Töövõtja: Smart Arch OÜ
Peterburi tee 13-5, Tallinn
11411 Harjumaa
Telefon: +372 512 6666
e-mail:
[email protected]
Omanikujärelvalve: MTR - EEO003618
Projekteerimine: MTR - EEP003505
Kesk tee 13 elamu
Eelprojekt
Harju maakond, Viimsi vald, Haabneeme alevik, Kesk tee 13
E-20-02
Objekti Tellija: Reet Neeme
Koostas: Kaspar Kissa
Kontrollis: Lembit Andres Tork
Saue
Mai 2020
SISUKORD
SISUKORD ................................................................................................................................................ 1
1.1 Sissejuhatus............................................................................................................................ 4
1.2 Ehitise tööiga.......................................................................................................................... 5
1.3 Üldandmed............................................................................................................................. 5
2 SITUATSIOONISKEEM ...................................................................................................................... 5
3 ASENDIPLAANILINE LAHENDUS ....................................................................................................... 6
3.1 Olemasolev olukord ............................................................................................................... 6
3.2 Plaanilahendus ....................................................................................................................... 6
3.3 Teed, platsid, krundisisene liikluskorraldus ja parkimine ...................................................... 6
3.4 Piirdeaed ja kõrghaljastus ...................................................................................................... 6
4 RADOON .......................................................................................................................................... 6
5 ARHITEKTUURNE OSA...................................................................................................................... 6
5.1 Krundi ja ehitise üldandmed ja tehnilised näitajad ............................................................... 6
5.2 Arhitektuurne üldlahendus .................................................................................................... 7
6 KONSTRUKTIIVNE OSA..................................................................................................................... 7
6.1 Konstruktsioonide üldine iseloomustus .................................................................. 7
6.1.1 Vundamenditaldmikud- ja seinad..................................................................... 7
6.1.2 Põrandad .................................................................................................................... 7
6.1.3 Vahelaed .................................................................................................................... 8
6.1.4 Seinad ......................................................................................................................... 8
6.1.5 Vihmavee süsteem ja veeplekid ....................................................................... 9
6.1.6 Aknad .......................................................................................................................... 9
Kesk tee 13; töö nr E-20-02 Mai 2020
Harju maakond, Viimsi vald, Haabneeme alevik, Kesk tee 13
6.1.7 Uksed........................................................................................................................... 9
7 Hoone sisearhitektuur ................................................................................................................... 10
8 KÜTE JA VENTILATSIOON............................................................................................................... 10
8.1 Küttesüsteemid .................................................................................................................... 10
8.2 Ventilatsioon ........................................................................................................................ 11
9 VEEVARUSTUS JA KANALISATSIOON ............................................................................................. 11
9.1.1 Veevarustuse allikas .................................................................................................... 11
9.1.2 Soojavee süsteem ................................................................................................ 11
9.1.3 Reovee kanalisatsioon ........................................................................................ 11
10 ELEKTER ........................................................................................................................................ 11
11 NÕRKVOOL.................................................................................................................................... 12
12 KESKKONNAKAITSE ....................................................................................................................... 12
12.1 Lammutus ja pinnasetööd ................................................................................................... 12
13 TULEOHUTUS ................................................................................................................................ 13
13.1 Üldist .................................................................................................................................... 13
13.2 Tuletõkkesektsioonid ........................................................................................................... 14
13.3 Põlemiskoorumus ................................................................................................................ 14
13.4 Evakuatsioon ........................................................................................................................ 14
13.5 Suitsueemaldus .................................................................................................................... 14
13.6 Kustutusvesi ......................................................................................................................... 14
13.7 Pääsud katusele ................................................................................................................... 14
13.8 Pääsud pööningule ............................................................................................................... 15
13.9 Tulekahju signalisatsioon ..................................................................................................... 15
13.10 Esmased kustutusvahendid ............................................................................................. 15
13.11 Küttesüsteemid................................................................................................................ 15
Kesk tee 13; töö nr E-20-02 Mai 2020
Harju maakond, Viimsi vald, Haabneeme alevik, Kesk tee 13
13.12 Läbiviigud ......................................................................................................................... 16
14 GRAAFILINE OSA ........................................................................................................................... 18
Kesk tee 13; töö nr E-20-02 Mai 2020
Harju maakond, Viimsi vald, Haabneeme alevik, Kesk tee 13
ÜLDOSA
1.1 Sissejuhatus
Käesolev eelprojekt on koostatud Harju maakond, Viimsi vald, Haabneeme alevik, Kesk tee
13 elamu ehitamiseks. Projekti koostamise aluseks on kokkulepped omanikuga.
Projekt on koostatud vastavalt Majandus- ja taristuministri 17.07.2015. a määrusele nr 97
„Nõuded ehitusprojektile“. Projekti koostamise aluseks ja ehitamise aluseks on järgmised
dokumendid:
Ehitusseadustik
Viimsi Vallavalitsus projekteerimistingimused Üksikelamule 12.02.2020
Tellijapoolne lähteülesanne
Standardid ja muud soovituslikud dokumendid:
Eesti Vabariigi Ehitusseadustik
EVS 932:2017 “Ehitusprojekt“
EVS 812-6:2012+A1:2013 – Ehitiste tuleohutus: Tuletõrje veevarustus
„Tuleohutuse seadus“
EVS 812-7:2018 ” Ehitiste tuleohutus. Osa 7: Ehitisele esitatavad tuleohutusnõuded“
07.04.2017 siseministri määrus nr 17 „Ehitisele esitatavad tuleohutusnõuded ja
nõuded tuletõrje veevarustusele“
Majandus- ja taristuministri määrus nr 97 „Nõuded ehitusprojektile“
Kesk tee 13; töö nr E-20-02 Mai 2020
Harju maakond, Viimsi vald, Haabneeme alevik, Kesk tee 13
Hoone projekteerimisel on arvestatud järgmisi tingimusi:
1. Arvestuslik välistemperatuur - 22 °C
2. Lumekoormuse normsuurus maapinnal sk = 1.5 kN/m²
3. Tuulekoormuse baasväärtuseks on tuulekiirus vref =21m/s
4. Heliisolatsiooninõuded sisepiiretele üldjuhul R´w=43dB
5. Uksed või ustekompleks R´w=27 (32)dB
6. Heliisolatsiooninõuded välispiiretele R´w=55dB
7. Hoone tulepüsivusklass TP 3
1.2 Ehitise tööiga
Kuna ei ole teisiti kokku lepitud, loetakse planeeritav ehitise tööeaks vähemalt 50 aastat
1.3 Üldandmed
Hoone nimetus ja kasutusotstarve: Ühepereelamu
Katastri number – 89001:009:0840
Kinnistu suurus – 1210m²
Kinnistu sihtotstarve – elamumaa
Kinnistu aadress – Harju maakond, Viimsi vald, Haabneeme alevik, Kesk tee 13
2 SITUATSIOONISKEEM
Kesk tee 13; töö nr E-20-02 Mai 2020
Harju maakond, Viimsi vald, Haabneeme alevik, Kesk tee 13
3 ASENDIPLAANILINE LAHENDUS
3.1 Olemasolev olukord
Kinnistu paikneb aadressil Harju maakond, Viimsi vald, Haabneeme alevik, Kesk tee 13.
Ehitisregistri andmetel asub kinnistul suvila:
Suvilale on väljastatud lammutusluba:
3.2 Plaanilahendus
Planeeritav plaanilahendus on kujutatud asendiplaanil AS-100.
3.3 Teed, platsid, krundisisene liikluskorraldus ja parkimine
Pääs krundile paikneb krundi kirdepoolses osas, Kesk teelt. Sõidukite parkimine on näidatud
asendiplaanil AS-100. Krundile on planeeritud 2 parkimiskohta.
3.4 Piirdeaed ja kõrghaljastus
Antud projekti raames piirdeaeda muuta ei planeerita.
Haljastus: Olemasolev kõrghaljastus säilitatakse.
4 RADOON
Radooni uuringut eraldi ei tellita. Radooni mõju vähendamiseks paigaldatakse vundamendi
tööde käigus radoonitõkke kile, mis peab tagama, et radoon ei pääse hoonesse sisse. Lisaks
on elamus kasutusel sundventilatsioon, mis tagab ruumides pideva õhuvahetuse.
5 ARHITEKTUURNE OSA
5.1 Krundi ja ehitise üldandmed ja tehnilised näitajad
KRUNDI SUURUS – 1210m²
KRUNDI SIHTOTSTARVE - elamumaa
HOONE KAVANDATUD ELUIGA - min. 50 aastat
HOONETE SISETORUSTIKUD - 20 aastat
Kesk tee 13; töö nr E-20-02 Mai 2020
Harju maakond, Viimsi vald, Haabneeme alevik, Kesk tee 13
VÄLISED VEE- JA KANALISATSIOONITORUSTIKUD - 50 aastat
PÕHIKORRUSE PÕRANDA ABSOLUUTKÕRGUS - 0,00 = 7,40
EHITISEALUNE PIND – 165,7m2
KORRUSELISUS – 1
ABSOLUUTNE KÕRGUS – 12,9m
HOONE KÕRGUS – 5,9m
HOONE PIKKUS – 15,4m
HOONE LAIUS – 11,7m
SULETUD BRUTOPIND – 162,5m2
SULETUD NETOPIND – 139,8m2
KÖETAV PIND –139,8m2
MAHT – 745m3
TULEPÜSIVUSKLASS – TP3
5.2 Arhitektuurne üldlahendus
Hoone on ühekordne elamu viilkatusega. Põhikorrusel asuvad elutuba, neli magamistuba,
avatud köök, abiruum, pesuruum, leiliruum, WC, koridor ja esik. Sissepääsude kohal
varikatus ja maja taga terrass katusealusega.
Viimistlusmaterjalina kasutatakse naturaalseid materjale, hoone katuse kattematerjaliks on
katusekivi Monier Elegant, värv tumehall, maja viimistletakse vertikaalse puitlaudisega.
6 KONSTRUKTIIVNE OSA
6.1 Konstruktsioonide üldine iseloomustus
6.1.1 Vundamenditaldmikud- ja seinad
Hoonele rajatakse lintvundament. Vundamendi armeerimine, betooniklass ning täpsed
mõõtmed kajastuvad põhiprojektis.
Vundament eraldatakse maapealsetest konstruktsioonidest hüdroisolatsiooniga nt
membraan Bituthene 4000 või analoog.
6.1.2 Põrandad
Hoone põrandad rajatakse alt soojustatud pinnasele toetuvate raudbetoonist plaatidena
paksusega 100 mm. Põrandasse valatakse küttetorustik. Raudbetoonplaat soojustatakse
altpoolt vahtpolüstüreen plaatidega 150 mm. Põrandate alt eemaldatakse kasvupinnase
kihid, mis asendatakse mineraalse täitepinnasega. Põrandakihtide alla paigaldatakse
minimaalselt 300 mm paksune tihendatud killustik- või kruusaluse kiht (suurim osakeste
läbimõõt on 32 mm).
Kesk tee 13; töö nr E-20-02 Mai 2020
Harju maakond, Viimsi vald, Haabneeme alevik, Kesk tee 13
Põrandaplaatide rajamisel paigaldada kõik vajalikud kommunikatsioonid enne
põrandaplaatide valamist (vesi, elekter, põrandaküte, kanalisatsioon). Täpsustada eriosade
projektidega.
Põrandate projekteerimisel on arvestatud ja ehitamisel tuleb arvestada asjaoluga, et
erinevates ruumides on erinevad viimistlusmaterjalid ning lisanduva tasandusvalu on
muutuva paksusega. Pesu- ja märgades ruumides tehakse tasandusvalu ja põhivalu
üheaegselt, selleks, et tagada kalded trappidesse. Pesuruumides kalded dušinurgas 1:50 ja
muus osas 1:80, Tehnoruumis 1:200. Sõltuvalt töövõtja võimekusest võib tasandusvalu
astmed valada ka üheaegselt aluspõrandaga, kuid arvestada tuleb asjaolu, et kergvaheseinad
rajatakse pärast betoneerimist.
Märgades ruumides tehakse keraamiliste plaatide alla 2x võõp hüdroisolatsioon
ülespööretega seintele. Hüdroisolatsiooni rajamisel kasutada tootja poolt ettenähtud
tugevduslinte ning töövõtteid. Isolatsiooni betoonalused lihvitakse tasaseks, aluse kalle
vastavalt tulevasele põrandapinnale. Isolatsiooni ei tohi paigaldada niiskele alusele.
Hüdroisolatsioon tehakse sertifitseeritud hüdroisolatsioonisüsteemi abil vastavalt tootja
juhistele. Kui eraldi pole teisiti määratud, tõuseb isolatsioon uste kohal 20 mm
põrandapinnast kõrgemale. Künniste ja põrandamaterjali vaheline vuuk, samuti ukselengi
alaosa ja lävepaku või põranda vaheline vuuk tihendatakse silikoonvuugimastiksiga.
Isolatsioon peab moodustama katkematu isolatsioonipinna.
Põrandate viimistlemine on lubatud alles siis, kui on saavutatud selline niiskussisaldus, mis
on nõutud põranda viimistlusmaterjalide tootjate poolt konkreetsele materjalile.
6.1.3 Vahelaed
Vahelagede rajamisel tuleb järgida RT 84-10916-et nõudeid ja juhiseid.
RIL 107-2000 Ehitiste hüdro- ja auruisolatsiooni juhised.
Vahelaeks on katusefermid. Paigaldus vastavalt tootja juhistele. Vahelae soojustuseks
mineraalvill 500mm.
Vahelae siseviimistlusena kasutatakse ühekordset kipsplaati. Kipsplaat pahteldatakse ja
värvitakse. Pahteldatud lagede viimistlus lahendatakse sisekujunduse projektiga. Niisketes
ruumides kasutada niiskuskindlaid materjale.
6.1.4 Seinad
Välisseinte konstruktsioon:
- laudis 21mm
- tuulutuslatt 22mm
- tuuletõkkeplaat 12mm
- postid 173+72mm, vahel vill 246mm
Kesk tee 13; töö nr E-20-02 Mai 2020
Harju maakond, Viimsi vald, Haabneeme alevik, Kesk tee 13
- aurutõkkekile
- kipsplaat (GEK)13mm
Siseseinte konstruktsioon:
- kipsplaat (GEK)13mm
- karkass 66mm, vahel vill 66mm
- kipsplaat (GEK)13mm
Duširuumis ja vannitoas kasutatakse niiskuskindlaid materjale, kogu sein võõbatakse
veetõkkega. Seinad ja põrand kaetakse keraamilisete plaatidega.
6.1.5 Vihmavee süsteem ja veeplekid
Katusele langev vihmavesi juhitakse hoonest eemale ja immutatakse omal kinnistul.
6.1.6 Aknad
Aknad – Puit-alumiinium aknad, kolmekordne klaaspakett.
Akende projekteeritud kasutusiga 50 aastat.
Akende kvaliteedi, koostisosade sobivuse ja eluea tagab akende tootja vastavate
sertifikaatidega.
Kõik sulused ja kinnitid peavad olema korrosioonikindlad. Suluste kinnitused väljanägemiselt
ja tehniliselt võimalikult samast materjalist kui vastav sulus. Kõik aknad peavad olema täiesti
kasutamiskõlblikud ja täielikult sulustega varustatud.
Akende paigaldusvaruks on arvestatud külgedel min 10 mm.
Akende erinevad avanemisvõimalused täpsustada enne akende tellimist.
6.1.7 Uksed
Uksed – Puituksed.
Uste kasutusiga 50a.
Puituste kvaliteediklass E.
Kõik sulused ja kinnitid peavad olema korrosioonikindlad ja kasutatavad kruvid soonpeaga.
Suluste kinnitid välimuselt ja tehniliselt võimalikult samast materjalist kui vastav sulus. Kõik
uksed peavad olema täiesti kasutuskõlblikud ja täielikult sulustega varustatud isegi siis, või
joonistel jäi mõni vajalik sulus nimetamata. Valmistaja vastutab suluste funktsionaalsuse ja
kokkusobivuse eest.
Siseuksed tehakse tahveldustega täispuitustena või sileustena. Uste lengi laius valida seina
paksusega sama. Siseuksed viimistletakse peitsiga ja kaetakse lakiga või värvitakse. Niiskete
Kesk tee 13; töö nr E-20-02 Mai 2020
Harju maakond, Viimsi vald, Haabneeme alevik, Kesk tee 13
ja märgade ruumide uksed teha niiskuskindlad ja pritsmekindla viimistlusega. Nõutud uste
tulepüsivus, tolerantsid, helipidavuse ja kulumiskindluse garanteerib tootja. Uste avanemise
suunale tuleb paigaldada stopperid selliselt, et uksed ei lõhuks seinte viimistlust.
Välisuksed tehakse puidust värvitud ja klaaspaketiga klaasitud puitustena. Uste raamide ja
lengide valmistamisel tuleb kasutada kõrgekvaliteetset liimpuitu ja tagada uste stabiilsus
pikema aja vältel. Välisuste konstruktsiooni ja koostetehnoloogia määrab uste tootja.
Välisuste viimistlus vastavalt joonistele. Uste koostekvaliteedi ja garantii tagab uste tootja.
Uste värvimisel kasutada UV-kiirgusele vastupidavaid värve.
7 Hoone sisearhitektuur
Hoone sisekujundust antud projekt ei käsitle.
8 KÜTE JA VENTILATSIOON
8.1 Küttesüsteemid
Hoone kütmine on planeeritud maasoojuspumbaga läbi põrandakütte. Soojuspump hakkab
asuma abiruumis. Lähtuvalt standardist ei ole soojuspumba puhul tehnoruumis vajaliku
paiskpinna arvutus nõutud. Põrandakütte temperatuuri kontroll toimub tehnilisest ruumist.
Kütte tehnilisest ruumist on projekteeritud edasine magistraaltorude jagunemine
põrandakütte kollektoritesse. Põrandakütte kollektoritest toimub jagunemine
põrandakütteringidesse. Põrandakütte ruumidekohane reguleerimine toimub spetsiaalse
lokaalse automaatikasüsteemi kaudu. Põrandküte on projekteeritud hapnikutõkkega
plasttorust ų20x2. Põrandküte on madalatemperatuuriline küte, kus soojuskandjana
kasutatakse vastava paigaldusskeemi kohaselt põrandakonstruktsiooni paigaldatud
plasttorudes ringlevat vett. Projekteeritud põrandkütte põrandapindade arvutuslikud
maksimaalsed temperatuurid ei ületa standardis " EVS 844:2016 Hoone kütte
projekteerimine" toodud väärtusi. Soojuskandja parameetrid põrandkütte süsteemis on
30/35°C. Põrandkütte jaotuskappi paigaldatakse jaotuskollektorid. Kollektor varustatakse
elektriajamiga täiturmootoritega. Ruumi temperatuuri reguleerimiseks paigaldatakse ruumi
siseseinale ruumitermostaat. Märgadesse ruumidesse paigaldatakse põrandatemperatuuri
andurid.
Täiendava kütteallikana asub elutoas kamin ühelõõrilise moodulkorstnaga. Kütteseadmed
paigaldada vastavalt tootja juhendile. Kütteseadmed ja nende paigaldus peab vastama
standardile EVS 812-3:2018 Ehitise tuleohutus Osa 3: Küttesüsteemid.
Kesk tee 13; töö nr E-20-02 Mai 2020
Harju maakond, Viimsi vald, Haabneeme alevik, Kesk tee 13
8.2 Ventilatsioon
Ventilatsioon lahendatakse soojusvahetiga sundventilatsiooniga. Köögi väljatõmbekanal, mis
ei ole rajatud šahti, peab olema tulepüsivusega vähemalt EI 15 ja tuletundlikkusega vähemalt
A2-s1,d0. Õhupuhasti ja väljatõmbekanali ühendamiseks võib kasutada painduvaid kanaleid.
9 VEEVARUSTUS JA KANALISATSIOON
Krundile on toimiv vee ja kanalisatsioonileping AS Viimsi Veega.
9.1.1 Veevarustuse allikas
AS Viimsi Vesi ühisveetrass.
9.1.2 Soojavee süsteem
Hoone soe vesi tuleb maaküttesoojaveeboilerist. Sooja veega varustatakse kõiki san.
seadmeid, v.a. klosetipotid, pesumasinad.
9.1.3 Reovee kanalisatsioon
AS Viimsi Vesi ühisreovee kanalisatsioon.
10 ELEKTER
Elektrisüsteemid ja võrgud projekteeritakse eraldi projektis.
Hoones varustatakse elektriga kõik ruumid. Hoone elektrivarustus tagatakse piirkonna
alajaamast, kust on rajatud kruntideni maakaabelliin. Krundi piirile on rajatud liitumiskilp.
Liitumiskilbist veetakse elektriühendus madalpinge maakaabeliga ja ühendatakse hoone
jaotuskilbiga. Maakaabel paigaldada torusse või kõrisse. Kaablikaevikusse paigaldada
hoiatuslint.
Hoonesisesed kaablid paigaldatakse peamiselt süvistatult seintel ning lagedel. Kaablid
paigaldatakse üldiselt paralleelselt ehitise arhitektuursete joontega. Kogu paigaldis
ehitatakse kaitsejuhiga (kolla-rohelise isolatsiooniga juht) kaablitega. Harukarpides
kasutatakse juhtide ühendamiseks vastavaid ühenduskübaraid või klemme.
Lülitite paigalduskõrgus põrandast on kuni 1.0 m. Pistikupesade paigalduskõrguseks on
üldiselt 0,3 m, v. a. eriseadmetele (köögis on paigalduskõrgus 1,1 m või vastavalt
ühendatava seadme vajadustele). Elamu kõik pistikupesade liinid ühendatakse läbi
rikkevoolu-kaitseseadme.
Kõik juhtmed, kaablid jms peavad olema PVC isolatsiooni ja kestaga, arvestatud juhi
temperatuurile vähemalt 65°C. Valgustite, pistikupesade või teiste jõuseadmete jaotusliinide
ehitamiseks kasutatud kaablitel peab olema eraldi maandusjuht (kui seadme isolatsiooni
Kesk tee 13; töö nr E-20-02 Mai 2020
Harju maakond, Viimsi vald, Haabneeme alevik, Kesk tee 13
klass ei luba kasutada teist juhistikku). PVC-isolatsiooniga kaablid ja juhtmed peavad olema
vähemalt: 1,5-4 mm2 – U0/U=300/500 V; 6-25 mm2 – U0/U=450/750 V isolatsiooniklassiga.
Ei tohi kasutada kaableid ja juhtmeid soonte ristlõikega väiksem kui 1,5 mm2.
Kõik elektritööd peavad olema kooskõlas Imatra Elektri AS poolt väljastatud võrgulepinguga.
11 NÕRKVOOL
Nõrkvool projekteeritakse eraldi projektis.
12 KESKKONNAKAITSE
Olmejäätmed ja prügi kogutakse omal krundil asuvasse konteinerisse, asukoht näidatud
asendiplaanil, mida tühjendatakse vastavalt omanike poolt sõlmitud lepingutele
jäätmefirmaga. Konteiner paigutatakse kõvakattega pinnale. Kokkuleppel
pakendiettevõtjaga tuleb kinnistul koguda eraldi ka pakendijäätmeid (klaas-, metall-, plast- ja
komposiitpakendeid ning teisi pakendijäätmeid). Tehiskeskkonna projekteerimisel on
lähtutud kõikidest normidest ja seadusaktidest.
12.1 Lammutus ja pinnasetööd
Ehitus- ja lammutusjäätmete käitlemine toimub vastavalt Viimsi valla
jäätmehoolduseeskirjale, vastu võetud 11.03.2014 nr 8.
Ehitamise käigus tekkinud ehitusjäätmete nõuetekohase käitlemise tõendamiseks tuleb
koos ehitise kasutusloa taotlusega esitada jäätmeõiend, milles on toodud käideldud
jäätmete kogus ja jäätmekäitluskoht.
Ehitamise käigus tekkivate ehitusjäätmete ära veoks sõlmib ehitaja lepingu
jäätmekäitlusettevõttega, kes vastavate konteineritega jäätmed minema veab ja sorteerib.
Ehitus- ja olmejäätmete käitlemist käsitletakse vastavalt kohaliku omavalitsuse
jäätmehoolduseeskirjadest: jäätmete käitlemisel tuleb lähtuda jäätmeseadusest ja
ehitusjäätmete käitlemise juhendist.
Ehitusjäätmed kogutakse ehitustööde käigus jooksvalt ja äravedu või taaskasutusse võtmine
korraldatakse vastavalt omavalitsuse eeskirjadele ja kehtivale seadusandlusele. Ehitaja
sõlmib ehitustööde ajaks ehitusjäätmete äraveoks lepingu vastavat litsentsi omava
ettevõttega.
Ehitamise käigus prognoositav jäätmekogus ei ületa 10 m3, võimalusel kogutakse
ehitusjäätmed liigiti eraldi vastavalt tähistatud kogumismahutitesse. Juhul, kui liigiti
kogumiseks puudub jäätmete tekkekohas võimalus või see pole majanduslikult otstarbekas,
Kesk tee 13; töö nr E-20-02 Mai 2020
Harju maakond, Viimsi vald, Haabneeme alevik, Kesk tee 13
antakse jäätmed sorteerimiseks ja käitlemiseks üle vastavat jäätmeluba omavale
teenusepakkujale.
Võimalusel kogutakse liigiti eraldi konteineritesse:
1) puidujäätmed;
2) metallijäätmed;
3) kiletamata paberi ja papijäätmed;
4) mineraalsed jäätmed (kivid, ehituskivid, tellised, krohvisegud jne);
5) raudbetoon ja betoondetailid;
6) plastijäätmed, sealhulgas kilejäätmed;
7) ohtlikud ehitusjäätmed;
8) muud jäätmed.
13 TULEOHUTUS
13.1 Üldist
Vastavalt siseministri määrusele nr 17 07.04.2017 „Ehitisele esitatavad tuleohutusnõuded ja
nõuded tuletõrje veevarustusele“ kuulub elamu tuleohutusklassi TP3 ja kasutusviisi I.
Hoone on 1korruseline.
- TP-3 klassi kuuluva ühekorruselise ehitise välisseina konstruktsioon võib vastata klassile
D-s2,d2,
- TP-3 klassi ehituses paiknevate ruumide siseseinte ja põrandate ja lagede pinnakihile
esitatavad nõuded tuletundlikkusele:
Projekti tuleohutuseosa koostamiseks aluseks olevad õigusaktid:
Tuleohutuse seadus
Majandus- ja taristuministri määrus nr 97 „Nõuded ehitusprojektile“
Siseministri määrus nr 17 07.04.2017 „Ehitisele esitatavad tuleohutusnõuded ja
nõuded tuletõrje veevarustusele“
EVS 812-3:2018– Ehitiste tuleohutus: Küttesüsteemid
EVS 812-6:2012+A1:2013 – Ehitiste tuleohutus: Tuletõrje veevarustus
EVS 812-2:2014/AC:2018 - Ehitiste tuleohutus. Osa 2: Ventilatsioonisüsteemid
EVS 812-7:2018 ” Ehitiste tuleohutus. Osa 7: Ehitisele esitatavad tuleohutusnõuded”
Tuletundlikus
Kesk tee 13; töö nr E-20-02 Mai 2020
Harju maakond, Viimsi vald, Haabneeme alevik, Kesk tee 13
Siseseinte: Seinad ja laed üdiselt D-s2,d2
Põrandad üldiselt– nõudeid ei esitata
Välisseina välispinnale ja õhutuspilu välispinnale D-s2,d2
Õhutuspilu sisepinnale-nõudeid ei esitata
Katusekatetele BROOF(t2)
Terrassipõranda konstruktsioonile D-s2
13.2 Tuletõkkesektsioonid
Hoone kuulub ühte tuletõkke sektsiooni.
13.3 Põlemiskoorumus
Vastavalt siseministri määrusele nr 17 07.04.2017 „Ehitisele esitatavad tuleohutusnõuded ja
nõuded tuletõrje veevarustusele“ kuulub olemasolev hoone tuleohutusklassi TP3 ja
kasutusviis I (eramu), mille alusel on hoones tervikuna põlemiskoormus alla 600 MJ/m².
13.4 Evakuatsioon
I kasutusviisiga hoones ei või väljumistee pikkus üldjuhul olla suurem kui 30 m. Antud
hoones ei ületata nõutud evakuatsioonitee pikkust.
Hoones viibivate inimeste arvu ei piirata.
Hädaväljapääs on hoonest lahendatud avatavate akende kaudu.
13.5 Suitsueemaldus
Suitsueemaldus hoonest on ette nähtud läbi avatavate akende. Igas ruumis on vähemalt üks
avatav aken. Lisaks akendele toimub suitsueemaldus ka läbi välisuste.
Aknad peavad olema lihtsalt avatavad.
13.6 Kustutusvesi
Hoonesse ei ole planeeritud sisemist tulekustutust. Ehitise väliskustutusvee normvooluhulk
on 10 l/s 3 tunni jooksul. Alus: EVS 812-6:2012+A1:2013
Lähim tuletõrjevee hüdrant asub projekteeritavast hoonest 6 m kaugusel, Kesk tee ja
Rohuneeme tee ristmikul.
13.7 Pääsud katusele
Hoone katusele pääseb teiseldatava redeliga. Korstna teenindamiseks paigaldatakse
kohtkindel käigutee ja kohtkindel redel katusele.
Kesk tee 13; töö nr E-20-02 Mai 2020
Harju maakond, Viimsi vald, Haabneeme alevik, Kesk tee 13
13.8 Pääsud pööningule
Pääsuks pööningule paigaldatakse koridori pööninguluuk 600x800 kolmeosalise redeliga.
13.9 Tulekahju signalisatsioon
Hoone ruumides on vähemalt üks autonoomne tulekahju signalisatsiooniandur ja üks
vingugaasiandur.
13.10 Esmased kustutusvahendid
Esmaste tulekustutusvahenditena paigaldatakse esikusse vähemalt üks 6 kg pulberkustuti.
Kõik projekti järgi paigaldatavad tulekustutid peavad vastama Eesti standardile EVS-EN 3
“Kantavad tulekustutid” nõuetele ja omama vastavustunnistust. Kasutatakse ABC klassi
pulberkustuteid tulekustutusaine massiga 6 kg. Sobivad A-, B- ja C-klassi tulekahjude
kustutamiseks.
13.11 Küttesüsteemid
Hoone kütmine on planeeritud maasoojuspumbaga.
Hoonele on planeeritud moodulkorsten 1 lõõriga kamina kütmiseks. Moodulkorsten ja
kamin paigaldatakse vastavalt tootja paigaldusjuhendile järgides EVS 812-3:2018.
Ehitatav kamin ja moodulkorsten asuvad elutoas. Kamina võimsuseks on arvestatud 2,4 – 7,5
kW. Kaminaks on planeeritud valmiskamin ASCIM II (Haas & Sohn), paigaldus vastavalt tootja
juhistele. Kamin on köetav halupuudega. Ühe küttekorra halupuid hoitakse kamina kõrval.
Kamina ette paigaldatakse mittepõlev põrandakate (nt klaas, plekk vms) .Uksega kolde puhul
(EVS 812-3:2018): mittepõlev põrandakate peab ukseavast ulatuma 100 mm kummalegi
poole, arvestades ukseava servast; mittepõlev põrandakate peab ukseavast ulatuma 400 mm
eemale, arvestades kolde esiservast.
Kamin ühendatakse korstna suitsulõõriga kütteseadme üla- ja/või allosas ühenduslõõride
abil. Kütteseade ja suitsulõõr müüritakse kokku allosas asuvas ühenduses kahe müüritisekihi
võrra kõrgemal. Kuna kütteseade ja suitsulõõr võivad omavahel erinevalt liikuda, tagatakse
ülaühenduse tihedus metalltoruga, mille külge võib kinnitada ka kütteseadme suitsusiibri.
Ühendustoru ja müüritise vahelise soojuspaisumise võimaldamiseks jäetakse nende vahele 5
mm kuni 10 mm laiune pilu, mis tihendatakse tulekindla isolatsioonimaterjaliga,
kasutustemperatuuriga min 1000° C. (EVS 812-3:2018).
Kamina ees peab olema vähemalt 1 m ja tahmaluukide ees 0,6 m vaba ruumi. Tahmaluugi
alumine serv peab põlevmaterjalist põrandast jääma vähemalt 50 mm kõrgemale. (EVS 812-
3:2018) Kütteseadme paigaldus ehitisse toimub vastavalt tootja etteantud juhistele.
Kesk tee 13; töö nr E-20-02 Mai 2020
Harju maakond, Viimsi vald, Haabneeme alevik, Kesk tee 13
Müüritud kütteseadme ohutu ehituse ja paigalduse tagab kutseline pottsepp. (EVS 812-
3:2018)
Korsten on ühelõõriline moodulkorsten temperatuuriklassiga T600.
(EVS 812-3:2018).
13.12 Läbiviigud
Kesk tee 13; töö nr E-20-02 Mai 2020
Harju maakond, Viimsi vald, Haabneeme alevik, Kesk tee 13
Kesk tee 13; töö nr E-20-02 Mai 2020
Harju maakond, Viimsi vald, Haabneeme alevik, Kesk tee 13
14 GRAAFILINE OSA
JOONISE NIMETUS TÄHIS
- Asendiplaan AS-100
- Vundamendiplaan A-100
- Põhikorruse plaan ja Lõige A-101
- Katuse plaan A-102
- Vaated A-103
- Avatäited A-104
LISA 1
- Riigilõivu maksmise maksekorraldus
- Pildid naaberkinnistu elamutest
Kesk tee 13; töö nr E-20-02 Mai 2020
Harju maakond, Viimsi vald, Haabneeme alevik, Kesk tee 13
5 ,3
Kanalisatsiooni
liitumispunkt
2
K11111
VK2 6 6,72 Veevarustuse liitumispunkt
4
K21
3
5
1 2
PK
E
10,
±
K21
7
57
8
,37
15
ELAMU E
TEHNILISED NÄITAJAD
KRUNDI PIND 1210m²
ELAMU EHITISEALUNE PIND 184m²
KORRUSELISUS 1
ELAMU KÕRGUS 5,9 m
ELAMU KOORDINAADID ELAMU PIKKUS 15,4 m
ELAMU LAIUS 11,7 m
X Y SULETUD BRUTOPIND 162,5 m²
SULETUD NETOPIND 139,8 m²
KÖETAV PIND 139,8 m²
MAHT 424 m3
TP3
TINGMÄRGID
krundipiir
projekteeritav elektriõhuliin
V1.1 V1.1 projekteeritav veetorustik
K1.1 K1.1 projekteeritav kanalisatsioonitorustik
K21 K21 projekteeritav drenaažitorustik
projekteeritav sidekaabel
pääs krundile
olemasolev puurkaev E
± projekteeritav elamu
maaküttetorustiku ala 420m² PK prügikonteiner
Tehnovõrgu valdaja Kooskõlastuse Kooskõlastuse Kooskõlastaja Märkused
kuupäev number
Imatra Elekter AS 17.12.2019 7199 Ants Heinsaar
AS KH Energia- 23.12.2019 Tõnu Roosna
Konsult
Telia Eesti AS 30.12.2019 33244500 Tiina Ojamaa
AS Viimsi Vesi 06.12.2019 6661 Jüri Mäevere
Saatja: <
[email protected]>
Saadetud: 26.05.2020 11:23
Adressaat: <
[email protected]>
Teema: Teade Ehitisregistrist - Ehitusloa taotlus nr 2011271/05055, menetlus nr 215468
Väline kooskõlastamine tähtaeg 05.06.2020
Maanteeamet palun teostage Ehitusloa taotlus Väline kooskõlastamine. Ülesande täitmiseks
sisenege Ehitisregistrisse ja avage menetlus nr 215468
Menetluse nr 215468
Menetlusse võtmise kp 23.05.2020
Ülesande saaja Maanteeamet
Ülesande määramise kp 26.05.2020
Ülesande tähtaeg 05.06.2020
Pädev asutus Viimsi Vallavalitsus
Menetleja PIRET KIRJANEN
Menetleja e-kirja aadress
[email protected]
Menetleja tel
Ehitise aadress Harju maakond, Viimsi vald, Haabneeme alevik, Kesk tee 13
Dokumendi nr 2011271/05055
Dokumendi kp 14.05.2020
Taotleja/teataja EDUARD ONUFREITŠUK
Ehitisregistri kood 221337190, 221337188, 221337187, 121330027
Ehitise nimetus Drenaažitorustik, Kanalisatsioonitorustik, Veetorustik, Elamu
NB! Tegemist on automaatteavitusega. Sisuliste küsimuste korral palun pöördu kohaliku
omavalitsuse menetleja (enamasti ehitusspetsialist) poole. Ehitisregistri kasutamise tehnilistes
küsimustes aitab Sind klienditugi aadressil
[email protected].
Töö nr.20047 Elamu – Kesk tee 13, Haabneeme alevik, Viimsi vald, Harju maakond
Välisveevarustus ja -kanalisatsioon. Tööprojekt. 6.05.2020
SISUKORD
EHITUSPROJEKTI KIRJELDUS ......................................................................................................................................... 4
1 ÜLDANDMED ....................................................................................................................................................... 4
1.1 PROJEKTEERIMISTÖÖ PIIRITLUS ......................................................................................................................... 4
1.2 ALUSDOKUMENDID ............................................................................................................................................. 4
1.2.1 LÄHTEANDMED ................................................................................................................................................... 4
1.2.2 EHITUSUURINGUD ............................................................................................................................................... 5
1.2.3 NORMDOKUMENDID............................................................................................................................................ 5
2 OLEMASOLEV...................................................................................................................................................... 5
3 VEEVARUSTUS .................................................................................................................................................... 5
3.1 VEEVARUSTUSE ÜLDPÕHIMÕTTED ..................................................................................................................... 5
3.2 PROJEKTEERITUD VEEVARUSTUS ....................................................................................................................... 5
3.3 VEEVARUSTUSE ARVUTUSLIKUD VOOLUHULGAD ............................................................................................... 6
3.4 VEEALLIKAS ........................................................................................................................................................ 6
3.5 VEEMÕÕDUSÕLM ................................................................................................................................................ 6
3.6 TULETÕRJEVEEVARUSTUS.................................................................................................................................. 6
3.7 TORUSTIKE MATERJAL ....................................................................................................................................... 6
3.8 ARMATUUR ......................................................................................................................................................... 7
4 KANALISATSIOON ............................................................................................................................................... 7
4.1 KANALISATSIOONI ÜLDPÕHIMÕTTED .................................................................................................................. 7
4.2 PROJEKTEERITUD KANALISATSIOON .................................................................................................................. 7
4.3 KANALISATSIOONI ARVUTUSLIK VOOLUHULK ..................................................................................................... 8
4.4 KANALISATSIOONI EELVOOL ............................................................................................................................... 8
4.5 TORUSTIKUD JA MATERJALID............................................................................................................................. 8
4.6 PUMPLA JA KOHTPUHASTID ............................................................................................................................... 8
4.7 KAEVUD .............................................................................................................................................................. 8
5 SADEMEVEE KANALISATSIOON ........................................................................................................................... 8
5.1 OLEMASOLEV OLUKORD ..................................................................................................................................... 8
5.2 PROJEKTEERITUD SADEMEVEEKANALISATSIOON ............................................................................................... 9
5.3 ARVUTUSÄRAVOOL ............................................................................................................................................. 9
5.4 TORUSTIKE MATERJAL ....................................................................................................................................... 9
5.5 EELVOOL ............................................................................................................................................................. 9
5.6 KAEVUD .............................................................................................................................................................. 9
6 PAIGALDUSNÕUDED ........................................................................................................................................... 9
6.1 TORUSTIKE JA KAEVUDE PAIGALDUS ............................................................................................................... 10
6.2 KAEVIK .............................................................................................................................................................. 10
6.3 TASANDUSKIHT ................................................................................................................................................ 11
6.4 TORUSTIKE PAIGALDUS JA KAEVIKU TÄIDE ...................................................................................................... 12
6.5 KÜLMUMISKAITSE, SOOJUSISOLATSIOON ........................................................................................................ 13
6.6 TORUSTIKE TOESTUS ........................................................................................................................................ 13
7 LIKVIDEERITAVAD RAJATISED ........................................................................................................................... 13
8 KESKKONNAKAITSE .......................................................................................................................................... 13
9 KVALITEEDI- JA KONTROLLINÕUDED EHITAJALE .............................................................................................. 14
9.1 ÜLDNÕUDED ..................................................................................................................................................... 14
9.2 HÜDRAULILISED KATSETUSED .......................................................................................................................... 14
10 PÕHIMATERJALIDE LOETELU ............................................................................................................................ 16
JOONISTE NIMISTU ....................................................................................................................................................... 17
Vastutav spetsialist: Evelin Anto 2 / 17 20047_TP_VK-3-01_seletuskiri.docx
Töö nr.20047 Elamu – Kesk tee 13, Haabneeme alevik, Viimsi vald, Harju maakond
Välisveevarustus ja -kanalisatsioon. Tööprojekt. 6.05.2020
Lisad
Lisa 1. AS Viimsi Vesi tehnilised tingimused
Vastutav spetsialist: Evelin Anto 3 / 17 20047_TP_VK-3-01_seletuskiri.docx
Töö nr.20047 Elamu – Kesk tee 13, Haabneeme alevik, Viimsi vald, Harju maakond
Välisveevarustus ja -kanalisatsioon. Tööprojekt. 6.05.2020
EHITUSPROJEKTI KIRJELDUS
1 ÜLDANDMED
1.1 PROJEKTEERIMISTÖÖ PIIRITLUS
Käesoleva projektiga lahendatakse uue hoone välisveevarustus ja -kanalisatsioon tööprojekti mahus. Elamu
asub aadressil Kesk tee 13, Haabneeme alevik, Viimsi vald, Harjumaa.
1.2 ALUSDOKUMENDID
1.2.1 LÄHTEANDMED
VK-süsteemide kavandamisel on arvestatud järgmisi lähteandmeid:
- Hoone asukoht: Kesk tee 13, Haabneeme alevik, Viimsi vald, Harju maakond
- Arhitektuursed joonised(Smart Arch OÜ)
- AS Viimsi Vesi tehnilised tingimused nr. 14.04.20/5914
- Projekteerimise lähteülesanne.
Vastutav spetsialist: Evelin Anto 4 / 17 20047_TP_VK-3-01_seletuskiri.docx
Töö nr.20047 Elamu – Kesk tee 13, Haabneeme alevik, Viimsi vald, Harju maakond
Välisveevarustus ja -kanalisatsioon. Tööprojekt. 6.05.2020
1.2.2 EHITUSUURINGUD
Ehitusgeodeetilised uuringud: Radiaan OÜ, Kesk tee 13, Haabneeme alevik, Viimsi vald geodeetilise uurimistöö
aruanne, töö nr 461G19
1.2.3 NORMDOKUMENDID
VK-süsteemide kavandamisel aluseks võetud peamised teineteist täiendavad dokumendid:
EVS 932:2017 Ehitusprojekt
EVS 835-2014 Hoone veevärk
EVS 846-2013 Hoone kanalisatsioon
EVS 848:2013 Väliskanalisatsioonivõrk
EVS 921:2014 Veevarustuse välisvõrk
EVS 843:2016 Linnatänavad
EVS 812-6:2012+A1+A2 Ehitiste tuleohutus (Osa 6: Tuletõrje veevarustus)
EVS-EN 1610:2015 Äravoolu- ja kanalisatsioonitorustike ehitamine ja katsetamine
Kehtivad seadused ja määrused
2 OLEMASOLEV
Uus ehitis. Kinnistul paikneva olemasolevad vee- ja kanalisatsioonitorustikud, sidekaablid ning magalpinge
õhuliinid.
3 VEEVARUSTUS
3.1 VEEVARUSTUSE ÜLDPÕHIMÕTTED
Ühisveevärk peab olema ehitatud nii, et kõik tarbijad saaksid vajalikus koguses ja vajaliku rõhu juures kvaliteetse
joogivee. Torud peavad olema vastupidavad vajalikule rõhule ühisveevärgis, korrosioonikindlad, kerge
paigaldatavusega, keemiliselt püsivad veekeskkonnas.
Hoone sisevõrku suunatav majandus-joogivesi peab kvaliteedilt vastama joogiveele esitatavatele nõuetele. Need
on määratud 31.07.2001.a. sotsiaalministri määrusega nr.82 „Joogivee kvaliteedi- ja kontrollinõuded ning
analüüsimeetodid“.
3.2 PROJEKTEERITUD VEEVARUSTUS
Kinnistul on olemasolev veevarustuse liitumispunkt Rohuneeme tee De63 ühisveetorustikult. Kinnistu
ühendustorustik on projekteeritud läbimõõduga De32 mm PE PN16 torustikust. Liitumispunktiks on olemasolev
maakraan DN25 kinnistu piirist tänava poole.
Veetorustik paigaldada 1,8m sügavusele maapinnast. Torustikud, mille lagi jääb maapinnale lähemale kui 1,8 m
tuleb soojustada.
Vastutav spetsialist: Evelin Anto 5 / 17 20047_TP_VK-3-01_seletuskiri.docx
Töö nr.20047 Elamu – Kesk tee 13, Haabneeme alevik, Viimsi vald, Harju maakond
Välisveevarustus ja -kanalisatsioon. Tööprojekt. 6.05.2020
3.3 VEEVARUSTUSE ARVUTUSLIKUD VOOLUHULGAD
Eramu on mõeldud 3 inimesele. Ööpäevane keskmine veetarbimine ühe inimese kohta on võetud 143 l/d.
Qd : 0,4 m3/d - ööpäevane vooluhulk
3
Qhm: 0,2 m /h - maksimaalne tunnine
Qa: 0,52 l/s - arvutusvooluhulk
3.4 VEEALLIKAS
Hoone majandus-joogiveega varustamine lahendatakse Rohuneeme tee De63 ühisveetorustikult. Kinnistule on
ette nähtud üks veesisend De32 PE100, PN16.
Vastavalt AS Viimsi Vesi tehnilised tingimused nr. 14.04.20/5914 on garanteeritud vabarõhk liitumispunktis on
200 kPa.
3.5 VEEMÕÕDUSÕLM
Veemõõdusõlm on projekteeritud hoone 1.korrusel asuvasse abiruumi.
Veearvesti paigaldada seinale veearvesti kanduriga. Veearvesti kandur maandatakse. Veemõõtja valitakse
lähtudes maksimaalsest veetarbimisest (DN15).
Veearvestid tuleb paigaldada horisontaalasendisse.
Enne ja pärast veearvestit on nõutav sulgur, veearvesti ette võib panna vaid täisavaga sulguri. Veearvestitaguse
sulguri taga peab olema tagasilöögiklapp (kui klapp ei ole arvesti sisse ehitatud). Arvestile peab eelnema
vähemalt viie arvesti tingläbimõõdu pikkune ning järgnema kolme läbimõõdu pikkune sirge horisontaalne
torulõik, mille sisse võib arvata ka täisavaga sulgurid. Veemõõdusõlmes peab arvestitaguse sulguri taga olema
kraan, mille kaudu saab vajadusel süsteemi tühjaks lasta, võtta veeproove või arvestit kontrollida. Enne
veearvestit paigaldada mudaeraldaja.
3.6 TULETÕRJEVEEVARUSTUS
Vajalik väline tuletõrjevee vooluhulk välistulekustutuseks on 10 l/s, arvestuslik tulekahju kestvus on 3h. Lähim
tuletõrjehüdrant paikneb Rohuneeme tee ja Kesk tee ristmikul.
3.7 TORUSTIKE MATERJAL
Projekteeritud veetorustik tuleb rajada PE 100 survetorudest, läbimõõduga De32x3,0 SDR11, PN16. PE
survetorud peavad vastama standardi EN12201 nõuetele. Torustiku ühendusteks piki trassi ja sõlmedes
kasutatakse põkk- või muhvkeevitust. Keevisliitmike surveklass peab olema vähemalt võrdne torude
surveklassiga.
Käänakud paigaldatakse elektrikeevispoognatega või PEH poognatega kas põkk-või elekterkeevismuhvide abil.
Väiksemate toruläbimõõtude puhul võib väiksemad käänakud (pöördenurk alla 30°) tekitada torustikku sujuvalt
painutades, kusjuures minimaalne pöörderaadius R=50 x De. Kõik torustike rajamiseks kasutatavad materjalid
peavad olema uued. Defektsed materjalid ja tooted tuleb ehitusplatsilt eemaldada.
Vastutav spetsialist: Evelin Anto 6 / 17 20047_TP_VK-3-01_seletuskiri.docx
Töö nr.20047 Elamu – Kesk tee 13, Haabneeme alevik, Viimsi vald, Harju maakond
Välisveevarustus ja -kanalisatsioon. Tööprojekt. 6.05.2020
3.8 ARMATUUR
Käesolevas projektis ei ole ette nähtud.
4 KANALISATSIOON
4.1 KANALISATSIOONI ÜLDPÕHIMÕTTED
Kanalisatsioonivõrk peab olema ehitatud selliselt, et ei tekitataks ohtu tervisele, ebameeldivat lõhna,
kanalisatsioonivee üleujutusi, müra ega muud kahju keskkonnale. Rajatud kanalisatsioonivõrk peab olema
kestev ja töökindel.
Kanalisatsioonivõrku on keelatud juhtida vett, mis sisaldab ohtlikke aineid vastavalt õigusaktides kehtestatud
nõuetele ohtlike ainete kohta ühiskanalisatsiooni juhitavas vees.
Üldised tehnilised nõuded:
rajatiste konstruktsioon ja materjal peavad taluma väliskoormuse mõju, materjal peab olema
korrosioonikindel;
torustik ei tohi ummistuda;
kanalisatsiooniuputuste risk peab olema viidud miinimumini;
kanalisatsioonivõrgu rajatised ei tohi ohustada keskkonda, läheduses paiknevaid hooneid ega rajatisi;
torustikud ja kollektorid peavad olema veetihedad;
rajatiste kavandatud eluiga ja püsivus peavad olema tagatud;
kanalisatsioonivõrk peab olema hooldatav
4.2 PROJEKTEERITUD KANALISATSIOON
Piirkonna kanalisatsioonisüsteem on lahkvoolne.
Kinnistul on olemasolev kanalisatsiooni liitumispunkt Rohuneeme teel. Torustikud on projekteeritud läbimõõduga
De160 mm PVC. Liitumispunktiks on olemasolev kaev DN200/160 kinnistu piirist tänava pool.
Torustik paigaldatakse vastavalt asendiplaanile.
Isevoolse kanalisatsioonitorustiku paigaldussügavus on vähem kui 1,20 m maapinnast toru peale, seega tuleb
kanalisatsioonitorustik kogu ulatuses soojustada.
Kõik ühendused muudest materjalidest torustikega tuleb teha sobivaid liitmikke ja üleminekuid kasutades.
Põlvede ja poognate kasutamine väljapool kaevusid torustiku suuna muutmiseks ei ole lubatud. Uute
kanalisatsioonikaevude sügavused ja asukohad peavad vastama joonistele, kuid Töövõtja peab arvestama
sellega, et tegelikud tingimused võivad nõuda sügavuse muutusi ja kaevude asukoha muutusi ilma täiendavate
kulude katmiseta.
Isevoolsete kanalisatsioonitorustike kalde määramisel on arvestatud EVS 848:2013 esitatud nõuetega:
kanalisatsioonitorustikus peab olema tagatud isepuhastus, s.o. voolukiirus peab olema vähemalt kord ööpäevas
≥0,7 m/s.
Vastutav spetsialist: Evelin Anto 7 / 17 20047_TP_VK-3-01_seletuskiri.docx
Töö nr.20047 Elamu – Kesk tee 13, Haabneeme alevik, Viimsi vald, Harju maakond
Välisveevarustus ja -kanalisatsioon. Tööprojekt. 6.05.2020
Kanalisatsioonitorustike rajamissügavus on üldjuhul piisav ja torustik on kaitstud mehaaniliste ja dünaamiliste
vigastuste eest.
4.3 KANALISATSIOONI ARVUTUSLIK VOOLUHULK
Hoone olmereovee kanalisatsiooni vooluhulgad:
Qa: 1,8 l/s - arvutuslik vooluhulk
Qd : 0,4 m3/d - ööpäevane vooluhulk
4.4 KANALISATSIOONI EELVOOL
Piirkonnas on lahkvoolne kanalisatsioonisüsteem. Kanalisatsiooni eelvooluks on Rohuneeme tee De160 plastist
kanalisatsioonitorustik. Hoonete kanalisatsiooni paisutuskõrguseks loetakse 0,10 m üle tänava kaevuluugi
kõrgusmärgi. Kõik allapoole paisutuskõrgust paigaldatavad reoveeneelud tuleb varustada tagasilöögiklappidega.
4.5 TORUSTIKUD JA MATERJALID
Isevoolse kanalisatsioonitorustikuna tuleb kasutada täisseinalist PVC plastist kanalisatsioonitorud läbimõõduga
De160 (standard EN 1401). Torude rõngasjäikusklass peab olema SN8. BD-tähisega torud sobivad
kasutamiseks hoonete sees, sissevalamiseks ning paigaldamiseks pinnasesse hoonest väljaspool.
4.6 PUMPLA JA KOHTPUHASTID
Käesolevas projektis ei ole ette nähtud.
4.7 KAEVUD
Kanalisatsioonitorustikule on ette nähtud paigaldada teleskoopsed PE kontrollkaevud De400/315. Kaevud tuleb
varustada ujuvate malmluukidega, mille koormustaluvus on 40T liiklusalal ja 25T haljasalal.
Kaevud ehitatakse kõrguse poolest sellistena, et kaevukaant oleks võimalik paigaldada vastavalt projektis antud
maapinna kõrgusele ja kaldega. Kaevude kaaned paigaldatakse kattepinnaga ühele kõrgusele ja samasuguse
kaldega. Kaevude kaane suurus valitakse vastavalt kaevu läbimõõdule.
Kaev peab olema varustatud kõikede tihenditega. Kaevu ja kanalisatsioonitorude ühendamisel kasutatakse
samasugust ühendusviisi nagu kanalisatsioonitorude ühendamisel.
Kanalisatsioonikaevud toestada nii, et põhjavee tõstejõud, pinnasesurve, liikluskoormus või muu ei põhjustaks
deformatsioone ega kahjustaks tihendust.
Torustike asendiplaanidel on esitatud kaevude tsentrite vahelised pikkused.
5 SADEMEVEE KANALISATSIOON
5.1 OLEMASOLEV OLUKORD
Sademevee allikas on hoone katus. Käesoleval ajal kinnistul puuduvad sademevee- ja drenaaži süsteemid.
Vastutav spetsialist: Evelin Anto 8 / 17 20047_TP_VK-3-01_seletuskiri.docx
Töö nr.20047 Elamu – Kesk tee 13, Haabneeme alevik, Viimsi vald, Harju maakond
Välisveevarustus ja -kanalisatsioon. Tööprojekt. 6.05.2020
5.2 PROJEKTEERITUD SADEMEVEEKANALISATSIOON
Sademevee kanalisatsiooni allikaks on hoone katus.
Olemasoleva vihmaveetorude alla on ette nähtud paigaldada sademeveelehtrid, ehitada hoone ümber
sademeveetorustik ning juhtida sademevesi Kesk tee ääres paiknevasse kraavi. Lehtrid ühendada toruga
painduvate käänikute ja kolmikute abil.
Kinnistu torustikud on projekteeritud läbimõõduga De110-160mm PP.
Sademeveetorustike rajamissügavus on üldjuhul piisav ja torustik on kaitstud mehaaniliste ja dünaamiliste
vigastuste eest. Torustiku peale jääva täite paksus on väiksem kui 1 m ja torustik tuleb soojustada.
5.3 ARVUTUSÄRAVOOL
Katuse pindala A=211m2. Sademevee arvutuslik vooluhulk katuselt 2,1 l/s.
Sademevee arvestuslikuks intensiivsuseks on võetud 100 l/s ha.
5.4 TORUSTIKE MATERJAL
Sademeveekanalisatsioon on ette nähtud rajada PP plasttorudest De110...160, rõngasjäikusega SN8 (standard
EN 13476).
5.5 EELVOOL
Sademeveekanalisatsiooni eelvooluks on Kesk tee ääres paiknev kraav.
5.6 KAEVUD
Sademeveekanalisatsioonitorustikule on ette nähtud paigaldada PE-st kontrollkaevud. Kaevud tuleb varustada
ujuvate malmluukidega, mille koormustaluvus on 40T liiklusalal ja 25T haljasalal.
Kontrollkaevud on projekteeritud läbimõõduga De400/315mm.
Kaevud ehitatakse kõrguse poolest sellistena, et kaevukaant oleks võimalik paigaldada vastavalt projektis antud
maapinna kõrgusele ja kaldega. Kaevude kaaned paigaldatakse kattepinnaga ühele kõrgusele ja samasuguse
kaldega. Kaevude kaane suurus valitakse vastavalt kaevu läbimõõdule.
6 PAIGALDUSNÕUDED
Kaevetöödel ja torustiku paigaldamisel tuleb juhinduda RIL77.
Torude paigaldamisel arvestada tootjate poolt etteantud nõudeid ja tehnilisi tingimusi. Tellija võib vajadusel
lisada omapoolseid juhiseid paigaldamiseks.
Kaevamistööd tuleb teha kehtiva korra ja vastavate lubade alusel.
Kõikidele töödele, seadmetele ja materjalidele peab kehtima 24 kuuline garantii.
Enne ehitustööde algust tuleb selgitada kõikide ehitusalal olevate tehnovõrkude asukohad.
Vastutav spetsialist: Evelin Anto 9 / 17 20047_TP_VK-3-01_seletuskiri.docx
Töö nr.20047 Elamu – Kesk tee 13, Haabneeme alevik, Viimsi vald, Harju maakond
Välisveevarustus ja -kanalisatsioon. Tööprojekt. 6.05.2020
Enne paigaldamist tuleb kontrollida, et torudel ja tarvikutel pole kahjustusi. Pärast transportimist ning enne
paigaldamist tuleb torud hoolega puhastada. Kui toru või tihend saab paigaldamise ajal vigastada, siis
vahetatakse see välja. Vigastatud tarvikud tuleb kohe paigalduskohast kõrvaldada.
Toru paigaldamisel talvetingimustes tuleb torud, muhvid, tihendid ja liitmikud enne paigaldamist puhastada
lumest, jääst ja külmunud pinnasest.
Kui paigalduskohas on õhutemperatuur madalam torustike või tarvikute valmistajate poolt soovitatavast
minimaalsest paigaldustemperatuurist, siis paigaldustöid ei tehta. Torusid ei tohi paigaldada jäätunud alusele.
Mahuti paigaldusel ja ankurdamisel järgida tootjapoolseid juhiseid.
Veetorustik
Veetorustik paigaldada sügavusele ~1,8m maapinnast.
Paigaldamise ajaks (ning paigaldustööde katkestuse ajaks) tuleb veetorude otsad sulgeda tihedate
kaitsekorkidega, et vältida mustuse ja võõrkehade sattumist torusse.
Veetorustike paigaldamisel tuleb torustiku külge kinnitada asukoha määramiseks min. 1,5 mm 2 ristlõikega
isoleeritud vaskkaabel, pinnasesse jäävad kaabli jätkud peavad olema veetihedad. Kaabli otsad tuua
veemõõdusõlme ja tänaval kape alla.
Veetoru kohale 0,3m kõrgusele paigaldada sinine märkelint kirjaga “Vesi”.
Kanalisatsioonitorustik
Paigaldatud toru kohale, 0.3m kõrgusele tuleb paigaldada märkelint kirjaga „Kanalisatsioon“.
6.1 TORUSTIKE JA KAEVUDE PAIGALDUS
Torustikud rajatakse lahtisel meetodil.
PE-torude ühendamisel tuleb kasutada mehaanilisi surveliitmikke või elektrikeevisühendusi.
Paigaldatud kanalisatsioonitorustikul peab olema ühtlane kalle.
Kaevu ümbruse täide tehakse mittekülmakerkelisest pinnasest ja vähemalt 0,3 m laiuselt. Tera mõõtmed on
samad kui sama läbimõõduga plastiktoru puhul. Täide pannakse labidaga kaevu ümber ning tihendatakse ca 20
cm kihtide kaupa. Jälgida tuleb pidevalt kaevu vertikaalsust. Tõusutoru (kaevukorpuse) kõrgus on sobiv siis, kui
ülaserv on 30 – 50 cm kaugusel lõplikust maapinnast.
PE-kaev lühendatakse kaevu korpusest osa maha lõigates. Ülemisse otsa paigaldatakse poltidega kinnitatav
teleskooprõngas koos tihenditega. Kui PE-kaev on liiga lühike, siis lisatakse pikem teleskooptoru.
Kanalisatsioonitorustiku rekonstrueerimisel tänavaalal pumbatakse reovett eelmisest kaevust teise töötavasse
kaevu torustikul.
6.2 KAEVIK
Toestamata kaeviku põhja minimaalne laius on 1.2m ja vähemalt 0.4m laiem toru läbimõõdust. Põhjendamatult
laia kaeviku tegemist tuleb vältida, sest sellisel juhul võib algtäite horisontaaltugi andev mõju plasttorule
väheneda.
Vastutav spetsialist: Evelin Anto 10 / 17 20047_TP_VK-3-01_seletuskiri.docx
Töö nr.20047 Elamu – Kesk tee 13, Haabneeme alevik, Viimsi vald, Harju maakond
Välisveevarustus ja -kanalisatsioon. Tööprojekt. 6.05.2020
Kaeviku sügavust määrates peab arvestama, et torustiku alla mahuks vähemalt 150mm paksune tasanduskiht.
Kaeviku nõlvus ja toestamisvajadus määratakse vastavalt vajadusele ja tööohutusnõuetele. Toestamisvajadust
määrates peab arvestama pinnase kandevõimet, pinnasevee taset, kaevesügavust, aastaaega, paigaldamistööde
kestvust, liiklust kaeviku vahetus läheduses, valli tõstetud väljakaevatud pinnase ja mehhanismide mõju.
Töövõtja kindlustab kaevised määral, mis tagab ohutu tööde korraldamise.
Kogu väljakaevatud pinnas, mida kasutatakse tagasitäiteks või muuks otstarbeks, tuleb ladustada kaeviku
vahetus läheduses nii, et see ei takistaks järgnevate tööde tegemist.
Kaevik teha nõlvade püsivuse parandamiseks kalletega. Nõrkades pinnastes tuleb kaeviku põhi kaevata käsitsi
või väiksema mehhanismiga, et vältida aluspinnase rikkumist ning ebaühtlase paksusega aluse kujunemist.
Töötamisel allpool pinnasevee taset kaevikust eemaldatakse vesi.
Torude kaugus kaeviku servadest peab olema vähemalt 400mm.
Olemasolevate kommunikatsioonide ristumisel kaevikuga lähtuda nende valdajate ettekirjutustest ja kehtivatest
normidest. Töö käigus vajalikke ehitisi ja seadmeid kaitstakse või paigutatakse ümber vastavalt projektile ja
nende haldaja antud juhisele. Kui kaevamistöid tehakse olemasolevate kommunikatsioonide kõrval või all,
toestatakse ja kaitstakse need nii, et nad ei liiguks ehitustööde jooksus või neid ei vigastataks.
Varem paigaldatud kaablite, kõrgepingeliinide, torude, seadmete ja tarindite läheduses tuleb kaevetöid teha
nende ehitiste omaniku juhendite kohaselt.
Kaableid peab enne ekskavaatoriga kaevamist vajalikes kohtades käsitsi välja kaevama, et näha kaablite
kulgemise suunda ja sügavust. Ekskavaatoriga kaevamine ei või ilma eelpool mainitud meetmete kasutamist
ulatuda lähemale kui 2m märgistatud kaablitele.
Talvetingimuses ehitamine eeldab kaablite ja torude läheduses kaevamist külmunud pinnase sulatamisega.
Kaeviku lahtihoidmise aeg peab olema nii lühike, kui võimalik. Kaevik tuleb kaevata vahetult enne toru
paigaldamist ja tagasitäide tuleb teha sama tööpäeva lõpuks, jättes vaid kuni 10m pikkuse kaeviku lõigu toru
otsa juures avatuks. Tagasitäiteta toru tuleb kaitsta kukkuvate kivide ja muude võimalike kahjustuste eest.
Kaevikul võib vajadusel olla minimaalseid erinevusi projekteeritavast suunast ja ristlõike kujust. Kaeviku
paiknemine ja sügavus fikseeritakse töö ajal tehtavate kontrollmõõdistuste abil enne tasanduskihi tegemist.
Tuleb vältida liigset kaevamist nii laiusesse kui ka sügavusse. Valmis kaevatud kaevikust eemaldatakse lahtised
kivid.
6.3 TASANDUSKIHT
Kaeviku põhja tehakse tasanduskiht, mille kõrgus toru põhjast mõõdetuna on vähemalt 150mm. Projekti
kohaselt on ette nähtud teha tasanduskiht liivast või peenkillustikust (fr.4-16).
Tasanduskiht tuleb tihendada 90% tihedusastmeni ja tihendamine peab olema tehtud mehhanismidega.
Vastutav spetsialist: Evelin Anto 11 / 17 20047_TP_VK-3-01_seletuskiri.docx
Töö nr.20047 Elamu – Kesk tee 13, Haabneeme alevik, Viimsi vald, Harju maakond
Välisveevarustus ja -kanalisatsioon. Tööprojekt. 6.05.2020
6.4 TORUSTIKE PAIGALDUS JA KAEVIKU TÄIDE
Torustikud paigaldada vastavalt asendiplaanile. Veetorustiku sisend paigaldada hoone vundamendist läbiminekul
hülsis.
Kanalisatsioonitorustiku väljaviigud on ette nähtud teha läbi vundamendi hülsis (läbiviiguhülss).
Hülsi väljast ja seest tihendada vett mitte läbilaskva materjaliga (elastne isolatsioon, nt. vahtkumm). Hülsi pikkus
on 20 mm suurem ehituskonstruktsiooni paksust.
Algtäide
Algtäide toru ümber ja peale teha liivaga, tihendada kuni 90% tihedusasteni.
Enne algtäite tegemist kontrollitakse, et torud on terved ja projekti kohaselt paigaldatud. Kaevikust eemaldatakse
võimalik jää ja lumi. Algtäide paigaldatakse kaevikusse ettevaatlikult, toru mõlemale küljele. Täitmistöö esimene
etapp tehakse käsitsi, et torud ei liiguks oma kohalt ega saaks viga. Algtäidet pannakse torude külgedele nii, et
toru kõrgus ei muutuks.
Algtäide De≥160mm torude korral peab ulatuma vähemalt 300mm toru ülaservast kõrgemale. Sängitusmaterjali
tihendatakse kihiti. Esimene kiht võib ulatuda maksimaalselt poole toruläbimõõdu kõrguseni. Vajadusel võib
torustiku tihendamistööde ajaks täita veega.
Otse torude peal olevat sängitusmaterjali tohib mehhanismidega tihendada alles siis, kui kiht on vähemalt
300mm paksune, teisi tihendusvõtteid kasutades peab kihi paksus olema vähemalt 150mm.
Täitematerjal ei tohi kahjustada torusid ega torude pinnakatet. See ei tohi sisaldada ka aineid, mis võivad
keemiliselt kahjustada torusid või tihendusmaterjali. Külmunud täitematerjali ei tohi kasutada.
Täitematerjali otse autokastist kaevikusse toru peale kallutada ei tohi, sest toru võib paigast ära nihkuda.
Lõpptäide
Lõpliku tagasitäite tegemisele võib asuda pärast seda, kui on korraldatud vajalikud testimised ning nende
tulemused heaks kiidetud.
Kui torustik paigaldatakse väljapoole üldkasutatavaid sõiduteid, siis üldiselt kasutada kaeviku tagasitäitmiseks
mineraalset pinnast.
Sõidutee all asuva kaeviku tagasitäiteks kasutatakse killustikku või ehitusliiva (võib kasutada ka kaevikust
väljakaevatud keskterist liiva), parkla all kasutada dreenivat täitematerjali liiv/kruus. Lõplik täitmine
üldkasutatavate teede all tehakse tihendamiseks sobiliku mineraalse pinnasega, antud liivaga või killustikuga.
Liivas tohib olla kõige suurem kivide või kamakate lubatud läbimõõt 2/3 ühe tihendatava kihi paksusest. Täiend
tihendatakse kihtide kaupa 95%-se tihedusastmeni (teede ja platside all 98%). Kaevude ümber tehakse lõplik
kaeviku täitmine nende välispinnast vähemalt 0,5 m kaugusele sõreda mittekülmuva materjaliga.
Tagasitäite tegemisel tuleb pinnas 25 cm paksuste kihtide kaupa tihendada.
Kaevik tuleb täita sellise kõrguseni, et täide pärast tihendamist jääks planeeritud kõrgusele või maapinnaga ühele
tasemele.
Vastutav spetsialist: Evelin Anto 12 / 17 20047_TP_VK-3-01_seletuskiri.docx
Töö nr.20047 Elamu – Kesk tee 13, Haabneeme alevik, Viimsi vald, Harju maakond
Välisveevarustus ja -kanalisatsioon. Tööprojekt. 6.05.2020
Keelatud on kasutada tagasitäitena külmunud materjale või materjale, mis sisaldavad jääd. Täidet ei tohi hoida
külmunud maapinnal. Iga kihti, täidet või aseainet tuleb niisutada või kuivatada kuni ühtlustatud
niiskussisalduseni.
Kaeviku täisajamine ilma Tellija loata on keelatud. Pärast tagasitäite lõppu peab ehitaja näitama täidetud pinnad
ette Tellijale ja pärast sellelt vastava heakskiidu saamist tohib jätkata edasiste töödega.
6.5 KÜLMUMISKAITSE, SOOJUSISOLATSIOON
Veetorustiku rajamissügavus on 1,8m planeeritavast maapinnast. Lisa külmumiskaitset ei ole ette nähtud.
Kanalisatsioonitorustikud, mille lagi on kõrgemal kui 1,2 m ja sademeeveetorustiku, mille lagi on kõrgemal kui 1
m tuleb soojustada koos (koos kaevu tõusutoruga) maa sisse paigaldamiseks ettenähtud vahtpolüsterool
koorikuga ja plaadiga.
6.6 TORUSTIKE TOESTUS
Plasttorude paigaldamisel lähtuda juhendist “Maa sisse ja vette paigaldatavad plasttorud. Paigaldusjuhend. (RIL
77)”.
7 LIKVIDEERITAVAD RAJATISED
Olemasolevad kasutusest välja jäävad vee- ja kanalisatsioonitorustikud, on ette nähtud likvideerida. Torustiku
likvideerimisel kaevamisega lõhkuda torulagi ja täita toru liivaga. Juhul kui ei ole otstarbekas olemasolevat toru
lahti kaevata, peab likvideeritava toru täitma vähemalt tee aluses lõigus vahtbetooniga. Haljasalal asuvatel
objektidel betoneeritakse toruotsad.
Kanalisatsioonikaevude likvideerimisel teisaldatakse kaevu lagi, kaev täidetakse liivaga ja tihendatakse.
Torustiku likvideerimine eraomaniku kinnistul kooskõlastada täiendavalt kinnistu omanikuga.
8 KESKKONNAKAITSE
Ehitusjäätmed
Keskkonnakaitse eest ehitusplatsil ja sellega vahetult piirnevatel aladel vastutab Ehituse Töövõtja vastavalt Eesti
Vabariigis kehtivaile seadustele ja nõuetele. Ehituse käigus tekkivad ehitusjäätmed (pinnas, betoondetailid, kivid,
asfaldijäägid) kõrvaldatakse vastavalt keskkonnaorganite ettekirjutustele ja ladustuskoha kasutuseeskirjadele.
Kaitset vajavate puude juures teha kaevetööd käsitsi.
Haljastuse taastamine
Kasvupinnas tuleb kujundada ilma järskude üleminekuteta ja saavutades projektis ettenähtud pinnakõrgused.
Vajadusel tuleb vajaliku kasvukihi paksuse säilitamiseks teostada lokaalseid kaevetöid. Alad tuleb ette
valmistada pehme pinnasega katmiseks.
Vastutav spetsialist: Evelin Anto 13 / 17 20047_TP_VK-3-01_seletuskiri.docx
Töö nr.20047 Elamu – Kesk tee 13, Haabneeme alevik, Viimsi vald, Harju maakond
Välisveevarustus ja -kanalisatsioon. Tööprojekt. 6.05.2020
9 KVALITEEDI- JA KONTROLLINÕUDED EHITAJALE
9.1 ÜLDNÕUDED
Töövõtjale on kohustuslikud kõik Eesti Vabariigis kehtivad ehitamist puudutavad nõuded, nagu seadused,
määrused, ministeeriumide otsused samuti tuletõrje-, töökaitse- ja politseiametkondade suunised ja määrused.
Eriküsimused peab töövõtja kooskõlastama tellija ja ametivõimudega.
Töövõtja väljastab vajaliku info vastavalt kokkulepitud tööde ajagraafikule ja oma hangete kohale toimetamise
aegadele õigeaegselt teistele töövõtjatele, tellijale ja santehniliste tööde järelvalvajale.
Juhul kui töövõtja kasutab seletuskirjas ja joonistes määratud seadmete ja materjalide asemel muid vastavaid
seadmeid ja materjale, peavad need oma suuruselt, asukohalt, tööpõhimõttelt ja tehnilistelt karakteristikutelt
vastama töövõtu-dokumentides määratud seadmetele ja materjalide.
Nende seadmete ja materjalide valimisele on vajalik tellija ja järelvalvaja kirjalik nõusolek enne kõnealuste
seadmete ja materjalide hankimist. Valiku õigsuse eest vastutab vaid töövõtja.
Juhul kui materjali ei ole määratud, valib töövõtja otstarbekohase materjali lähtudes eri seadmetele esitatud
nõuetest võttes arvesse näit. Transporditavat ainet ja keskkonna tingimusi. Valikut tehes tuleb pöörata
tähelepanu eriti teineteisega ühendatud eri materjalide vahelise korrosiooni vältimisele.
Töövõtja on kohustatud kontrollima ehitusplatsil kõik ehitustarindite, seadmete, jm. Töövõtuga seonduvad
mõõdud. Töövõtja on kohustatud kogu teostamisele kuuluva projektdokumentatsiooni nii põhjalikult läbi
vaatama, et nendes esinevad võimalikud vastuolud saaks lahendada enne tööde teostamise algust. Kui
vastuolud on sellised, mida töövõtja oleks pidanud märkama ja tellijale teatama, ja see põhjustab tööde
hilinemise või liigsed kulutused, vastutab selle eest töövõtja.
Üleandmisdokumendid
1. Isevoolse kanalisatsioonitorustiku katsetamise protokoll.
2. Vajaduse korral, kui on tekkinud kahtlus, et torustike paigaldus ei vasta RIL 77 nõuetele, teha
kaamerauuringud.
3. Veetorustiku katsetamise protokoll. Katsetamine teha standardi SFS 3115 järgi.
4. Teha teostusjoonised, mis anda tellijale üle digitaalsel kujul ja paberkandjal.
5. Anda tellijale üle kõigi kasutatud materjalide ja seadmete sertifikaadid ja garantiidokumendid.
9.2 HÜDRAULILISED KATSETUSED
Hüdrauliline surveproov tehakse kõigile ehitatud veesurvetorudele, mille pikkus on vähemalt 10m.
Veetorustiku surveproov
Veetorustikule teha surveproov vastavalt standardile SFS 3115, EN-805. Proov viiakse läbi vastavalt toru
nimirõhule (PN10).
Surveproovi ei tohi teostada vastu olemasolevat kinnist, toestamata sulgelementi.
Enne surveproovi täita torustik veega ja jätta seisma võrgu survel vähemalt 24 tunniks.
Vastutav spetsialist: Evelin Anto 14 / 17 20047_TP_VK-3-01_seletuskiri.docx
Töö nr.20047 Elamu – Kesk tee 13, Haabneeme alevik, Viimsi vald, Harju maakond
Välisveevarustus ja -kanalisatsioon. Tööprojekt. 6.05.2020
Surveproovi alustades tõsta rõhk torus 1,3 kordse toru nominaalse rõhuni ja lasta torul survestatuna
seista minimaalselt 2 tundi tagamaks toru ja ühenduste venimise.
Seejärel vähendada rõhku toru nominaalrõhuni. Jälgida, et 30 minuti jooksul rõhk torus ei langeks üle
0,2 bari. Peale tulemuse fikseerimist vähendada rõhk võrgu surveni.
Pärast surveproovi teostab ehitaja torustiku läbipesu ja tellib vee analüüsi.
Veetorustiku pesemine
Enne pesemist peab torustiku algtäide olema tehtud ja toru toestatud nii, et ta peab vastu pesemisel ja
surveproovil tekkivatele koormustele. Pesemiseks kasutatakse olemasoleva veevõrgu vett. Pesemiseks
kasutatud vesi juhitakse kanalisatsiooni võrku.
Läbipesu tehakse 10...15 minuti jooksul maksimaalse vooga, sõltuvalt torustiku läbimõõdust ja pikkusest.
Visuaalselt hinnatakse, kas väljavoolav vesi on täiesti selge, seejärel võib läbipesemise lõpetada.
Kanalisatsiooni tiheduse kontroll
Kõigile isevoolsetele torustikele tehakse tihedusproov veega, näiteks vastavalt standardile SFS 3113 või temaga
võrdsele standardile.
Tihedusproov tehakse korraga ühe kaevelõigu ulatuses kui kaevik on täidetud.
Selle meetodiga on võimalik teha eelkontroll ka lahtisel torustiku osal. Seda võib teha ka osaliselt täidetud
kaevise korral nii, et liitekohad on jäetud katmata võimaliku lekkekoha avastamiseks ja parandamiseks.
Enne proovi puhastatakse torustik mullast ja muudest osistest. Torustik, kus proovi tehakse, suletakse
troppidega. Tropid tuleb asetada nii, et nad proovi ajal lahti ei tuleks.
Kui torustikul on harusid, suletakse ka need troppidega tihedusproovi ajaks.
Kui proovi tulemus pole vastuvõetav, tuleb lekkekoht avastada ja parandada.
Muud testid
Toruehituse tööde kvaliteeti kontrollitakse videokaameraga.
Kui plasttorustiku visuaalsel vaatlusel on põhjust kahelda, et toru on deformeeritud ja läbimõõt on mõnes
suunas vähenenud, siis kontrollitakse toru kuju puust või plastmassist tehtud silindri, mille otsad on ümardunud
ja pikkus umbes 1,5-kordne toru läbimõõt, torust läbitõmbamisega. Silindri läbimõõt peab olema 92%
ümmarguse toru siseläbimõõdust. Toru deformatsioon ei ületa lubatud väärtust, kui silinder tuleb takistamatult
läbi toru. Alternatiivselt võidakse toru deformatsiooni ulatust mõõta spetsiaalse mõõteseadmega või kasutada
videokaamera abil saadud andmeid.
Vastutav spetsialist: Evelin Anto 15 / 17 20047_TP_VK-3-01_seletuskiri.docx
Töö nr.20047 Elamu – Kesk tee 13, Haabneeme alevik, Viimsi vald, Harju maakond
Välisveevarustus ja -kanalisatsioon. Tööprojekt. 6.05.2020
10 PÕHIMATERJALIDE LOETELU
POS. TOODE MÕÕT, mm TEHN.NÄITAJAD KOGUS ÜHIK
VEEVARUSTUS
1 Veesurvetoru 32X3,0 PE100, PN16 24 m
2 Elekterkeevispoogen 32x45° 2 tk
3 Elekterkeevispoogen 32x45° 2 tk
4 Märkelint „VESI“ ja traat 24 m
KANALISATSIOON
1 Kanalisatsioonitoru 160 PVC SN8 25 m
Kanalisatsioonikaev, teleskoopne,
2 malmkaanega 40t 400/315 PE 2 kompl.
3 Ühendus olemasoleva kaevuga 1 kompl.
4 Toruhülss 1 tk
5 Märkelint „KANALISATSIOON“ 25 m
SADEMEVEEKANALISATSIOON
1 Sademeveekanalisatsioonitoru 110 PP SN8 32 m
2 Sademeveekanalisatsioonitoru 160 PP SN8 23 m
3 Painduv kolmik 110 PE SN8 1 tk
4 Painduv käänik 0˚-90˚ 110 PE SN8 2 tk
5 Vihmaveelehter 269/110 PP SN8 4 tk
7 Sademeveekaev, malmkaanega 25t 400/315 PE 2 kompl.
8 Märkelint „KANALISATSIOON“ 55 m
Koostas: Evelin Anto
/allkirjastatud digitaalselt/
Vastutav spetsialist: Evelin Anto 16 / 17 20047_TP_VK-3-01_seletuskiri.docx
Töö nr.20047 Elamu – Kesk tee 13, Haabneeme alevik, Viimsi vald, Harju maakond
Välisveevarustus ja -kanalisatsioon. Tööprojekt. 6.05.2020
JOONISTE NIMISTU
JOONISE NIMETUS JOONISE KUUPÄEV MÕÕTKAVA
NR
Vee- ja kanalisatsioonitorustike asendiplaan VK-4-01 08.05.2020 M 1:500
1.korruse plaan. Veemõõdusõlme asukoht VK-5-01 08.05.2020 M 1:100
Vee- ja kanalisatsioonitorustike pikiprofiilid VK-6-01 08.05.2020 1:500, 1:50
Sademeveetorustike pikiprofiilid VK-6-02 08.05.2020 1:500, 1:50
Sademevee- ja kanalisatsioonikaevude skeemid VK-7-01 08.05.2020 -
Veemõõdusõlme tüüpjoonis VK-7-02 08.05.2020 -
Vastutav spetsialist: Evelin Anto 17 / 17 20047_TP_VK-3-01_seletuskiri.docx
Kinnistu piir
E
Projekteeritud hoone
PK
V11 Projekteeritud kinnistu veetorustik
K11 K11 Projekteeritud kinnistu kanalisatsioonitorustik
K21 Projekteeritud kinnistu sademeveetorustik
V V Olemasolev veetorustik
K K Olemasolev kanalisatsioon
SK Olemasolev sademeveekanalisatsioon
D D
S S Olemasolev sidekanalisatsioon
Kanalisatsiooni
liitumispunkt Olemasolev madalpingekaabel
X
K11111 X Veevarustuse liitumispunkt
VK2
X
X
K21
PK
K21
PEH
De 32 mm
m
H
PE
m
PE
H
2
e3
D
e3
D
ELEKTERKEEVISPOOGEN
2
m
m
Reg. nr: 11124774 OBJEKTI NIMETUS
K=0,95 Laki tn. 5, 10621 Tallinn
ELEKTERKEEVISPOOGEN
De 32 mm
liiklusalal K=0,98 web: www.sma.ee
e-mail:
[email protected] TELLIJA OBJEKTI AADRESS
SIRKEL&MALL
PEH
PEH tel:+372 6 555 480
tihedusaste 90% ARHITEKTUUR JA PROJEKTEERIMINE fax: +372 6 100 540
De 32 mm Projekteerimine: EEP 000543 JOONISE NIMETUS
0,3m
mehaanilise tihendamiseta OL.OLEV MAAKRAAN
DN 25 mm De 32
PROJEKTIJUHT
De 32 mm
min 0,4m
KONTROLLIJA
PEH
min 1,2m
liiv min 150mm projekt. toru PROJEKTEERIJA STAADIUM
tasandatav kiht
tihedusaste 90% JOONESTAS
Viimsi Vallavalitsus
[email protected] Teie 26.05.2020
Nelgi tee 1
Viimsi alevik, Viimsi vald, 74001, Meie 08.06.2020 nr 15-2/20/25063-2
Harju maakond
Üksikelamu ning selle välisveevarustuse ja
kanalisatsiooni ehitusprojekti
kooskõlastamine riigitee nr 11251
kaitsevööndis
Olete taotlenud Maanteeameti ehitusseadustiku (EhS) § 70 lg 3 kohast nõusolekut üksikelamu ning
selle välisveevarustuse ja -kanalisatsiooni ehitusprojektile riigitee nr 11251 kaitsevööndisse km
1,02. Projektidega kavandatakse üksikelamu ning selle välisveevarustuse ja -kanalisatsiooni
ehitamist.
Võttes aluseks EhS § 19, § 24, § 70, § 71, § 92 lg 6 ja lg 10, § 97 ning Maanteeameti põhimääruse,
anname nõusoleku riigitee kaitsevööndis kehtivatest piirangutest kõrvale kaldumiseks vastavalt
Smart Arch OÜ tööle nr E-20-02 „Kesk tee 13 elamu eelprojekt“ ja Sirkel & Mall OÜ tööle nr
20047 „Elamu Kesk tee 13 välisveevarustus ja -kanalisatsioon“. Nõusolek tugineb asjaolule, et
projekti realiseerimisest huvitatud isik ja tehnovõrgu omanik on nõus arvestama Maanteeameti
poolt esitatud ettepanekute ja järgmiste nõuetega:
1. Vastavalt EhS § 72 lg 2 on tee kaitsevööndi maa kinnisasja omanik kohustatud lubama
kõrvaldada nähtavust piirava istandiku, puu, põõsa või liiklusele ohtliku rajatise, mistõttu
ehitiste ehitamisel peavad olema tagatud majandus- ja taristuministri 5.08.2015 määruse nr
106 „Tee projekteerimise normid“ lisas „Maanteede projekteerimisnormid“ toodud nõuded
külgnähtavuse ja ristumiskoha nähtavuskolmnurga kohta.
2. Ehitatav tehnovõrk peab vastama ehitusseadustikust tulenevatele normidele ning ei tohi
ehituse ajal ega kasutusele võtu järgselt seada takistusi liiklusele, tee ja teerajatiste teehoiule
(korrashoiule) või sademe- ja pinnasevete ärajuhtimisele riigitee transpordimaalt ja
kaitsevööndist.
3. EhS § 70 lg 2 p 1 kohaselt ei tohi ehitus- ega muu tegevus kaitsevööndis ohustada riigiteed ega
selle korrakohast kasutamist. Juhul kui tööde tegemine võib riigiteel liiklejaid ohustada
mistahes viisil, tuleb ohutuse tagamisel lähtuda liiklusseaduse § 71 lõike 4 alusel kehtestatud
majandus- ja taristuministri 13.07.2018 määrusest nr 43 „Nõuded ajutisele
liikluskorraldusele“. Riigiteel liikluskorralduse ajutiseks muutmiseks on vajalik
liikluskorralduse projekt, millele on saadud tee omaniku nõusolek.
4. Riigitee ja selle rajatiste kahjustamine on keelatud; ehitustehnikaga manööverdamine riigiteel
ja riigitee mulde nõlvadel ei ole lubatud. Materjalide veod korraldada olemasolevate
juurdepääsuteede kaudu.
5. Projekti realiseerimisel tuleb vältida pinnase (muda, kruus jms) kandumist riigiteele. Vajadusel
näha ette vastavaid leevendavaid meetmeid, näiteks sõidukite puhastamine enne riigiteele
sõitmist.
Teelise 4 / 10916 Tallinn / 6119 300 / Registrikood 70001490 / www.mnt.ee /
[email protected], 620 1200 (kliendiinfo) /
[email protected]; 611 9300 (teedealased küsimused)
6. Töövõtjal näha ette paigaldustöödega rikutud maa-ala korrastamine ning kahjustatud
teerajatiste taastamine.
7. Maanteeamet ei võta kohustusi projektiga seotud rajatiste väljaehitamiseks.
Järelevalvet esitatud nõuete täitmise üle riigitee kaitsevööndi ulatuses teostab Maanteeamet
ehitusseadustikus kehtestatud korras.
Käesolev nõusolek kehtib kaks aastat.
Lugupidamisega
(allkirjastatud digitaalselt)
Tiit Harjak
juhtivspetsialist
taristu teenuste osakond
Lisad: projektide asendiplaanid ja seletuskirjad
Ave Voolaid
58505568
[email protected]
2 (2)