (CBSC13, Mexico City, Mexico, 27-29 May 2015 and Seventh Meeting
of the Inter‐Regional Coordination Committee (IRCC7) Mexico City, Mexico, 1-3
June 2015
Dear Hydrographer,
1. The 13th Meeting of the IHO Capacity Building Sub-Committee (CBSC13) took place in
Mexico City, Mexico, from 27 to 29 May, hosted by the Secretaría de Marina of Mexico in the
Centro de Estudios Superiores Navales - the Naval Staff College of Mexico. The Meeting was
chaired by Mr. Thomas Dehling (Germany) and attended by 18 members and 14 observers from 13
Regional Hydrographic Commissions (RHCs), 19 Member States and two observing organizations.
2. The minutes of the CBSC13, together with all documents tabled at the meeting are available
on the IHO website (www.iho.int → Committees & WG → CBSC → CBSC13). The most
significant topics discussed at the meeting are summarized below.
Impact of the IHO CB Strategy
3. The Sub-Committee reviewed the impact of the revised IHO Capacity Building (CB) Strategy
approved by the 5th Extraordinary International Hydrographic Conference (EIHC-5) on the work of the
CBSC, especially in building the Management Plan, the access of non-Member States only to Phase 1
activities, the need to identify larger and comprehensive projects to attract funding from donor
agencies and the development of a Public Relations paper to raise awareness of the importance of the
IHO CB Programme and to improve its visibility.
Workload associated with Capacity Building
4. The CBSC considered the increasing number of CB activities, the associated administrative
workload, intersessional correspondence and the workload associated with meetings. The Sub-
Committee acknowledged the existing limitations of the IHO Secretariat to support the administration
of the CB Programme and the challenges that this raises.
Interaction with other IHO bodies
5. The increasing interaction with the World-Wide Navigational Warning Service Sub-
Committee (WWNWS-SC), the Marine Spatial Data Infrastructures Working Group (MSDIWG) and
the Tides, Water Level and Current Working Group (TWCWG) was considered with respect to
feedback concerning the CB activities in which they were involved, and the need for further support
and the development of course material.
IHO Publication C-55
6. The CBSC considered the development of the current IHO Publication C-55 - Status of
Hydrographic Surveying and Nautical Charting Worldwide and its transition to a GIS database
environment, the development of supporting databases (the IHO Country Information System and the
regional database), the progress made in the IHO GIS infrastructure and the possibilities for creating
an improved C-55 function by using the values of Zones of Confidence (CATZOC) extracted from
ENCs as a proxy for the quality of the underlying survey data. This work will lead to the ability to
create country profiles that can better support the decision-making process when assessing priorities
and allocating CB resources.
Risk assessment methodology
7. The Sub-Committee commended the work done by New Zealand in developing an evidence-
based risk assessment methodology and its implementation in the area of the South West Pacific
Hydrographic Commission to establish priorities for surveys and charting. Other developments were
presented by the UK (describing the Organization of the Eastern Caribbean States – OECS Project),
the Republic of Korea (describing the East Asia Hydrographic Commission Training, Research and
Development Center), France (describing the East Atlantic Hydrographic Commission Definition
Study for a Long Term CB Project) and Mexico (describing strengthening the hydrographic
capabilities in Meso-America and Caribbean Sea area).
In-kind contribution and cooperation
8. The CBSC acknowledged the continuing contributions made by the Republic of Korea and
Japan, through the Nippon Foundation (NF), to the IHO CB Programme. The Sub Committee also
acknowledged the significant contributions from the International Maritime Organization (IMO) and
the International Association of Marine Aids to Navigation and Lighthouse Authorities (IALA) in
supporting the development of hydrographic services in developing States through the delivery of joint
capacity building programmes.
CB Management
9. The Sub-Committee reviewed draft CB Procedure 9 - Technical Visits and agreed to use this
draft procedure for one year and obtain feedback before considering its formal approval at the next
meeting of the CBSC.
10. The CB Management Plan (CBMP) was reviewed and approved by the meeting as the basis
for the 2016 CB Work Programme (CBWP). The CBSC expressed some concern that there were
currently only limited financial resources available to execute the full 2016 CBWP. The in-kind
contributions from Republic of Korea and from the Nippon Foundation of Japan will be allocated to
the earmarked activities and the remainder of the programmes will have to be executed using the
annual contribution from the IHO budget to the CB Fund.
2016 Capacity Building Work Programme (2016 CBWP)
11. The Annex to this letter presents the 2016 CBWP taking into account the available resources
and priorities. In previous years the CBWP only reflected the activities for which funds were available
at the time of approving the plan. The 2016 CBWP lists all the activities that have been endorsed by
the Sub-Committee in priority order. Those for which funds are currently not available have been
marked as "Not funded yet". The Sub-Committee invited the Chair and the IHB to monitor the CB
funds and seek additional resources, and in the event that additional funds become available during the
inter-sessional period, to take into account the additional funds available, the priority listing and the
feasibility of implementing projects at relatively short notices, and to propose to the Sub-Committee
those currently unfunded projects that could be then implemented.
12. The total of 31 endorsed projects would require 952 000 Euros. Of those 31 projects, 21 are
currently unfunded and will need an additional 385 000 Euros in order to be executed. If and when
additional funds become available, the previously unfunded projects will be undertaken as far as
possible in priority order and the relevant RHCs will be invited to take the actions required for their
implementation. In addition, the 2016 CBWP includes two training courses that will be executed with
the support of the IMO.
Additional contributions
13. The Directing Committee takes this opportunity to invite the Member States to consider
providing in-kind contributions to the IHO CB Fund in accordance with IHO Resolution 5/2004 as
amended, in order to progress the delivery of the Capacity Building activities. Member States are also
invited to liaise with existing national and regional funding agencies to attract funds for the IHO CB
Fund.
14. An additional possibility for those Member States able to assist in the execution of the 2016
CBWP is to sponsor endorsed CB activities directly, without the need to transfer funds to the CB
Fund. This method of support is particularly suitable for the delivery of training and workshops.
Next meeting
15. The 14th meeting of the CBSC (CBSC14) will be held from 24 to 26 May 2016 in Abu Dhabi,
hosted by the United Arab Emirates. Representatives of Member States who may require a visa are
advised to submit their applications well in advance. CBSC14 will be followed by the 8th meeting of
the Inter-Regional Coordination Committee (IRCC8) from 29 to 31 May 2016 which will also be held
in Abu Dhabi.
Action Requested of RHC Chairs and CB Coordinators
16. In order to fully implement the 2015 CBWP, the Directing Committee requests the Chairs of
the RHCs and CB Coordinators that have not already done so, to provide to the IHB the names of the
Project Leaders and the anticipated budget required for outstanding activities in the 2015 CBWP in
accordance with CB Procedure 8.
17. The Directing Committee also requests RHC Chairs to confirm and implement the approved
projects in the 2016 CBWP as early in the year as possible in order to facilitate the financial
management of the CB Fund by the IHB and the adoption of contingency plans by the CBSC when
appropriate.
On behalf of the Directing Committee
Yours sincerely,
Mustafa IPTES
Director
Annex: 2016 CB Work Programme (CBWP).
ANNEX TO IHO CL 76/2015
2016 CB WORK PROGRAMME
IHO WP Element: Capacity Building Assessment - Technical and High-Level Visits
No. Events Responsible Budget Resources
Technical Assessment & Advice - Samoa (former
A-01 SWPHC 6,000.00 € IHO
2015 CBWP A-07)
A-02 High-level Visit to Tanzania SAIHC 8,000.00 € IHO
A-03 Technical Assessment & Advice – Tuvalu SWPHC 3,326.00 € IHO
High-level Visit to Lebanon and Technical Visit to
A-04 MBSHC 3,400.00 € Not funded yet
Albania
A-05 Technical Visit to Timor Leste EAHC 7,800.00 € Not funded yet
- 28,526.00 €
IHO WP Element: Capacity Building Provision - Technical Workshops, Seminars, Courses
No. Events Responsible Budget Resources
P-01 ROK Category A Programme IHB 184,000.00 € ROK
P-02 Training for Trainers - Basic Hydrography EAHC 50,000.00 € ROK
P-03 ROK Category B Programme (second phase) IHB 84,700.00 € ROK
P-04 Nippon Foundation CHART Project IHB 195,000.00 € NF
P-05 Seminar on Raising Awareness of Hydrography MACHC 15,500.00 € IHO
P-06 E-learning experimentation (MSI) EAtHC 20,000.00 € IHO
P-07 MBES Processing (5 days) NIOHC 8,500.00 € Not funded yet
Technical Workshop for PICTs in Formulating and
P-08 Implementing Strategic Development Plans for SWPHC 36,000.00 € Not funded yet
Hydrography
P-09 CB Assistant IHB 10,000.00 € Not funded yet
P-10 Tide Training Course SWAtHC 16,400.00 € Not funded yet
P-11 MSI and Hydro Governance Workshop MACHC 19,952.00 € Not funded yet
Workshop on technics, methodology of MBES data
P-12 SEPRHC 26,911.00 € Not funded yet
processing
P-13 Chart Scheming (3 days) NIOHC 16,627.00 € Not funded yet
P-14 MSI Regional Workshop SWPHC 25,000.00 € Not funded yet
P-15 MBES setting to work project for Mozambique SAIHC 9,604.00 € Not funded yet
P-16 Multi-beam Training Course SWAtHC 25,000.00 € Not funded yet
P-17 MSDI Workshop for Spanish speakers MACHC 23,658.00 € Not funded yet
P-18 Introduction to MSDI and Data Management NIOHC 14,344.00 € Not funded yet
P-19 Satellite Derived Bathymetry Workshop MACHC 21,734.00 € Not funded yet
P-20 Advanced ENC Production (5 days) NIOHC 8,500.00 € Not funded yet
Workshop on LIDAR technology for shallow
P-21 SEPRHC 26,540.00 € Not funded yet
waters
P-22 ENC Production and QA RSAHC 25,110.00 € Not funded yet
P-23 Satellite Derived Bathymetry EAHC 20,450.00 € Not funded yet
Cartographic Production Database System
P-24 EAHC 19,150.99 € Not funded yet
Workshop
P-25 Multi-beam Survey and Seabed Classification EAHC 20,500.00 € Not funded yet
Regional Training Course in Basic Hydrography In-kind from
P-26 SAIHC -
and Hydrographic Governance for Southern Africa IMO
IHO WP Element: Capacity Building Provision - Technical Workshops, Seminars, Courses
No. Events Responsible Budget Resources
Regional Training Course in Hydrographic Field In-kind from
P-27 EAtHC -
Operator for Francophone Africa IMO
In-kind from
P-28 GEBCO Training Project UHN -
NF
Subtotal of P (Provision) - 923,180.00 €
Total 951,706.00 €
ROK 318,700.00 € Subtotal ROK
IHO 52,826.00 € Subtotal IHO
NF 195,000.00 € Subtotal NF
Not funded
385,180.00 € Not funded yet
yet